W912QR23F0438
DESIGN-BID-BUILD CONSTRUCTION OF A NEW SINGLE STORY ADMINISTRATION OFFICE FOR THE AIR FORCE RESERVE CENTER INTELLIGENCE GROUP AND THREE SQUADRONS AT JOINT BASE LANGLEY- EUSTIS AFB, VIRGINIA.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W072 ENDIST LOUISVILLE |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Y1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | W912QR21D0060 |
| Set-aside | SMALL BUSINESS SET ASIDE - TOTAL |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $14.2M |
| Current contract value | $14.2M |
| Potential contract value / ceiling | $14.3M |
| Start date | Oct 25, 2023 |
| Current end date | Oct 4, 2025 |
| Potential end date | Oct 4, 2025 |
| Latest award activity | May 14, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 16 of 16 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 14, 2026 | A00012 | $23.0K | JOINT BASE LANGLEY-EUSTIS, VA - AFRC INTELLIGENCE GROUP FACILITY (MCAFR PN MUHJ 18-3001) (P2# 480589) |
| Apr 13, 2026 | A00011 | $44.5K | CR 00016 UNFORESEEN CONCRETE - UTILITIES |
| Mar 25, 2026 | A00010 | $19.6K | CR 00017 ELECTRICAL CHANGES - VARIOUS RFIS |
| Mar 12, 2026 | A00009 | $0 | WEATHER TIME EXT. JAN 25 - DEC 25 |
| Dec 4, 2025 | A00008 | $5.6K | REFERENCE NO. R00011 CR15 SOPR ROOM DRYWALL |
| Sep 15, 2025 | A00007 | $186.2K | CR 13 RFI-0066 TRANSPORT PFAS-PFOS SOIL TO K & O LANDFILL |
| Apr 28, 2025 | A00006 | $0 | CR 10 REA-TIME DIG & LAYDOWN PERMIT CR 11 WEATHER TIME EXTENSION DEC 23 - DEC 24 |
| Apr 7, 2025 | A00005 | $0 | CR 05, AIR SHOW TIME EXT |
| Feb 26, 2025 | A00004 | $-24.9K | CR 08, DELETE SWITCH GEAR |
| Dec 23, 2024 | A00003 | $77.8K | CR M02 EXTERIOR MECHANICAL FENCE CR 06 REVISED SANITARY PIPING |
| Nov 1, 2024 | A00002 | $24.6K | CR: 00007 UNFORESEEN CONCRETE - (RFI-0044) |
| Aug 23, 2024 | A00001 | $80.3K | CR: 00004 UNFORESEEN CONCRETE (RFI-0032) |
| May 30, 2024 | P00003 | $0 | ADMINISTRATIVE MODIFICATION TO INCORPORATE DEFENSE PRIORITY CLAUSE. |
| May 24, 2024 | P00002 | $592.5K | EXERCISE OPTION 1 FOR FURNITURE, FIXTURES, AND EQUIPMENT |
| Nov 28, 2023 | P00001 | $0 | ADMINISTRATIVE NOTICE TO PROCEED |
| Sep 27, 2023 | 0 | $13.2M | DESIGN-BID-BUILD CONSTRUCTION OF A NEW SINGLE STORY ADMINISTRATION OFFICE FOR THE AIR FORCE RESERVE CENTER INTELLIGENCE GROUP AND THREE SQUADRONS AT JOINT BASE LANGLEY- EUSTIS AFB, VIRGINIA. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.