Federal contract award
47PH0424F0014
THE CONVERSION OF LANES 7 AND 8 FROM COMMERCIAL TO PERSONAL VEHICLE INSPECT. INCLUDES INSTALL OF SECURITY EQUIPMENT ELECTRIC AND MECHANICAL FOR TWO PREFABRICATED BOOTHS AT EAGLE PASS 2 LAND PORT OF ENTRY 500 SOUTH ADAMS STREET EAGLE PASS TEXAS 78852
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | General Services Administration |
| Office | PBS R7 NON-PROSPECTUS - BORDER |
| NAICS | 236220 — Commercial and Institutional Building Construction |
| PSC | Z2AA — REPAIR OR ALTERATION OF OFFICE BUILDINGS |
| Parent award / vehicle | 47PH0820D0002 |
| Set-aside | Not reported |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $1.4M |
| Current contract value | $1.4M |
| Potential contract value / ceiling | $1.4M |
| Start date | Mar 11, 2024 |
| Current end date | May 23, 2025 |
| Potential end date | Jun 24, 2025 |
| Latest award activity | May 5, 2025 |
| Source loaded | Aug 15, 2026 |
Funding and modification history
Showing the latest 7 of 7 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 5, 2025 | PS0009 | $4.1K | THIS MODIFICATION INCLUDES A TIME EXTENSION OF 28 DAYS TO ALLOW FOR PROJECT COMPLETION AND FINALIZATION. THE END DATE WILL GO FROM: 4/25/25 TO: 5/23/25 THE PRICE WILL INCREASE FROM: $1,397,252.33 TO: $1,401,359.07 - A DIFFERENCE OF $4,106.74. |
| Apr 8, 2025 | PS0008 | $0 | THE PURPOSE OF THIS MODIFICATION (PS0008) TO 47PH0424F0014 IS TO PROVIDE A TIME EXTENSION OF 46 DAYS TO ALLOW FOR PROJECT COMPLETION AND FINALIZATION. THE END DATE WILL GO FROM: 3/10/25 TO: 4/25/25 |
| Mar 18, 2025 | PS0007 | $0 | THE PURPOSE OF THIS MODIFICATION (PS0007) TO 47PH0424F0014 IS TO PROVIDE A TIME EXTENSION OF 31 DAYS TO ALLOW FOR PROJECT COMPLETION AND FINALIZATION. THE END DATE WILL GO FROM: 3/10/25 TO: 4/10/25 |
| Feb 18, 2025 | PS0006 | $0 | THE PURPOSE OF THIS MODIFICATION (PS0006) TO 47PH0424F0014 IS TO PROVIDE A TIME EXTENSION TO ALLOW FOR ADDITIONAL WORK AND PROJECT COMPLETION. THE END DATE WILL GO FROM: 2/10/25 TO: 3/10/25 |
| Jan 16, 2025 | PS0005 | $34.3K | PROVIDE A TIME EXTENSION TO ALLOW FOR ADDITIONAL WORK AND PROJECT COMPLETION. THERE IS A TIME EXTENSION OF 30 DAYS. THE END WILL GO FROM: 1/10/25 TO: 2/10/25 THE PRICE WILL INCREASE BY 34293-32. FROM:1362959-01 TO: 1397252-33 FOR ADDED WORK |
| Dec 16, 2024 | PS0004 | $0 | MODIFICATION PS0004 TO 47PH0424F0014 IS TO PROVIDE A TIME EXTENSION TO ALLOW PROJECT COMPLETION. THE MODIFICATION INCLUDES A TIME EXTENSION OF 24 DAYS TO ALLOW FOR PROJECT COMPLETION AND FINALIZATION. THE END DATE WILL GO FROM: 12/27/24 TO: 1/10/25 |
| Oct 30, 2024 | PS0003 | $48.5K | THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE A 21 DAY TIME EXTENSION AND COST INCREASE OF $48,463.40. THE END DATE WILL GO FROM:11/23/24 TO: 12/17/24 AND THE PRICE WILL GO FROM:$1,314,495.61 TO:$1,362,959.01 TO ADD BOLLARDS, GATE AND LANE MARKINGS |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.