Federal contract award
68HE0521F0042
DES CLIN 0002 - JACOBSVILLE SUPERFUND SITE REMEDIAL DESIGN INITIAL TASK ORDER AWARD
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Environmental Protection Agency |
| Office | REGION 5 CONTRACTING OFFICE |
| NAICS | 562910 — Remediation Services |
| PSC | F108 — Hazardous Substance Removal, Cleanup, and Disposal Services and Operational Support |
| Parent award / vehicle | 68HE0318D0004 |
| Set-aside | Not reported |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $7.1M |
| Current contract value | $7.1M |
| Potential contract value / ceiling | $7.1M |
| Start date | Mar 24, 2021 |
| Current end date | Mar 28, 2026 |
| Potential end date | Apr 29, 2026 |
| Latest award activity | May 1, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 19 of 19 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 1, 2026 | P00018 | $0 | JACOBSVILLE NEIGHBORHOOD SOIL CONTAMINATION SUPERFUND SITE: RAF, DES, CLIN 0002, RD TASK ORDER THE PURPOSE OF MODIFICATION P00018 UPDATE TOCOR |
| Oct 11, 2024 | P00017 | $136.3K | JACOBSVILLE:RAF/DES/CLIN2/RD TO P7: INCORPORATE RFI#7 (W/ P16) 1.EXTENDS POP END DATE 3/28/26 (PREV 9/29/25) 2.OBLIGATES NEW FUNDING $136,323.33(COST=$130,515.96, FEE=$5,807.37) 3.ASSIGNS NEW PRIMARY & ALTERNATE PROJECT OFFICER/INVOICE APPROV |
| Sep 30, 2024 | P00016 | $0 | JACOBSVILLE NEIGHBORHOOD SOIL CONTAMINATION SUPERFUND SITE: RAF, DES, CLIN 0002, RD TO THE PURPOSE OF P16: REQUISITION FOR MODIFICATION TO APPROVE RFI #7 REPRIORITIZING FUNDING OF $1,098,284.33 FROM CLINS 0003, 0004, 0006 TO CLIN 0005 (OP. YR 4) |
| Sep 11, 2024 | P00015 | $21.1K | JACOBSVILLE NEIGHBORHOOD SOIL CONTAMINATION SUPERFUND SITE: RAF, DES, CLIN 0002, RD TASK ORDER THE PURPOSE OF MODIFICATION P00015: 1) IRA INVOICE ADJUSTMENT FOR FY22. |
| Dec 6, 2023 | P00014 | $828.7K | JACOBSVILLE: RAF, DES, CLIN0002, RD TO, P14 1)EXERCISE OPYR4 CLIN0005, EXTENDING POP END TO 9/29/25 2)OBLIGATE $828,679.20 TO FUND OPYR4: DIRECT=$788,912.72;FEE=$39,766.48 3)CHANGE PRIMARY PROJECT OFFICER/INVOICE APRV. 4)CHANGE ALT. INVOICE APRV. |
| Dec 4, 2023 | P00013 | $0 | JACOBSVILLE NEIGHBORHOOD SOIL CONTAMINATION SUPERFUND SITE: RAF, DES, CLIN 0002, RD TO MOD P13 REQ FOR MOD: SHIFTING $97,359.56 FROM CLIN 006(SUBTASK 06.1.6.6, BASE OP. TASKS COMMUNITY INVOLVEMENT) TO CLIN 004(SUBTASK 04.8.1.1.4, ACCESS AGREEMENTS) |
| Aug 2, 2023 | P00012 | $0 | JACOBSVILLE NEIGHBORHOOD SOIL CONTAMINATION SUPERFUND SITE: RD TASK ORDER, RAF, DES, CLIN 0002 ADMINISTRATIVE MODIFICATION THE PURPOSE OF MODIFICATION P00012: GEOPROBE RFI 5 |
| Jul 14, 2023 | P00011 | $0 | JACOBSVILLE NEIGHBORHOOD SOIL CONTAMINATION SUPERFUND SITE: RD TASK ORDER, RAF, DES, CLIN 0002 ADMINISTRATIVE MODIFICATION THE PURPOSE OF MODIFICATION P00011: 1) UPDATE CLIN DATES FOR IPP |
| Apr 3, 2023 | P00010 | $0 | JACOBSVILLE NEIGHBORHOOD SOIL CONTAMINATION SUPERFUND SITE: RD TASK ORDER, RAF, DES, CLIN 0002 ADMINISTRATIVE MODIFICATION: THE PURPOSE OF MODIFICATION P00010: 1) TOCOR CHANGE |
| Mar 13, 2023 | P00009 | $808.7K | JACOBSVILLE SITE RD TO, RAF, DES, CLIN 0002, MOD P9: 1)EXERCISE OPYR 3 CLIN 0004, EXTENDING THE POP END DATE TO 9/29/24 2)OBLIGATE $808,680.70 TO FUND OPYR 3 (DIRECT COST=$770,046.20 FEE=$38,634.50) 3) ASSIGN NEW ALT. INVOICE APPROVER |
| Dec 30, 2022 | P00008 | $0 | RAF, DES, CLIN 0002, JACOBSVILLE RD THE PURPOSE OF MODIFICATION P00008 IS TO PROCESS A REQUISITION FOR MODIFICATION TO MOVE FUNDING DUE TO FINANCE ISSUES. |
| Oct 11, 2022 | P00007 | $0 | DESIGN AND ENGINEERING SERVICES, CLIN 002, OAZ SUPERFUND SITE REMEDIAL DESIGN ADMIN MODIFICATION: MOD P00007 CHANGES THE TOCOR |
| Aug 10, 2022 | P00006 | $0 | DESIGN AND ENGINEERING SERVICES, CLIN 002, OAZ SUPERFUND SITE REMEDIAL DESIGN MODIFICATION P00006 CHANGES CONTRACTOR PROJECT MANAGER TO RACHEL CLENNON |
| Jun 13, 2022 | P00005 | $25.0K | MODIFICATION P00005 ADDS ADDITIONAL FUNDING TO CLIN 0001 DUE TO CALIBRATION ISSUES DESCRIBED IN RFI 003. |
| Apr 13, 2022 | P00004 | $2.9M | MODIFICATION P0004 EXERCISES OPTIONAL CLIN 006. |
| Sep 17, 2021 | P00003 | $784.7K | MODIFICATION P0002 INCORPORATES CH2M'S FINAL REVISED PMP DATED 06/18/2021 |
| Jul 6, 2021 | P00002 | $0 | MODIFICATION P0002 INCORPORATES CH2M'S FINAL REVISED PMP DATED 06/18/2021 |
| Apr 26, 2021 | P00001 | $0 | MODIFICATION P0001 INCORPORATES CH2M'S FINAL PMP AND ADDS OPTIONAL QTY CLAUSE |
| Mar 24, 2021 | 0 | $1.6M | DES CLIN 0002 - JACOBSVILLE SUPERFUND SITE REMEDIAL DESIGN INITIAL TASK ORDER AWARD |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.