Explore federal awards
Date filters select awards with transaction activity in the period. Amounts below are lifetime award obligations. IDV values remain separate.
Export these results to CSV ยท 8 matching records
ASPHALT REPAIRS - BISMARCK ADMINISTRATION BUILDING, BISMARCK O&M SERVICE CENTER, DEVILS LAKE SUBSTATION, AND FARGO SUBSTATION, NORTH DAKOTADepartment of Energy$510.1K obligationsEnds Jun 30, 2027
70-FT MONOPOLE FOUNDATION, HURON MAINTENANCE FACILITY, SDDepartment of Energy$87.7K obligationsEnds Aug 4, 2027
BISMARCK - GLENHAM 230-KV TRANSMISSION LINE FOUNDATION REPAIRS FOR STRS. 50/4, 50/5, 51/1, 53/2, 54/1, 54/3, 81/4, 83/5, 84/1, 88/2, AND 91/5, ND, SDDepartment of Energy$260.6K obligationsEnds Sep 15, 2026
FENCE AND EROSION REPAIRS, VARIOUS LOCATIONS, ND, SDDepartment of Energy$589.4K obligationsEnds Jul 31, 2023
WATERTOWN ALTERNATE OPERATIONS- KONES CORNER MICROWAVE SITE, HIGH-SECURITY FENCING, SOUTH DAKOTADepartment of Energy$673.0K obligationsEnds Jun 15, 2023
HURON SUBSTATION, BUS POLE FOUNDATION REMOVALS AND REPLACEMENTS, SOUTH DAKOTADepartment of Energy$109.4K obligationsEnds Jun 20, 2024
SIOUX CITY AND SIOUX CITY NO. 2 SUBSTATIONS, FOUNDATION REPAIRSDepartment of Energy$87.8K obligationsEnds Sep 1, 2022
2024 COMMUNICATION SITES DEMOLITION, RESTORATION, AND DRAINAGE WORK AT VARIOUS SITES, MINNESOTA AND NORTH DAKOTADepartment of Energy$564.1K obligationsEnds Jun 30, 2025