W912UM22C0009
SMYU21-1204, REPAIR SEWER FORCE MAIN LINE, OSAN AIR BASE, KOREA
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | W2SN ENDIST FAR EAST |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2JZ — REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $4.7M |
| Current contract value | $4.7M |
| Potential contract value / ceiling | $4.7M |
| Start date | Sep 26, 2022 |
| Current end date | Feb 13, 2026 |
| Potential end date | Feb 13, 2026 |
| Latest award activity | Aug 18, 2025 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 18, 2025 | A00005 | $41.1K | SMYU21-1204, C.I #CR007, REPLACE FLOW METER |
| Apr 4, 2025 | A00004 | $195.5K | C.I #CR005, REMAIN TEMPORARY SEWER PUMP C.I #CR006, TIME EXTENSION FOR VFD APPROVAL DELAY #2 SMYU21-1204 |
| Sep 13, 2024 | A00003 | $0 | C.I #CRO04, TIME EXTENSION FOR VFD APPROVAL DELAY #1 |
| Apr 15, 2024 | A00002 | $0 | C.I #CRO03, TIME EXTENSION OFF-SHORE MATERIAL DELAY |
| Apr 2, 2024 | A00001 | $0 | C.I #CRO02, TIME EXTENSION FOR SUSPENSIONS OF WORK |
| Sep 26, 2022 | 0 | $4.5M | SMYU21-1204, REPAIR SEWER FORCE MAIN LINE, OSAN AIR BASE, KOREA |