Federal contract award
1240LT24F0016
0402 SIL CONST BOISE BRIDGE 236 REPLACEMENT
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Agriculture |
| Office | USDA-FS, CSA INTERMOUNTAIN 8 |
| NAICS | 237310 — Highway, Street, and Bridge Construction |
| PSC | Z2LB — REPAIR OR ALTERATION OF HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS |
| Parent award / vehicle | 1284M820D0019 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $762.5K |
| Current contract value | $762.5K |
| Potential contract value / ceiling | $762.5K |
| Start date | Jun 3, 2024 |
| Current end date | May 14, 2026 |
| Potential end date | Sep 30, 2026 |
| Latest award activity | May 14, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 4 of 4 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 14, 2026 | P00003 | $0 | MOD P00003 - CHANGE POP END DATE FOR CLOSE OUT. CONTRACT IS PHYSICALLY COMPLETE AND ALL CLOSE OUT DOCUMENTS HAVE BEEN UPLOADED. |
| Dec 2, 2025 | P00002 | $-73.5K | MOD P00002 - INCORPORATES REDESIGN OF BRIDGE BASED ON GEOTECHNICAL INVESTIGATION FROM MOD P00001. ALSO EXTENDS THE POP TO ACCOMMODATE THE REDESIGN AND GOVERNMENT SHUTDOWN. |
| Jul 30, 2025 | P00001 | $40.0K | GEOTECHNICAL INVESTIGATION AND ANALYSIS: PERFORM A GEOTECHNICAL INVESTIGATION AND PROVIDE RECOMMENDATIONS FOR THE PURPOSE OF A BRIDGE FOUNDATION DESIGN ACCORDING TO AASHTO STANDARDS AND TASK ITEMS PRESENTED IN THIS STATEMENT OF WORK. |
| May 28, 2024 | 0 | $796.0K | 0402 SIL CONST BOISE BRIDGE 236 REPLACEMENT |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.