Federal contract award
47PE0522F0001
THIS REQUIREMENT IS FOR ADA RAMP REPAIRS AND A NEW ELEVATOR LOCATED AT THE COCHRAN CH, 501 EAST COURT STREET, JACKSON, MS.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R4 AMD SPECIAL PROJECTS BRANCH |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PE0120D0010 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.9M |
| Current contract value | $1.9M |
| Potential contract value / ceiling | $1.9M |
| Start date | Nov 1, 2021 |
| Current end date | Jun 30, 2026 |
| Potential end date | Aug 31, 2026 |
| Latest award activity | Apr 8, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 8, 2026 | PS0013 | $0 | MOD TO EXTEND POP THROUGH JUNE TO ALLOW PUNCHLIST TO BE COMPLETED. |
| Oct 23, 2025 | PS0012 | $0 | THIS REQUIREMENT IS TO EXTEND THE PROJECT COMPLETION DATE BY 90 DAYS TO RESOLVE IT ISSUES REQUIRED FOR THE NEW ELEVATOR IN THE JACKSON FB MS0007ZZ. |
| Sep 12, 2025 | PS0011 | $-25.6K | THIS MODIFICATION IS REQUIRED TO DECREASE THE FUNDING FOR UNNECESSARY WORK REQUIREMENTS, LOCATED AT THE JACKSON COURTHOUSE, JACKSON, MS. |
| Mar 20, 2025 | PS0010 | $56.7K | THIS MODIFICATION IS REQUIRED TO EXTEND POP 60 DAYS CHANGE COR ADD CLIN 0005 AND FUNDING TO ADD REQUIRED MAD SYSTEM TO THE ELEVATOR AND MATCH STONE WORK FOR RAMP AT THE JACKSON CH MS0007ZZ. |
| Feb 25, 2025 | PS0009 | $0 | THIS MODIFICATION IS TO EXTEND THE POP COMPLETION DATE 91 DAYS TO ALLOW TIME FOR EXTRA CONSTRUCTION FUNDING TO BE APPROVED AND APPLIED TO AWARD. PROJECT LOCATED IN JACKSON MS. |
| Nov 8, 2024 | PS0008 | $35.7K | THIS AWARD MOD IS REQUIRED TO ADD FIRE ALARM SYSTEM CPU UPGRADE, REPLACE 10 LIGHT FIXTURES, AND EXTEND POP BY 126 DAYS FOR THE PROJECT LOCATED AT THE COCHRAN FB MS0007ZZ IN JACKSON, MS. |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.