Federal contract award

70Z05023F43000003

DB CONSTRUCTION SERVICES FOR CDC, PLAY AREA TRACEN PETALUMA, CA

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Homeland Security
OfficeFDCC DET SEATTLE(00050)
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicle70Z04718DWHITUR00
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$15.3M
Current contract value$15.3M
Potential contract value / ceiling$15.3M
Start dateNov 29, 2022
Current end dateMar 17, 2026
Potential end dateMar 17, 2026
Latest award activitySep 25, 2025
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 21 of 21 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Sep 25, 2025P00020$477.1KTECHNICAL ACCEPTANCE OF PROPOSAL FOR KITCHEN FFE AND PERIOD OF PERFORMANCE EXTENSION FROM 9.30.2025 TO 3.17.2026
Aug 18, 2025P00019$95.4KTECHNICAL ACCEPTANCE OF WORK FOR REA 6: REPLACE THE DEAD BREAK ELBOWS, AND RE-TEST THE CABLES AND CONDUCTORS.
Jul 29, 2025P00018$23.9KTECHNICAL ACCEPTANCE OF REA 5; THIS MODIFICATION WILL ALSO EXTEND THE DUE DATE FROM 09/11/2025 TO 09/30/2025 AND CONFIRMS THE COR IS MARQUISE STEWART.
May 22, 2025P00017$52.7KACCEPTANCE OF CONTRACTOR PROPOSAL DATED 3.25.25 FOR REA 4, SEWER MH01, MH02, IN THE AMOUNT OF $52,665.43.
Apr 9, 2025P00016$0USCG ACCEPTANCE OF NO COST EXTENSION OF PERIOD OF PERFORMANCE FROM 11SEP2025 TO 24SEP2025 - WEATHER DAYS UP TO DECEMBER 26, 2024, ONLY
Jan 27, 2025P00015$108.6KTECHNICAL ACCEPTANCE OF WT PROPOSAL AMOUNT OF $108,602.21 FOR REA 3_RFI 36.1 UNFORESEEN UTILITIES. THIS MODIFICATION ALSO CORRECTS AN INTERNAL USCG FINANCE ISSUE.
Nov 20, 2024P00014$676.5KPER FSMS0218086, VASSER_WIELAND EMAIL EXCHANGE DATED 10.23.24, ONCE THE A/L IS PROCESSED, FUNDED, AND APPROVED, CONTRACTING WILL DIRECTLY OBLIGATE $676,493.15 USING A/L FUNDS BY ADDING A NEW LINE TO THE AWARD.
Sep 26, 2024P00012$8.7KREA 2 UNFORESEEN PIPE
Sep 26, 2024P00013$207.1KCMR 5, SATURATED SOIL REMOVAL AND REPLACEMENT. PERIOD OF PERFORMANCE EXTENDED TO SEPTEMBER 11, 2025.
Sep 16, 2024P00011$64.6KCMR 4 SEWER LINE RE-ROUTE
Jul 10, 2024P00010$1.3MCMR 3 CONTRUCTION CHANGES
Apr 3, 2024P00009$173.1KREA/CMR CDC 2C PARTS 5 AND 6 ADMINISTRATIVE COSTS: $173,145.25.
Jan 3, 2024P00008$0UNILATERAL MODIFICATION TO ADD COR, EDWARD WIELAND
Nov 27, 2023P00007$98.7KCMR PART 1, UTILITY LOCATION AND TOPOGRAPHIC SURVEY. CMR PART 2, POTHOLING - UTILITY CROSSING DEPTS CMR PART 3, MEASURE EXISTING WASTEWATER MANHOLE INVERTS
Nov 9, 2023P00006$147.3KREA 1, CMR 2C PART 4
Sep 11, 2023P00005$52.6KCMR 2B DESIGN CHARETTE THIS MODIFICATION INCORPORATES THE NOTICE-TO-PROCEED EMAILED TO WHITING TURNER ON 9.7.23.
Aug 8, 2023P00004$42.7KCMR-2A FOR GEOTECHNICAL BORINGS AND REPORTING ONLY, THIS MODIFICATION INCORPORATES A NOTICE TO PROCEED.
Jun 15, 2023P00003$0THIS UNILATERAL MODIFICATION EXTENDS THE SUSPENSION OF WORK ISSUED ON MAY 19, 2023, FOR 30 CALENDAR DAYS (SCHEDULED TO EXPIRE JUNE 18, 2023) TO JUNE 30, 2023. A REQUEST FOR EQUITABLE ADJUSTMENT MAY BE SUBMITTED IN ACCORDANCE WITH FAR REGULATIONS.
May 24, 2023P00002$13.7KCMR 01
Feb 24, 2023P00001$0THIS MODIFICATION IS ISSUED TO IMMEDIATELY SUSPEND GEOTECHNICAL BORINGS UNDER THIS TASK ORDER IN ACCORDANCE WITH FAR 52242-14 SUSPENSION OF WORK (APR 1984), UNTIL FURTHER NOTICE.
Nov 25, 20220$11.8MDB CONSTRUCTION SERVICES FOR CDC, PLAY AREA TRACEN PETALUMA, CA