Date filters select awards with transaction activity in the period. Amounts below are lifetime award obligations. IDV values remain separate.
ALCOVA-NORTH CODY BREAKER FOUNDATIONS REPLACEMENTDepartment of Energy$148.7K obligationsEnds Sep 24, 2027
REPAIR WALL AND REPLACE ROOFING, SIDING, AND HVAC, SERVICE BUILDING, BONESTEEL SUBSTATION, SDDepartment of Energy$118.5K obligationsEnds Sep 7, 2027
ASPHALT REPAIRS - BISMARCK ADMINISTRATION BUILDING, BISMARCK O&M SERVICE CENTER, DEVILS LAKE SUBSTATION, AND FARGO SUBSTATION, NORTH DAKOTADepartment of Energy$510.1K obligationsEnds Jun 30, 2027
70-FT MONOPOLE FOUNDATION, HURON MAINTENANCE FACILITY, SDDepartment of Energy$87.7K obligationsEnds Aug 4, 2027
WAUNETA SUBSTATION HVACDepartment of Energy$56.6K obligationsEnds Apr 2, 2024
GDE- 502 BREAKER CONCRETE FOUNDATION PROJECTDepartment of Energy$47.8K obligationsEnds Dec 31, 2023
CMRL BATHROOM DRAIN LINE REPAIRDepartment of Energy$13.7K obligationsEnds Jul 1, 2025
VIRGINIA SMITH CONVERTER STATION ROOF COATINGDepartment of Energy$215.8K obligationsEnds Oct 31, 2025
CASPER SUB HYDRANT REMOVALDepartment of Energy$57.4K obligationsEnds Jan 9, 2026
YELLOWTAIL CONTAMINATED ROCK REMOVALDepartment of Energy$270.9K obligationsEnds Feb 20, 2026
RMR_GERING SUBSTATION 142 & 742 BREAKER REPLACEMENTDepartment of Energy$79.5K obligationsEnds Jul 5, 2026
PMOC DISPATCH REMODEL OF EXISTING KITCHEN, OPERATORS RESTROOM, HALL RESTROOMS; AND ADDING/REMOVING DOORS. THE CONTRACTOR SHALL CONDUCT ALL NECESSARY DEMOLITION TO PREPARE THE…Department of Energy$260.0K obligationsEnds May 14, 2026
MAINTENANCE BUILDING PAINT AND REPAIRDepartment of Energy$401.8K obligationsEnds Dec 29, 2025
BISMARCK - GLENHAM 230-KV TRANSMISSION LINE FOUNDATION REPAIRS FOR STRS. 50/4, 50/5, 51/1, 53/2, 54/1, 54/3, 81/4, 83/5, 84/1, 88/2, AND 91/5, ND, SDDepartment of Energy$260.6K obligationsEnds Sep 15, 2026
PMOC BASEMENT COMM OFFICE HVACDepartment of Energy$30.3K obligationsEnds Sep 8, 2024
WATERTOWN OPERATIONS OFFICE BUILDING, HVAC UPGRADE, SDDepartment of Energy$1.0M obligationsEnds Oct 15, 2025
PMOC CONCRETE WORKDepartment of Energy$682.7K obligationsEnds Sep 26, 2025
WATERTOWN OPERATIONS OFFICE BUILDING, EXTERNAL BATTERY-ROOM ENCLOUSRE, SDDepartment of Energy$190.4K obligationsEnds Oct 1, 2025
WHITE SUBSTATION, CIRCUIT BREAKER JU3A FOUNDATION, REMOVAL AND REPLACEMENT, SOUTH DAKOTADepartment of Energy$55.9K obligationsEnds Mar 26, 2025
MORRIS SUBSTATION, SERVICE BUILDING HVAC EQUIPMENT REPLACEMENT, NDDepartment of Energy$28.5K obligationsEnds Jul 29, 2022
HURON SERVICE CENTER, CONCRETE APRON AND OVERHEAD DOOR REPLACEMENTS AT WAREHOUSE NO. 2 & OVERHEAD DOOR REPLACEMENT AT O&M SHOPS BUILDING, SOUTH DAKOTADepartment of Energy$385.5K obligationsEnds Jul 31, 2023
FENCE AND EROSION REPAIRS, VARIOUS LOCATIONS, ND, SDDepartment of Energy$589.4K obligationsEnds Jul 31, 2023
WATERTOWN ALTERNATE OPERATIONS- KONES CORNER MICROWAVE SITE, HIGH-SECURITY FENCING, SOUTH DAKOTADepartment of Energy$673.0K obligationsEnds Jun 15, 2023
WHITE SUBSTATION, CIRCUIT BREAKER FOUNDATION, REMOVAL AND REPLACEMENT, SOUTH DAKOTADepartment of Energy$50.7K obligationsEnds Apr 24, 2024
HURON SUBSTATION, BUS POLE FOUNDATION REMOVALS AND REPLACEMENTS, SOUTH DAKOTADepartment of Energy$109.4K obligationsEnds Jun 20, 2024