BURGER DISTRICT COOLING DECOUPLING HEAT EXCHANGERS WARREN BURGER FEDERAL BUILDING AND UNITED STATES COURTHOUSE, SAINT PAUL, MINNESOTA COURTHOUSE ST PAUL, MINNESOTA 55101General Services Administration$856.0K obligationsEnds Jan 6, 2027
PROJECT TO REPLACE THE TWO EXISTING ROOFTOP UNITS FOR COURTROOM 1 AND 2 THAT ARE LOCATED IN THE ATTIC SPACE OF THE EDWARD J. DEVITT FEDERAL BUILDING, 118 S. MILL ST., FERGUS…General Services Administration$203.0K obligationsEnds Jun 28, 2027
REPLACE EAST SIDEWALK, MINNEAPOLIS FEDERAL OFFICE BUILDING, 212 THIRD AVENUE, SOUTH, MINNEAPOLIS, MINNESOTA 55401General Services Administration$186.8K obligationsEnds Dec 17, 2026
GENERAL CONTRACTOR IS TO PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION FOR A PROJECT ON THE 4TH FLOOR AT THE BISHOP HENRY WHIPPLE FEDERAL BUILDING AT 1 FEDERAL DR…General Services Administration$316.1K obligationsEnds Oct 21, 2026
PROJECT FOR THE GEOTHERMAL CIRCUIT LEAK AT THE WHIPPLE FEDERAL BUILDING, 1 FEDERAL DRIVE, FORT SNELLING, MN 55111General Services Administration$125.1K obligationsEnds Dec 21, 2026
PROJECT IS TO REPAIR/REPLACE WATER DAMAGE TO ITS PRIOR STATE FOR PASSPORTS OFFICE SPACE DUE TO A BURST PIPE. WELLSTONE FEDERAL OFFICE BUILDING, 212 THIRD AVE. S., MINNEAPOLIS, MN…General Services Administration$139.8K obligationsEnds Apr 14, 2027
REFURBISH FREIGHT ELEVATOR #7, INSTALL NEW SUMP PUMP PIPING BOILER ROOM, MODERNIZE CARTAGE & HOISTING, PREVENTATIVE MAINTENANCE SERVICE - FREIGHT ELEVATOR MODERNIZATION - WHIPPLE…General Services Administration$532.3K obligationsEnds Oct 21, 2025
THE PURPOSE OF THIS PROJECT IS TO PROVIDE RENOVATION AND ALTERATION FOR CHAMBERS 724 AT THE WARREN E. BURGER FEDERAL BUILDING & U.S. COURTHOUSE 316 ROBERT ST. N. ST. PAUL, MN 55101General Services Administration$148.5K obligationsEnds Mar 10, 2027
INSTALL NEW SUMP PUMP & ROUTE SUMP PUMP PIPING MODERNIZE ELEVATOR, CARTAGE & HOISTING INSTALL ELECTRICAL CONNECTIONS PATCH & REPAIR FINISHES - PASSENGER ELEVATOR MODERNIZATION…General Services Administration$619.3K obligationsEnds Jan 30, 2027
WATER HEATER DDC AND KILL SWITCHDepartment of Defense$138.9K obligationsEnds Jul 24, 2026
GENERAL CONTRACTOR IS TO PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION FOR A PROJECT LOCATED AT EDWARD J. DEVITT U.S. COURTHOUSE & FEDERAL BUILDING 118 S MILL ST…General Services Administration$100.8K obligationsEnds Oct 13, 2026
B656 BOILER REPLACEMENTDepartment of Defense$92.2K obligationsEnds Aug 7, 2026
B683 WATER HEATERSDepartment of Defense$7.0K obligationsEnds Jul 10, 2026
GENERAL CONTRACTOR IS TO PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION FOR A PROJECT ON THE CHAMBERS 2A CARPET INSTALL 316 ROBERT ST N, ST. PAUL, MN 55101-1495General Services Administration$33.8K obligationsEnds Sep 19, 2026
THE PURPOSE OF THIS PROJECT IS TO REPLACE THE EXISTING LIGHT CONTROLLERS AT THE WARREN E. BURGER FEDERAL BUILDING AND U.S. COURTHOUSE IN ST PAUL, MN.General Services Administration$353.0K obligationsEnds Jul 31, 2026
INSTALL EXTERIOR OVERHEAD DOOR AT PARKING STRUCTURE ENTRANCE - DIANA E. MURPHY UNITED STATES COURTHOUSE - MINNEAPOLIS, MINNESOTAGeneral Services Administration$252.0K obligationsEnds Apr 30, 2025
CONSTRUCTION AWARD FOR THE US DISTRICT COURT OF APPEALS 2ND FLOOR, 300 S. FOURTH STREET, MINNEAPOLIS, MN 55415 (MN0092ZZ)General Services Administration$1.9M obligationsEnds Aug 8, 2025
VA DOGHOUSE FLOOR BOX REPLACEMENT, WHIPPLE FEDERAL BUILDING, FORT SNELLING, MN THE PURPOSE OF THIS PROJECT IS TO DEMOLISH THE EXISTING 20 DOGHOUSES CONTAINING POWER AND DATA IN…General Services Administration$31.9K obligationsEnds Apr 9, 2026
CONSTRUCTION AWARD FOR THE USAO OFFICE RENOVATION 5TH FLOOR AT THE DIANA E. MURPHY U.S. COURTHOUSE, 300 SOUTH 4TH STREET, MINNEAPOLIS, MN, 55415. (MN0092ZZ)General Services Administration$235.4K obligationsEnds Sep 19, 2025
REMODEL OF THE JURY ASSEMBLY ROOM AT THE W.E. BURGER FEDERAL BUILDING AND COURTHOUSE IN ST. PAUL MN. WORK INCLUDES REPLACE FLOORING, REMOVE VWC COVERING, PAINT THE WALLS, INSTALL…General Services Administration$326.2K obligationsEnds Nov 9, 2025
B687 REPLACEMENT BOILERSDepartment of Defense$83.3K obligationsEnds Jan 14, 2026
QJKL242003 MANUAL TRANSFER SWITCHDepartment of Defense$168.7K obligationsEnds Feb 20, 2026
B642 REPLACEMENT WINDOWSDepartment of Defense$630.0K obligationsEnds Jan 22, 2026
CHAMBERS ALTERATIONS, DIANA MURPHY COURTHOUSE, MINNEAPOLIS, MN THE PURPOSE OF THIS PROJECT IS TO REMODEL CHAMBERS 9W, 9E, 11W, 14W, AND 11TH FLOOR LAW LIBRARYGeneral Services Administration$573.8K obligationsEnds Dec 1, 2025
5TH FLOOR, COMMON AREA REFRESH PHASE 3 THE PURPOSE OF THIS PROJECT IS TO INSTALL NEW CARPET TILES, VINYL FLOORING, BASE MOLDING AND PAINT AT THE DIANA E. MURPHY COURTHOUSE…General Services Administration$144.6K obligationsEnds Oct 31, 2025