Federal contract award

47PH0424F0014

THE CONVERSION OF LANES 7 AND 8 FROM COMMERCIAL TO PERSONAL VEHICLE INSPECT. INCLUDES INSTALL OF SECURITY EQUIPMENT ELECTRIC AND MECHANICAL FOR TWO PREFABRICATED BOOTHS AT EAGLE PASS 2 LAND PORT OF ENTRY 500 SOUTH ADAMS STREET EAGLE PASS TEXAS 78852

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyGeneral Services Administration
OfficePBS R7 NON-PROSPECTUS - BORDER
NAICS236220 — Commercial and Institutional Building Construction
PSCZ2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS
Parent award / vehicle47PH0820D0002
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.4M
Current contract value$1.4M
Potential contract value / ceiling$1.4M
Start dateMar 11, 2024
Current end dateMay 23, 2025
Potential end dateJun 24, 2025
Latest award activityMay 5, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 5, 2025PS0009$4.1KTHIS MODIFICATION INCLUDES A TIME EXTENSION OF 28 DAYS TO ALLOW FOR PROJECT COMPLETION AND FINALIZATION. THE END DATE WILL GO FROM: 4/25/25 TO: 5/23/25 THE PRICE WILL INCREASE FROM: $1,397,252.33 TO: $1,401,359.07 - A DIFFERENCE OF $4,106.74.
Apr 8, 2025PS0008$0THE PURPOSE OF THIS MODIFICATION (PS0008) TO 47PH0424F0014 IS TO PROVIDE A TIME EXTENSION OF 46 DAYS TO ALLOW FOR PROJECT COMPLETION AND FINALIZATION. THE END DATE WILL GO FROM: 3/10/25 TO: 4/25/25
Mar 18, 2025PS0007$0THE PURPOSE OF THIS MODIFICATION (PS0007) TO 47PH0424F0014 IS TO PROVIDE A TIME EXTENSION OF 31 DAYS TO ALLOW FOR PROJECT COMPLETION AND FINALIZATION. THE END DATE WILL GO FROM: 3/10/25 TO: 4/10/25
Feb 18, 2025PS0006$0THE PURPOSE OF THIS MODIFICATION (PS0006) TO 47PH0424F0014 IS TO PROVIDE A TIME EXTENSION TO ALLOW FOR ADDITIONAL WORK AND PROJECT COMPLETION. THE END DATE WILL GO FROM: 2/10/25 TO: 3/10/25
Jan 16, 2025PS0005$34.3KPROVIDE A TIME EXTENSION TO ALLOW FOR ADDITIONAL WORK AND PROJECT COMPLETION. THERE IS A TIME EXTENSION OF 30 DAYS. THE END WILL GO FROM: 1/10/25 TO: 2/10/25 THE PRICE WILL INCREASE BY 34293-32. FROM:1362959-01 TO: 1397252-33 FOR ADDED WORK
Dec 16, 2024PS0004$0MODIFICATION PS0004 TO 47PH0424F0014 IS TO PROVIDE A TIME EXTENSION TO ALLOW PROJECT COMPLETION. THE MODIFICATION INCLUDES A TIME EXTENSION OF 24 DAYS TO ALLOW FOR PROJECT COMPLETION AND FINALIZATION. THE END DATE WILL GO FROM: 12/27/24 TO: 1/10/25
Oct 30, 2024PS0003$48.5KTHE PURPOSE OF THIS MODIFICATION IS TO PROVIDE A 21 DAY TIME EXTENSION AND COST INCREASE OF $48,463.40. THE END DATE WILL GO FROM:11/23/24 TO: 12/17/24 AND THE PRICE WILL GO FROM:$1,314,495.61 TO:$1,362,959.01 TO ADD BOLLARDS, GATE AND LANE MARKINGS

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.