IDV vehicle
N0001919D0026
FRP8-12 WGU-59/B GUIDANCE SECTIONS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NAVAL AIR SYSTEMS COMMAND |
| NAICS | 336414 — Guided Missile and Space Vehicle Manufacturing |
| PSC | 1420 — Guided Missile Components |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $0 |
| Current contract value | Not reported |
| Potential contract value / ceiling | $2.7B |
| Start date | Sep 25, 2019 |
| Current end date | Not available |
| Potential end date | Not available |
| Latest award activity | Jun 4, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 24 of 24 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 4, 2026 | P00021 | $0 | UPDATES TO SECTION J ATTACHMENT 26 AND EXHIBITS CDRLS C008 AND C009 UPDATE TO PAYMENT OFFICE |
| Jan 15, 2026 | P00020 | $0 | UPDATE THE GFP LIST TO THE LATEST VERSION DATED 25 SEP 2025 |
| Sep 11, 2025 | P00019 | $0 | NO COST MOD TO UPDATE ATTACHMENT 6 GOVERNMENT FURNISHED PROPERTY IN SECTION J. |
| May 16, 2025 | P00018 | $0 | UPDATE SECTION A WITH CONSIDERATION LANGUAGE, SECTION B CLIN 0309 ETBI QUANTITY ADJUSTMENT, SECTION J ATTACHMENT UPDATE AND ADMINISTRATIVE UPDATES TO ISSUED BY AND PAYMENT BY OFFICE INFORMATION. |
| Feb 24, 2025 | P00017 | $0 | NO COST MOD TO UPDATE SECTION J WITH ATTACHMENT 33, UPDATE ADMINISTERED BY OFFICE AND UPDATE CONTRACTOR INFORMATION |
| Jan 29, 2024 | ARZ998 | $0 | FRP8-12 WGU-59/B GUIDANCE SECTIONS |
| Nov 29, 2023 | P00016 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE ECP APK FRP10-003 VIA ATTACHMENT 31, AND ADD CLINS AND ADJUSTMENTS AS CONSIDERATION FOR DELIVERY SCHEDULE CHANGES TO FRPS 9,10, AND 11 DUE TO DELAYED DELIVERIES. |
| Oct 23, 2023 | P00015 | $0 | (1) ADD FAR CLAUSE 52.204-27 IN SECTION I (2) DELETE CDRLS C001 AND C007 IN SECTION J (3) INCORPORATE REVISED CDRL C006 AND C009 IN SECTION J AND (4) INCORPORATE REVISED ATTACHMENT (24) AND ATTACHMENT (26) IN SECTION J. |
| May 18, 2023 | P00014 | $0 | MODIFICATION IS TO (1) ADD ECPS APK-FRP10-001 AND ECP APK-FRP10-002 INTO SECT C (2) INCORPORATE REVISED ATTACHS (6), (18) AND (27) INTO SECTION J AND (3) ADD ATTACH (29), ECP APK-FRP10-001, AND ATTACH (30), ECP APK-FRP10-0002, INTO SECT J. |
| Oct 3, 2022 | P00013 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE CONSIDERATION EFFORTS IN EXCHANGE FOR SCHEDULE RELIEF FOR DELIVERIES UNDER FRP 8, 9, AND 10. |
| Jul 19, 2022 | P00012 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE ATTACHMENTS (6) GFP AND (8) DD FORM 254 AND TO UPDATE CLAUSES. |
| Sep 27, 2021 | P00011 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE SVBU ECP AND TO IMPLEMENT THE 2D TAG REQUIREMENTS. |
| Aug 16, 2021 | P00010 | $0 | UPDATE PART NUMBERS UNDER CLIN 0203 |
| Jun 29, 2021 | P00009 | $0 | THE PURPOSE OF THIS NO COST ADMINISTRATIVE MODIFICATION TO INDEFINITE DELIVERY INDEFINITE QUANTITY (IDIQ) CONTRACT N00019-19-D-0026 IS TO UPDATE AN ADDRESS IN ATTACHMENT (8) CONTRACT SECURITY CLASSIFICATION SPECIFICATION (DD254). |
| Jun 8, 2021 | P00008 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION E, ATTACHMENT (1), AND ATTACHMENT (13) TO ALLOW FOR DISCRETIONARY WAIVER OF GAT. |
| Apr 14, 2021 | P00007 | $0 | NO COST MOD TO ADD CLINS 0203 AND 0204 IN SUPPORT OF THE CAS FLEX CABLE REWORK |
| Nov 24, 2020 | P00006 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE ATTACHMENT (18) COMPREHENSIVE SUBCONTRACTING PLAN. |
| Sep 8, 2020 | P00005 | $0 | THE PURPOSE OF THIS MOD IS TO INCORPORATE RFV 0019-V006 INTO SECTION C, APPLICABLE TO ITEMS 0001 AND 0101. |
| Sep 1, 2020 | P00004 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE CLAUSE AT FAR 52.204-25. |
| Jul 20, 2020 | P00003 | $0 | REPLACE ATTACHMENT (10) TO INCORPORATE PRICING UPDATES AS IDENTIFIED IN BAE LTR 20-008 ECO PRICE ADJ DISCLOSURE, DATED 15 MAY 2020. |
| Jun 23, 2020 | ARZ999 | $0 | FRP8-12 WGU-59/B GUIDANCE SECTIONS |
| Jan 22, 2020 | P00002 | $0 | ADMIN MOD |
| Nov 15, 2019 | P00001 | $0 | UPDATING RFV FOR ATTACHMENT (2) |
| Sep 25, 2019 | 0 | $0 | FRP8-12 WGU-59/B GUIDANCE SECTIONS |