Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyEnvironmental Protection Agency
OfficeREGION 5 CONTRACTING OFFICE
NAICS562910 — Remediation Services
PSCF108 — Hazardous Substance Removal, Cleanup, and Disposal Services and Operational Support
Parent award / vehicle68HE0118D0010
Set-asideNot reported
Pricing typeTIME AND MATERIALS
Obligations$206.2K
Current contract value$218.4K
Potential contract value / ceiling$218.4K
Start dateApr 9, 2021
Current end dateJul 31, 2026
Potential end dateJul 31, 2026
Latest award activitySep 19, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 12 of 12 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 19, 2025P00011$51.6KDUE TO CHANGE IN REQUIREMENTS, THERE IS A SHIFT FROM LINE ITEM 1002A FIELD AUDITS TO 1002C RI/FS SUPPORT. SUBJECT MODIFICATION DEOBLIGATES FUNDS IN THE AMOUNT OF $8,389.61 FROM LINE ITEM 1002A. THIS WILL FREE UP CAPACITY. DUE TO SYSTEM RESTRICTIONS
Sep 12, 2025P00010$-50.4KDUE TO CHANGE IN REQUIREMENTS, THERE IS A SHIFT FROM LINE ITEM 1002A FIELD AUDITS TO 1002C RI/FS SUPPORT. SUBJECT MODIFICATION DEOBLIGATES FUNDS IN THE AMOUNT OF $50,378.83 FROM LINE ITEM 1002A. THIS WILL FREE UP CAPACITY. DUE TO SYSTEM RESTRICTION
Jul 24, 2024P00009$-15.3KDEOBLIGATE THE FOLLOWING REMAINING BALANCES. 0002B TREATABILITY REMAINING BALANCE: $6,902.54 0002D REMOVAL SUPPORT REMAINING BALANCE: $8,447.22
May 9, 2024P00008$-140CANCEL THE FOLLOWING: 1001BA QAPP UPDATE YR 1 NOT REQUIRED 0001E CLOSE OUT BASE 1001E CLOSE OUT OPTION PERIOD IS FUNDED.
Dec 20, 2023P00007$-977CANCEL THE FOLLOWING: 0001BB QAPP UPDATE YEAR 3 NOT REQUIRED 0001E CLOSE OUT BASE 1001E CLOSE OUT OPTION PERIOD IS FUNDED.
Dec 14, 2023P00006$0SHIFT FUNDS FROM THE FOLLOWING BASE LINE ITEMS TO 1002A 0002A FIELD AUDITS $15,536.01 0002C RI/FS SUPPORT $33,956.96 0003A MEETINGS $16,421.98 THE FOLLOWING LINE ITEMS ARE EXTENDED TO 07/31/2026 0002B TREATABILITY 0002D REMOVAL SUPPORT
Jul 20, 2023P00005$89.0KEXTEND THE PERIOD OF PERFORMANCE TO 07/31/2026 OBLIGATE FUNDING IN THE AMOUNT OF $89,040.00 APPOINT INVOICE APPROVER APPOINT THE ALTERNATE INVOICE APPROVER ADD NET30 TO THE PAYMENT TERMS
Oct 13, 2022P00004$0INCORPORATE REVISED SOW CHANGE IN PROJECT OFFICER
Aug 11, 2022P00003$0INCORPORATE REVISED SOW CHANGE IN PROJECT OFFICER
Jul 2, 2021P00002$0INCORPORATE REVISED SOW
May 15, 2021P00001$0INCORPORATE FINAL PMP AND APPOINT TOCOR
Apr 9, 20210$132.4KESO KURT

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.