Federal contract award

68HE0922F0060

TASK ORDER NO. 68HE0922F0060 (054) IS FOR THE REMEDIAL INVESTIGATION/FEASIBILITY STUDY SULPHUR BANK MERCURY MINE SUPERFUND SITE CLEARLAKE OAKS, CALIFORNIA.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyEnvironmental Protection Agency
OfficeREGION 9 CONTRACTING OFFICE
NAICS562910 — Remediation Services
PSCC214 — A&E Management Engineering Services
Parent award / vehicleEPS91401
Set-asideNot reported
Pricing typeTIME AND MATERIALS
Obligations$3.7M
Current contract value$3.9M
Potential contract value / ceiling$3.9M
Start dateSep 29, 2022
Current end dateJan 27, 2025
Potential end dateJan 27, 2025
Latest award activityJun 26, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 26, 2025P00015$-180.4KSULPHUR BANK MERCURY MINE SUPERFUND SITE OU 1 PRE-DESIGN INVESTIGATION. THE PURPOSE OF THIS MODIFICATION IS TO CLOSEOUT AND DE-OBLIGATE EXCESS FUNDING.
Dec 18, 2024P00014$0SULPHUR BANK MERCURY MINE SUPERFUND SITE OU 1 PRE-DESIGN INVESTIGATION. THE PURPOSE OF THIS CORRECTIVE MODIFICATION FOR MODIFICATION P00013 IS TO OBTAIN CONTRACTOR SIGNATURE IN THE SF30, BLOCK 15B.
Nov 29, 2024P00013$0SULPHUR BANK MERCURY MINE SUPERFUND SITE OU 1 PRE-DESIGN INVESTIGATION. THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE WORK VARIANCE NOTICE 2, DATED 11/22/2024, AND EXTEND THE PERIOD OF PERFORMANCE.

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.