Date filters select awards with transaction activity in the period. Amounts below are lifetime award obligations. IDV values remain separate.
THIS SABER TASK ORDER IS TO REPLACE CHILLER (PIO HVAC) IN B7206.Department of Defense$415.3K obligationsEnds Jun 29, 2026
REMOVE EXISTING FLOOR PANELS AND INSTALL NEW RAISED FLOORING WITHIN THE SERVER ROOM, SECURE SERVER ROOM AND STORAGE AREA.Department of Defense$601.9K obligationsEnds Mar 7, 2027
PROPOSAL FEE FOR A SUNSHADE FOR B9111. MAGNITUDE OF CONSTRUCTION: PURSUANT TO FAR 36.204(E) THE FOLLOWING IS PROVIDED: THE MAGNITUDE OF CONSTRUCTION IS BETWEEN $500,000 AND…Department of Defense$500 obligationsEnds Jun 23, 2026
THE CONTRACTOR SHALL PROVIDE ALL LABOR, EQUIPMENT, TOOLS, MATERIAL, SUPERVISION, AND ALL OTHER NECESSARY ITEMS TO DEMO AND DISPOSE OF EXISTING LIGHT POLES, WIRING AND LIGHTS AND…Department of Defense$289.8K obligationsEnds Mar 7, 2027
THIS IS A TASK ORDER OFF THE SABER CONTRACT FA466117D0003 FOR REPAIR WATER TOWER, 6221 TOPR #114. $500 HAS BEEN SUBTRACTED FROM THE PROPOSED PRICE OF $1,535,938.76 DUE TO THE…Department of Defense$1.8M obligationsEnds Jun 17, 2026
EXTEND B4216 SEWER LIFE BY CLEANING PIPES, REPAIRING LINING, AND INSTALLING NEW CONNECTION TO MAIN LINE SOUTH OF BUILDING. REPLACE CHIPPED/BROKEN CORRIDOR TILE NEAR ROOM 325…Department of Defense$239.9K obligationsEnds Jun 22, 2026
REPLACE AIR HANDLER, CHILLED WATER PUMP, AND PIPING IN B8030. REPLACE DIRECT EXPANSION UNIT AND AIR HANDLER IN B11955Department of Defense$249.0K obligationsEnds Jul 13, 2026
THIS TASK ORDER IS TO REPLACE HVAC IN DORMS B6126/6127Department of Defense$487.8K obligationsEnds Mar 6, 2027
REMOVE AND REPLACE THE AIR HANDLERS, BOILERS, CHILLED WATER PUMPS, AND THE YORK CHILLER LOCATED AT BUILDING 8202.Department of Defense$1.3M obligationsEnds Apr 23, 2027
PROPOSAL FEE TO REPLACE FIREHOUSE DOORS/AIR HOSES AT B5013. TASK ORDER UTILIZES CLINS 3001 AND 3003.Department of Defense$500 obligationsEnds May 20, 2026
THE PURPOSE OF THIS TASK ORDER IS TO REPAIR THE DEFICIENT HVAC SYSTEM IN BUILDING 5013, FIRE STATION.Department of Defense$607.6K obligationsEnds Oct 6, 2026
THE PURPOSE OF THIS TASK ORDER IS FOR THE REPAIR OF THE CCU FUEL CELL VENTILATION SYSTEM IN BUILDING 4230.Department of Defense$1.3M obligationsEnds May 11, 2026
PROPOSAL FEE FOR 436 TRS CRASH PAD B8202 DESIGNS AND QUANTS. MAGNITUDE OF CONSTRUCTION: PURSUANT TO FAR 36.204(D) THE FOLLOWING IS PROVIDED: THE MAGNITUDE OF CONSTRUCTION IS…Department of Defense$500 obligationsEnds Jul 9, 2026
THIS TASK ORDER IS TO PERFORM MOLD REMEDIATION IAW SOO FOR DORM ROOMS.Department of Defense$886.4K obligationsEnds Oct 27, 2026
PROPOSAL FEE FOR HVAC REPLACEMENT FOR B6126 AND 6127. MAGNITUDE OF CONSTRUCTION: PURSUANT TO FAR 36.204(C) THE FOLLOWING IS PROVIDED: THE MAGNITUDE OF CONSTRUCTION IS BETWEEN…Department of Defense$500 obligationsEnds Mar 13, 2026
RENOVATE B4314 BATHROOMS IN ACCORDANCE WITH THE SOO.Department of Defense$449.2K obligationsEnds Sep 2, 2026
THE USER AT B4216 WANTS TO RENOVATE THEIR AUDITORIUM. THEIR MAIN FOCUSES INCLUDE NEW SEATING, NEW CARPET, UPDATED PAINT AND WALL FIXTURES, AND RENOVATING THE STAGE.Department of Defense$478.5K obligationsEnds Aug 10, 2026
X060 NBPL-47. UPGRADE EXISTING LOCKER AND SHOWER ROOMDepartment of Defense$709.1K obligationsEnds Sep 22, 2026
THIS TASK ORDER IS UTILIZING CLIN 2001 AND 2002 TO PERFORM MOLD REMEDIATION IAW STATEMENT OF OBJECTIVES (SOO) FOR B6126 AND B6127.Department of Defense$500 obligationsEnds Jan 26, 2026
THIS PROJECT ENTAILS THE INSTALLATION OF GENERATORS TO EACH OF THE BUILDINGS LISTED, 5225, 9330, 6030, AND 6122, TO INCLUDE ACCOMPANYING PANEL BOARDS, AUTOMATIC TRANSFER…Department of Defense$395.1K obligationsEnds Apr 26, 2027
4311 RENO TO INCLUDE HVAC AND FLOORINGDepartment of Defense$251.3K obligationsEnds Jul 28, 2026
BUILDING 9304, TO RENOVATE THE CARBON MONOXIDE AND NITROGEN OXIDES (CO/NOX) VENTILATION EXHAUST SYSTEM.Department of Defense$597.7K obligationsEnds Jul 27, 2026
THIS IS A TASK ORDER OFF THE MAIN SABER IDIQ, FA466123D0001, TO RENOVATE THE BUILDING IN 7312. ALL WORK WILL BE IN ACCORDANCE WITH SOO FNWZ 24-0108, SOW AND ATTACHED DESIGNS.Department of Defense$1.9M obligationsEnds Sep 19, 2025
N6247319D2625_X066 B-268 UAV LANDING ZONE INSTALL GFE SUPATRAC AND PROVIDE 120/220V OUTLETS TO SUPPORT EQUIPMENT, SSTCDepartment of Defense$61.8K obligationsEnds Oct 15, 2025
SABER TASK ORDER FOR 8006 INTERIOR COURTYARD FNWZ 23-0036.Department of Defense$224.5K obligationsEnds Sep 8, 2025