Federal contract award

W912QR23C0008

RENOVATE/REPAIR BUILDING 10262, PHASE 1

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW072 ENDIST LOUISVILLE
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AZ — REPAIR OR ALTERATION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$127.3M
Current contract value$127.3M
Potential contract value / ceiling$127.3M
Start dateMay 9, 2023
Current end dateApr 16, 2027
Potential end dateApr 16, 2027
Latest award activityMay 13, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 28 of 28 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 9, 2026A00017$257.0KAFMC HEADQUARTERS PH1
May 13, 2026P00010$1.6MAFMC HEADQUARTERS PH1
Apr 13, 2026A00016$448.7KAFMC HEADQUARTERS PH1
Mar 31, 2026P00009$1.3MCR 0077,0087,0091,0094,0103,0106,0119
Feb 10, 2026P00008$679.0KCHANGE REQUEST 0031, DOOR STANDARDIZATION CAC UCR
Sep 9, 2025A00015$12.8KCR 116-1 MISSING COLUMN REPLACEMENT, PART I NTP
Sep 8, 2025A00014$255.6KCR 67 EXTERIOR DEMO DIFFERING SITE CR 81 WATER SERVICE LINE DEMOLITION CR 92 NW ROOF REPAIRS
Aug 21, 2025A00013$434.0KCR35-FIRE DAMPERS CR40 EXT ELEV CONDITIONS CR43 N205 COM RELOC CR47 AHU ELEC REV RTU PLTFORM CR59 EXST STEEL BRAC CR60 LV2 TEMP BACKBONE CR61 PK SPACE UCR CR62 STEEL PLTS FRP CR64 PENTHSE CLERESTORY STRUCT CR72 RAF COMM CR73 CMU DEMO CR 78 COL WRAPS
Aug 13, 2025A00012$497.9KCR 014 STC RATINGS CR 015 10264 OH DOOR UCR CR 037 REROUTE EXISTING AHU OA DUCTWORK CR 052 EAST EXISTING OA INTAKE CR 058 EXTERIOR DEMO EXISTING CONDITIONS
Aug 4, 2025A00011$36.0KCR 0076 CARPET UCR
Aug 4, 2025P00007$62.2KCR 054-1 AAFES & CHAPLAIN UCR, PART I NTP REVISE CASEWORK AND ADD WALLS PER USER REQUEST RENOVATE/REPAIR BUILDING 10262, PHASE 1
Jul 30, 2025A00010$426.0KCR011 EXISTING TUNNEL LOCATIONS CR025 CONCEALED PIPES LOADING DOCK CR042 RELOC TRANSFORMER PAD WTRPRFING CR 051, STR 6 CRACK/VOIDS CR056 UNDGRD CONCRETE STRUCTURE CR063 LVL 1 FLOOR INFILLS CR082 L2 EAST BUMPOUT RPRS CR088 EXPANS JOINT FLR TRANSITION
Mar 31, 2025P00006$150.0KEXERCISING OPTION 1 IN THE AMOUNT OF $150,000.00 LEAVING SIX (6) ITERATIONS REMAINING.
Dec 27, 2024P00005$659.0KEXERCISING OPTION 5 IN THE AMOUNT OF $659,000.
Dec 4, 2024A00009$132.9KCR 026 STAIRWELL SPRINKLER MODIFICATIONS CR 0033 CONSTRUCTION BARRIER ASSEMBLIES CR 0045 CURTAINWALL ASSEMBLY MCP CR 0050 COMM DEMO S106 & S212 BUILDING 10262, PHASE 1
Nov 20, 2024A00008$365.7KCR 19 DELETE LIGHT TUNING CR 24 LOADING DOCK SPRINKLER COVERAGE CR 29 STEEL PLATES FOR FRP CR 32 MECH PIPING & DUCT RECONFIGURATIONS CR 36 SARRIS/CORONA POWER REFEED CR 38 ELEV 3 & STAIR 10 EXISTING STEEL CR 41 BASEMENT MEP EXISTING CONDITIONS
Oct 15, 2024A00007$-480.0KCR 010 PROTECTIVE ENCLOSURES RENOVATE/REPAIR BUILDING 10262, PHASE 1
Sep 30, 2024P00004$1.1MCR 018 STEAM TUNNEL ROAD SECTIONS RENOVATE/REPAIR BUILDING 10262, PHASE 1
Sep 11, 2024A00006$-52.1KCR 004 ARC RESISTANT SWITCHGEAR CR 0023 PAINTING PIPE ABOVE SUSPENDED CEILNGS RENOVATE/REPAIR BUILDING 10262, PHASE 1
Jul 31, 2024A00005$77.0KCR 006 REMOVE TECTUM FOR WALL PARTITIONS CR 0030 EXTERIOR MISCELLANEOUS DEMOLITION RENOVATE/REPAIR BUILDING 10262, PHASE 1
Jul 8, 2024A00004$8.6KCR 008 CRAC UNIT CR 0028 PLUMBING RECONFIGURATIONS NAD MECH DEMO CR 0020 CORNER AND END GUARDS
Jun 18, 2024A00003$482.9KCR 07 LEVEL 1 MISC DEMO CR 016 LEVEL 2 MISC DEMO CR 017 ELECTRICAL RECONFIGURATIONS CR 021 BUCKEYE CONF ROOM DUCTWORK CR 022 COMM RECONFIGURATIONS RENOVATE REPAIR BUILDING 10262, PHASE 1
Jun 11, 2024A00002$-358.5KCR 009 CONSTRUCTION SITE CHANGES RENOVATE REPAIR BUILDING 10262, PHASE 1
Sep 30, 2023P00003$1.4MOPTION MOD - RENOVATE/REPAIR BUILDING 10262, PHASE 1
Sep 12, 2023A00001$0CR 002 MOVEMENT SUPPORT DELAYS RENOVATE/REPAIR BUILDING 10262, PHASE 1
Aug 31, 2023P00002$605.4KOPTIONS 1,2,3 & 4 EXERCISED ONE (1) TIME. (CLINS 6,7,8 & 9)
Jun 22, 2023P00001$0RENOVATE/REPAIR BUILDING 10262, PHASE 1 ISSUANCE OF ADMINISTRATIVE NOTICE TO PROCEED
May 25, 20230$116.6MRENOVATE/REPAIR BUILDING 10262, PHASE 1

Estimated positioning window

Nov 1, 2026 – Jan 30, 2027

Recompete signal:
75/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 75/100. Available recorded signals: 70 points.

Contract end 2027-04-16 (166 days from calculation)
+35 points
3 historical awards in this buyer and category group
+10 points
28 recorded award transactions
+10 points
Latest award action: 2026-05-13
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-11-01 10:17:53.997580+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Nov 1, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.