Federal contract award

W912QR24C0003

DESIGN/BID/BUILD CONSTRUCTION OF THE COLLECTIVE TRAINING ENLISTED BARRACKS EAST AT FORT MCCOY, WISCONSIN.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW071 ENDIST OMAHA
NAICS236220 — Commercial and Institutional Building Construction
PSCY1FC — CONSTRUCTION OF TROOP HOUSING FACILITIES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$27.7M
Current contract value$27.7M
Potential contract value / ceiling$27.7M
Start dateFeb 15, 2024
Current end dateApr 24, 2026
Potential end dateApr 24, 2026
Latest award activityJun 12, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 19 of 19 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 12, 2026A00015$4.2KCONSTRUCT A FOUR-STORY COLLECTIVE TRAINING ENLISTED BARRACKS FOR MAJOR EXERCISES, ANNUAL TRAINING, BATTLE ASSEMBLY, AND MOBILIZATION TRAINING AT FORT MCCOY, WI TO HOUSE 400-SOLDIERS APPROXIMATELY 60,000 SF.
Jun 5, 2026A00014$20.3KCONSTRUCT A FOUR-STORY COLLECTIVE TRAINING ENLISTED BARRACKS FOR MAJOR EXERCISES, ANNUAL TRAINING, BATTLE ASSEMBLY, AND MOBILIZATION TRAINING AT FORT MCCOY, WI TO HOUSE 400-SOLDIERS APPROXIMATELY 60,000 SF.
May 6, 2026A00013$0CONSTRUCT A FOUR-STORY COLLECTIVE TRAINING ENLISTED BARRACKS FOR MAJOR EXERCISES, ANNUAL TRAINING, BATTLE ASSEMBLY, AND MOBILIZATION TRAINING AT FORT MCCOY, WI TO HOUSE 400-SOLDIERS APPROXIMATELY 60,000 SF.
Mar 6, 2026A00012$14.4KCONSTRUCT A FOUR-STORY COLLECTIVE TRAINING ENLISTED BARRACKS FOR MAJOR EXERCISES, ANNUAL TRAINING, BATTLE ASSEMBLY, AND MOBILIZATION TRAINING AT FORT MCCOY, WI TO HOUSE 400-SOLDIERS APPROXIMATELY 60,000 SF.
Mar 2, 2026A00011$28.3KCONSTRUCT A FOUR-STORY COLLECTIVE TRAINING ENLISTED BARRACKS FOR MAJOR EXERCISES, ANNUAL TRAINING, BATTLE ASSEMBLY, AND MOBILIZATION TRAINING AT FORT MCCOY, WI TO HOUSE 400-SOLDIERS APPROXIMATELY 60,000 SF.
Feb 5, 2026A00010$0CONSTRUCT A FOUR-STORY COLLECTIVE TRAINING ENLISTED BARRACKS FOR MAJOR EXERCISES, ANNUAL TRAINING, BATTLE ASSEMBLY, AND MOBILIZATION TRAINING AT FORT MCCOY, WI TO HOUSE 400-SOLDIERS APPROXIMATELY 60,000 SF.
Dec 30, 2025A00009$42.0KREFERENCE NO. R00013, CR0013-1 METAL DOORS NTE (NOT TO EXCEED) PART I INCREASE: $42,000.00 - CONTRACT REQUIRED COMPLETION DATE: 24 APRIL 2026 - CALENDAR DAY TIME EXTENSION: NONE
Dec 18, 2025A00008$10.2KR00012, SENIOR COMMISSIONING CHANGES THE FOLLOWING HAVE BEEN ADDED BY FULL TEXT:PROVIDE ALL LABOR, EQUIPMENT, AND MATERIALS TO PERFORM THE FOLLOWING SCOPE OF WORK, IDENTIFIED AS CHANGE REQUEST:
Aug 6, 2025A00007$8.5KCR 008 COMMUNICATIONS PEDESTAL -REPLACE EXISTING COMM PEDESTAL WITH NEW HANDHOLE BARRACKS BUILDING
Jun 5, 2025A00006$4.0KCR 009 FIRE DAMPERS -INSTALL FIRE DAMPERS PRIMARY FACILITIES BARRACKS BUILDING
Apr 22, 2025A00005$7.6KCR 008 SPLIT SYSTEM A/C UNIT SIZE CHANGES BARRACKS BUILDING
Apr 17, 2025P00003$48.5KEXERCISING OPTIONAL BID ITEM FOR BONA FIDE NEED OPERATIONS AND MAINTENANCE, ARMY RESERVE FUNDED EQUIPMENT FOR CONTRACT W912QR24C0003 FOR CONSTRUCTION OF THE COLLECTIVE TRAINING ENLISTED BARRACKS EAST AT FT. MCCOY, WISCONSIN.
Apr 11, 2025P00002$0THE PURPOSE OF THIS MODIFICATION IS TO IMPLEMENT EXECUTIVE ORDER 14173
Feb 21, 2025A00004$32.0KCR 005 ARC FAULT CIRCUIT INTERRUPTER CHANGES BARRACKS BUILDING
Feb 19, 2025A00003$39.2KCR 004 SECONDARY SERVICE ENTRANCE FEED CHANGES BARRACKS BUILDING
Jan 28, 2025A00002$-6.7KCR 002 REFLECTED CEILING PLAN CHANGES PRIMARY FACILITIES BARRACKS BUILDING
Jan 16, 2025A00001$9.9KCR 001 SITE UTILITY CHANGES PRIMARY FACILITIES BARRACKS BUILDING
Mar 5, 2024P00001$0ISSUE ADMINISTRATIVE NOTICE TO PROCEED FOR THE DESIGN-BID-BUILD CONSTRUCTION OF THE COLLECTIVE TRAINING ENLISTED BARRACKS EAST AT FORT MCCOY, WISCONSIN.
Feb 15, 20240$27.2MDESIGN/BID/BUILD CONSTRUCTION OF THE COLLECTIVE TRAINING ENLISTED BARRACKS EAST AT FORT MCCOY, WISCONSIN.