Date filters select awards with transaction activity in the period. Amounts below are lifetime award obligations. IDV values remain separate.
THIS PROJECT IS A 100% DESIGN BUILD RENOVATION BARRACK BUILDING 4057, PROJECT, FE201310J, IN STRICT ACCORDANCE WITH THE FORT CAMPBELL SPECIFIC GUIDELINES IN THEIR DESIGN AND…Department of Defense$16.0M obligationsEnds Oct 7, 2027
CONSOLIDATED HOUSING FURNITURE STORAGE FACILITY BLDG 6453Department of Defense$6.0M obligationsEnds Sep 26, 2027
RENOVATE COMPANY OPERATION FACILITY (COF), BUILDING 3672.Department of Defense$2.0M obligationsEnds Sep 20, 2026
THE PROJECT REQUIRES THE REPLACEMENT OF UNDERGROUND FUEL TANKS (UST) FOR MOTOR DIESEL DISPENSING DUE TO LIFE CYCLE REPLACEMENT AND THE NEED TO UPDATE TO ABOVEGROUND FUEL TANKS…Department of Defense$672.2K obligationsEnds Mar 7, 2026
THIS PROJECT IS TO PERFORM RESURFACE FRYER STADIUM TRACK.Department of Defense$974.8K obligationsEnds May 27, 2026
THIS PROJECT IS TO PERFORM DESIGN/BUILD, REPLACE FCX CONVERTERS AT BLDGS. 7272 AND 7274.Department of Defense$349.3K obligationsEnds Jul 19, 2026
THIS PROJECT IS TO REPLACE WATER HEATERS AT BLDG. 7274.Department of Defense$119.5K obligationsEnds Feb 5, 2026
REPAIR SABRE HELIPORTDepartment of Defense$4.5M obligationsEnds Aug 15, 2025
DESIGN BUILD RENOVATION BARRACKS BLDG.3731Department of Defense$15.9M obligationsEnds Oct 15, 2025
D/B LEAD ACID BATTERY STORAGEDepartment of Defense$738.5K obligationsEnds Aug 14, 2025
INDIVIDUAL ISSUE AREA INSTALL OH COVERDepartment of Defense$717.5K obligationsEnds Jul 8, 2025
REPLACING THE ROOF ON BUILDING 7154 DUE TO LEAKAGEDepartment of Defense$1.1M obligationsEnds Nov 9, 2025
THIS PROJECT WILL BE TASKED WITH REPLACING THE HEATING, VENTILATION, AND AIR CONDITIONING (HVAC) SYSTEM IN BUILDING 6241. THE DUCT WORK WILL NEED TO BE REMOVED, AND A NEW DUCT…Department of Defense$417.8K obligationsEnds Jan 2, 2026
FIP D/B RENOVATION BARRACK BUILDING 4024Department of Defense$13.7M obligationsEnds May 29, 2025
ALERT HOLDING AREA COVERED INSPECTIONDepartment of Defense$711.6K obligationsEnds Jun 7, 2025
FIP DB RENOVATE BARRACKS 3748Department of Defense$15.8M obligationsEnds Jun 23, 2025
ALL DESIGN & SEDIMENT BASIIN #5Department of Defense$1.7M obligationsEnds Feb 24, 2026
INCREASE LEACHATE HOLDING CAPACITY. EXTEND RETAINING WALL. DEMO EXISTING SHED AND INSTALL NEW 10 X 14 PUMP HOUSE BLOCK BUILDING.Department of Defense$618.4K obligationsEnds Sep 10, 2025
DESIGN-BUILD RENOVATION BARRACK B-3730Department of Defense$13.5M obligationsEnds Mar 31, 2025
CONSTRUCT 25 FT PAVED SHOULDERDepartment of Defense$412.0K obligationsEnds Apr 30, 2025
MINIMUM GUARANTEE TASK ORDER - W912QR21D0032 - INTECDepartment of Defense$5.0K obligationsEnds Mar 28, 2024