Federal contract award
DEAC2708RV14800
MANAGEMENT OF THE HANFORD SITE TANK FARMS
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Energy |
| Office | HANFORD FIELD OFFICE |
| NAICS | 562211 — Hazardous Waste Treatment and Disposal |
| PSC | M300 — Operation of Restoration of real property (public or private). All actions necessary to restore, rehabilitate, or reclaim property. |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | COST PLUS AWARD FEE |
| Obligations | $10.6B |
| Current contract value | $11.3B |
| Potential contract value / ceiling | $11.3B |
| Start date | Jun 20, 2008 |
| Current end date | Feb 23, 2025 |
| Potential end date | Feb 23, 2025 |
| Latest award activity | Aug 7, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 200 of 747 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 7, 2026 | 747 | $-11.7M | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Apr 15, 2026 | 746 | $1.8M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Mar 10, 2026 | 745 | $500.0K | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Feb 18, 2026 | 744 | $400.0K | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Dec 1, 2025 | 743 | $600.0K | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Aug 27, 2025 | 742 | $250.0K | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jul 21, 2025 | 741 | $-10.5M | THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jun 18, 2025 | 740 | $-17.0M | THE PURPOSE OF THIS MODIFICATION IS TO DEOBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| May 30, 2025 | 739 | $2.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Apr 25, 2025 | 738 | $1.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE FUNDS PURSUANT TO CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Mar 5, 2025 | 737 | $2.2M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Feb 14, 2025 | 736 | $-5.9M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jan 31, 2025 | 735 | $40.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Dec 20, 2024 | 734 | $39.1M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Dec 16, 2024 | 733 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REMOVE CONTRACT CLOSEOUT FROM SECTION B AND C. |
| Nov 12, 2024 | 732 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE COST AND FEE FOR THE FISCAL YEAR (FY) 2024/2025 CONTRACT EXTENSION CHANGE PROPOSAL, RECONCILE THE ROCKY FLATS AND MOUND BENEFITS PLANS AND INCORPORATE THE FY 2024/2025 PEMP. |
| Oct 24, 2024 | 730 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE REFERENCES TO THE NAMES OF THE U.S. DEPARTMENT OF ENERGY ORGANIZATIONAL UNITS IDENTIFIED IN THE CONTRACT, EFFECTIVE OCTOBER 1, 2024. |
| Oct 24, 2024 | 731 | $51.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Sep 30, 2024 | 727 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT BLOCK 14 IN MOD 726, UPDATE CONTRACT SECTION F, DELIVERIES OR PERFORMANCE, SECTION H, SPECIAL CONTRACT REQUIREMENTS, AND CONTRACT SECTION J, ATTACHMENT J.13, HANFORD SITE STRUCTURES LIST. |
| Sep 26, 2024 | 729 | $23.1M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Sep 20, 2024 | 728 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, ATTACHMENT J.4, PERFORMANCE EVALUATION MEASUREMENT PLAN (PEMP). |
| Aug 26, 2024 | 726 | $113.2M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS, AND TO INCREASE THE FY 2024-2025 NOT-TO-EXCEED VALUE AND INCORPORATE THAT VALUE TO TABLE B.4-1. |
| Jul 30, 2024 | 724 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION H AND CONTRACT SECTION J, ATTACHMENT J.2, REQUIREMENTS SOURCES AND IMPLEMENTING DOCUMENTS. |
| Jul 30, 2024 | 725 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CORRECT CONTRACT SECTION J, ATTACHMENT J.2, REQUIREMENTS SOURCES AND IMPLEMENTING DOCUMENTS. |
| Jun 18, 2024 | 723 | $210.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jun 5, 2024 | 722 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, ATTACHMENT J.10 |
| May 8, 2024 | 721 | $56.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| May 2, 2024 | 716 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.6 |
| Apr 4, 2024 | 720 | $72.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Apr 2, 2024 | 719 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE FY 2024-2025 NOT-TO-EXCEED VALUE AND INCORPORATE THAT VALUE TO TABLE B.4-1. |
| Mar 25, 2024 | 718 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION H AND CONTRACT SECTION J, ATTACHMENT J.2, REQUIREMENTS SOURCES AND IMPLEMENTING DOCUMENTS. |
| Feb 9, 2024 | 717 | $85.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS AND INCORPORATE THE FY 24-25 NTE VALUE FROM MOD 708. |
| Dec 18, 2023 | 714 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION J, ATTACHMENTS J.2, J.3, J.5 & J.13. |
| Dec 12, 2023 | 712 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION H. |
| Dec 12, 2023 | 715 | $116.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Nov 14, 2023 | 713 | $14.8M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Oct 13, 2023 | 711 | $85.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Sep 27, 2023 | 709 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, ATTACHMENT J.4 |
| Sep 27, 2023 | 710 | $5.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Sep 19, 2023 | 708 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE FOR UP TO 24 MONTHS AND PROVIDE A NOT-TO-EXCEED TO ALLOW WORK TO CONTINUE THROUGH CONTRACT NEGOTIATIONS. |
| Sep 18, 2023 | 705 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, ATTACHMENT J.2 & J.13. |
| Sep 12, 2023 | 707 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE CP-23-003, UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS, AND UPDATE ATTACHMENT J.4. |
| Aug 17, 2023 | 706 | $1.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jul 28, 2023 | 701 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION H, SPECIAL CONTRACT REQUIREMENTS AND CONTRACT SECTION I, CONTRACT CLAUSES. |
| Jul 25, 2023 | 704 | $171.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jul 13, 2023 | 703 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.6, ATTACHMENT J.9, AND ATTACHMENT J.10. |
| Jun 20, 2023 | 702 | $1.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| May 10, 2023 | 700 | $5.2M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Apr 27, 2023 | 699 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE CP-22-002, CP-22-007, AND UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS. |
| Apr 12, 2023 | 698 | $180.3M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Apr 10, 2023 | 696 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO (1) REVISE ATTACHMENT J.4, TO INCORPORATE THE FISCAL YEARS 2022-2023 PERFORMANCE EVALUATION AND MEASUREMENT PLAN REV. 4 AND (2) UPDATE THE B.4-1 TABLE. |
| Mar 22, 2023 | 697 | $55.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Feb 24, 2023 | 694 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION H AND CONTRACT SECTION J, ATTACHMENT J.2, REQUIREMENTS SOURCES AND IMPLEMENTING DOCUMENTS, TO REVISE DOE ORDERS IN THE CONTRACT. |
| Feb 23, 2023 | 695 | $50.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jan 18, 2023 | 693 | $85.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jan 4, 2023 | 692 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE NOT-TO-EXCEED (NTE) FOR THE FISCAL YEAR 2022-2023 ADDITIONAL WORK SCOPE ISSUED IN MODIFICATION 666 BY $750,000.00. |
| Dec 29, 2022 | 691 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE 200 WEST AREA TANK FARMS RISK MANAGEMENT PROJECT AND UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS. |
| Oct 26, 2022 | 690 | $160.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Oct 20, 2022 | 689 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO FORMALIZE THE CONTRACTING OFFICERS EMAIL OF SEPTEMBER 21, 2022, AUTHORIZING WASHINGTON RIVER PROTECTION SOLUTIONS, LLC (WRPS) TO COMMENCE WORK ON THE 200W AREA RISK MANAGEMENT PROJECT. |
| Oct 17, 2022 | 688 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE NOT-TO-EXCEED (NTE) FOR THE LOW-ACTIVITY WASTE PRETREATMENT SYSTEM PROJECT SUB-PROJECT TWO SCOPE ISSUED IN MODIFICATION 680. |
| Sep 26, 2022 | 687 | $7.4M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT, DE-OBLIGATE PERSONAL TIME BANK LIABILITY FUNDS AND UPDATE CONTRACT SECTION B.3, OBLIGATION AND AVAILABILITY OF FUNDS. |
| Aug 24, 2022 | 686 | $201.1M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND REVISE CONTRACT SECTION B.3(A) OBLIGATION AND AVAILABILITY OF FUNDS. |
| Aug 16, 2022 | 685 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE LEAD CONTRACTING OFFICER BY UPDATING G.1(A) IN CONTRACT SECTION G. |
| Aug 15, 2022 | 684 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENTS J.2, TO ADD DOE O 243.1C AND ATTACHMENT J.3A, TO UPDATE INTERFACE 14. |
| Jul 21, 2022 | 683 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO (1) UPDATE CONTRACT CLAUSE I.29, FAR REFERENCE 52.219-9 AND (2) REVISE CONTRACT SECTION J, ATTACHMENT J.6, SMALL BUSINESS SUBCONTRACTING PLAN, TO INCORPORATE THE UPDATED SMALL BUSINESS SUBCONTRACTING PLAN IN ITS |
| Jul 14, 2022 | 682 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO (1) REVISE ATTACHMENT J.4, TO INCORPORATE THE FISCAL YEARS 2022-2023 PERFORMANCE EVALUATION AND MEASUREMENT PLAN REV. 3 AND (2) UPDATE THE B.4-1 TABLE. |
| Jun 30, 2022 | 681 | $52.3M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND REVISE CONTRACT SECTION B.3(A) OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jun 21, 2022 | 679 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, LIST OF ATTACHMENTS, ATTACHMENT J.3A HANFORD SITE SERVICES AND INTERFACE REQUIREMENTS TO ADD INTERFACE NUMBER 33. |
| Jun 21, 2022 | 680 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE A NOT TO EXCEED AMOUNT OF $500,000.00 TO ALLOW WRPS TO BEGIN PERFORMANCE ON THE LOW-ACTIVITY WASTE PRETREATMENT SYSTEM PROJECT SUB-PROJECT SCOPE OF WORK PER RFP LETTER 22-TF-001660 DATED 6/15/2022. |
| Jun 2, 2022 | 678 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE CONTRACT COSTS FOR FY2021 COVID-19 REA AND UPDATE SECTION B. |
| Jun 1, 2022 | 677 | $64.5M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND REVISE CONTRACT SECTION B.3(A) OBLIGATION AND AVAILABILITY OF FUNDS. |
| May 30, 2022 | 675 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE UNDISTRIBUTED BUDGET SCOPE REMOVAL AND REVISE SECTION B-SUPPLIES OR SERVICES AND PRICES/COSTS TABLE B.4-1. |
| May 26, 2022 | 676 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.2, REQUIREMENTS SOURCES AND IMPLEMENTING DOCUMENTS, TO REVISE, ADD, AND DELETE DOE ORDERS IN THE CONTRACT. |
| May 10, 2022 | 674 | $73.7M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND REVISE CONTRACT SECTION B.3(A) OBLIGATION AND AVAILABILITY OF FUNDS. |
| May 5, 2022 | 672 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, ATTACHMENT J.8, ADVANCE UNDERSTANDING OF COSTS, TO REVISE THE WINTER PROTECTIVE CLOTHING CLARIFICATION STATEMENT FOUND ON PAGE J.8-6. |
| Apr 28, 2022 | 673 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.2,REQUIREMENTS SOURCES AND IMPLEMENTING DOCUMENTS, TO INCORPORATE DOE ORDER 471.6, CHANGE 3 AND DOE ORDER 550.1, CHANGE 1 AT NO COST TO THE GOVERNMENT. |
| Apr 13, 2022 | 671 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION H, SPECIAL CONTRACT REQUIREMENTS, TO UPDATE THE KEY PERSONNEL UNDER H.15(F) KEY PERSONNEL FOR THIS CONTRACT. |
| Apr 12, 2022 | 670 | $64.7M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND REVISE CONTRACT SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS. |
| Apr 7, 2022 | 669 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J TOC, ATTACHMENT J.4, FY 22/23 PEMP, DELETE ATTACHMENT J.17, AND UPDATE THE SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS B.4-1 TABLE. |
| Apr 4, 2022 | 662 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, ATTACHMENT J.8, ADVANCE UNDERSTANDING OF COSTS, TO ADD CARES ACT EFFECTIVE DATE AND ALLOW ADMINISTRATIVE LEAVE FOR COVID-19 BOOSTER SHOTS |
| Mar 23, 2022 | 668 | $31.1M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND REVISE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Mar 18, 2022 | 667 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE SECTION H, ATTACHMENT J.2, AND ATTACHMENT J10. |
| Mar 2, 2022 | 666 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE A NOT-TO-EXCEED AMOUNT OF $750,000 TO ALLOW WRPS TO BEGIN PERFORMANCE ON THE WASTE FEED DELIVERY REDUNDANT POWER UPGRADES, VERIFICATION TANK COATING, AND LIQUID EFFLUENT RETENTION FACILITY (LERF) LEGAC |
| Feb 10, 2022 | 665 | $2.9M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Feb 2, 2022 | 663 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION B, SECTION J, TABLE OF CONTENTS AND SECTION J, ATTACHMENT J.17 FOR THE FY 2022/2023 CONTRACT EXTENSION. |
| Feb 1, 2022 | 664 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE SECTION J: LIST OF ATTACHMENTS J.3.A HANFORD SITE SERVICES AND INTERFACE REQUIREMENTS MATRIX. |
| Jan 12, 2022 | 660 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION C, SECTION H AND SECTION J. |
| Dec 29, 2021 | 661 | $140.6M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Dec 28, 2021 | 656 | $0 | THE PURPOSE OF THIS MOD IS TO (1) CORRECT MOD 632 BY UPDATING CLAUSE I.65A UNDER CONTRACT SECTION I TITLED CONTRACT CLAUSES AND (2) CORRECT MOD 345 BY UPDATING TABLE J.2.9 UNDER CONTRACT SECTION J.2 TITLED REQUIREMENTS SOURCES AND IMPLEMENTING DOCUME |
| Dec 28, 2021 | 657 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE ATTACHMENT J.4, PERFORMANCE EVALUATION AND MEASUREMENT PLAN, TO INCORPORATE REVISION 1. |
| Dec 21, 2021 | 658 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE 242A BOILER ANNEX WORK SCOPE, AND REVISE SECTION B-SUPPLIES OR SERVICES AND PRICES/COSTS AND SECTION C- STATEMENT OF WORK. |
| Dec 20, 2021 | 659 | $0 | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO UPDATE ATTACHMENT J.8, ADVANCE UNDERSTANDING OF COSTS, TO ADD ADMINISTRATIVE LEAVE TO ACCOMPANY FAMILY MEMBERS TO RECEIVE COVID-19 VACCINE. |
| Nov 8, 2021 | 655 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE ATTACHMENT J.3.A, HANFORD SITE SERVICES AND INTERFACE REQUIREMENTS MATRIX BY REVISING TABLES 37 AND 38, AND FORMATTING TABLE 4 FROM TWO PAGES TO ONE. |
| Oct 21, 2021 | 654 | $125.8M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Oct 8, 2021 | 653 | $0 | EO14042 - THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FAR 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS, (OCT 2021) (DEVIATION) INTO CONTRACT SECTION I. |
| Oct 4, 2021 | 652 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE 200 WEST AREA ANALYSIS OF ALTERNATIVES PROJECT AND UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS. |
| Sep 30, 2021 | 650 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE FY 22/23 PEMP INTO ATTACHMENT J.4, PEMP; AND UPDATE FY 22/23 FEE IN ATTACHMENT J.17, POST FY 2021 COST AND FEE TABLE. |
| Sep 28, 2021 | 651 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE NTE FOR THE 242A BOILER ANNEX FROM $400,000.00 TO $800,000.00. |
| Sep 23, 2021 | 648 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE NTE FOR THE 200 WEST AREA ANALYSIS OF ALTERNATIVES PROJECT FROM FROM $600,000 TO $687,000. |
| Sep 23, 2021 | 649 | $4.8M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT, DE-OBLIGATE PERSONAL TIME BANK LIABILITY FUNDS AND UPDATE CONTRACT SECTION B.3, OBLIGATION AND AVAILABILITY OF FUNDS. |
| Sep 21, 2021 | 647 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE ATTACHMENT J.3.A, HANFORD SITE SERVICES AND INTERFACE REQUIREMENTS MATRIX TABLES 91, 94, 95 AND 98 AND CONTRACT CLAUSE H.15 KEY PERSONNEL. |
| Sep 17, 2021 | 646 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE SECTION C STATEMENT OF WORK, TO REMOVE THE 222-S LAB WORK SCOPE DEFINITIZED ON MOD 641. |
| Sep 15, 2021 | 645 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE FOR UP TO 24 MONTHS AND PROVIDE A NOT-TO-EXCEED TO ALLOW WORK TO CONTINUE THROUGH CONTRACT NEGOTIATIONS. |
| Sep 1, 2021 | 643 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION B, TABLE B.4-1 AVAILABLE FEE FOR FISCAL YEARS 2019 AND 2020 AND SECTION J, ATTACHMENT J.17 POST FY 2021 COST AND FEE TABLE. |
| Sep 1, 2021 | 644 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.4, TO INCORPORATE THE FISCAL YEAR 2021 PERFORMANCE EVALUATION AND MEASUREMENT PLAN REV. 3 AND UPDATE THE B.4-1 TABLE FEE AVAILABLE. |
| Aug 19, 2021 | 641 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE 222-S LABORATORY SCOPE REMOVAL AND TEST BED INITIATIVE DEMONSTRATION CHANGE ORDERS AND UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS. |
| Aug 19, 2021 | 642 | $29.8K | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS. |
| Jul 27, 2021 | 637 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.4, PERFORMANCE EVALUATION AND MEASUREMENT PLAN, REVISION 1 AND UPDATE FEE AVAILABLE ON THE B.4-1 TABLE. |
| Jul 27, 2021 | 640 | $178.2M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B, SUPPLIES OR SERVICES & PRICES/COSTS. |
| Jul 26, 2021 | 639 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE NTE FOR THE 242-A BOILER CHANGE PROPOSAL, FROM $125,000 TO $400,000. |
| Jul 23, 2021 | 636 | $0 | COVID-19 ACTION. THE PURPOSE FOR THIS MODIFICATION IS INCREASE COSTS PER THE COVID-19 REQUEST FOR EQUITABLE ADJUSTMENT AND REVISE THE B-4 TABLE |
| Jul 22, 2021 | 635 | $0 | THE PURPOSE FOR THIS MODIFICATION IS TO REVISE CONTRACT SECTION H, SPECIAL CONTRACT REQUIREMENTS, REQUIREMENT H.11, WORKFORCE RESTRUCTURING. |
| Jul 21, 2021 | 638 | $0 | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, ATTACHMENT J.8, ADVANCE UNDERSTANDING OF COSTS. |
| Jul 14, 2021 | 634 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCREASE THE VALUE OF THE CONTRACT FOR THE FIRE PROTECTION PROGRAM EXPANSION BY $340,000.00 AND CORRECT THE B.4-1 COST AND FEE TABLE. |
| Jul 7, 2021 | 633 | $0 | THE PURPOSE FOR THIS MODIFICATION IS TO CORRECT A NARRATIVE NUMERICAL ERROR ON MOD 631 CONTINUATION PAGE |
| Jul 1, 2021 | 631 | $1.8M | THE PURPOSE OF THIS MODIFICATION IS TO ADD INCREMENTAL FUNDING AND REVISE CONTRACT SECTION B SUPPLIES OR SERVICES AND PRICES/COSTS |
| Jul 1, 2021 | 632 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION H, SPECIAL CONTRACT REQUIREMENTS, AND CONTRACT SECTION I, CONTRACT CLAUSES, AT NO ADDITIONAL COST TO THE GOVERNMENT. |
| Jun 14, 2021 | 629 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE TX- BARRIER AND REVISE CONTRACT SECTION B, TABLE B.4-1, CONTRACT COST AND CONTRACT FEE |
| Jun 2, 2021 | 630 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE SUBCONTRACTING PLAN IN CONTRACT SECTION J, ATTACHMENT J.6. |
| May 25, 2021 | 627 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE A NOT-TO-EXCEED FOR THE WEST AREA TANK FARMS RISK MANAGEMENT PROJECT. |
| May 25, 2021 | 628 | $-2.9M | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS FOR THE PERSONAL TIME BANK AND UPDATE CONTRACT SECTION B. |
| May 17, 2021 | 626 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO (1) UPDATE CONTACT CLAUSE G.1 TITLED CONTRACT ADMINISTRATION AND (2) UPDATE CONTRACT SECTION J, ATTACHMENT J.2, CHANGING DOE ORDER 205.1A TO DOE ORDER 205.1B. |
| May 5, 2021 | 623 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE LEGACY PENSION AND BENEFIT PLAN MANAGEMENT SCOPE IN CONTRACT SECTIONS H AND C DUE TO THE SCOPE TRANSITION TO HANFORD MISSION ESSENTIAL SERVICES CONTRACT. |
| Apr 29, 2021 | 625 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO AUTHORIZE A NOT-TO-EXCEED FOR THE 242-A BOILER SCOPE. |
| Apr 28, 2021 | 624 | $-32.7M | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS FOR THE ADMINISTRATION OF THE HANFORD LEGACY BENEFIT PROGRAMS. AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Apr 20, 2021 | 622 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ISSUE AN INCREASE OF THE NOT-TO-EXCEED ISSUED FOR THE 241-TX TANK FARM BARRIER SCOPE. |
| Apr 15, 2021 | 620 | $0 | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.8, ADVANCE UNDERSTANDING OF COSTS, TO INCORPORATE AUTHORIZATION FOR CONTRACTOR PERSONNEL TO USE UP TO FOUR HOURS ADMINISTRATIVE LEAVE PER DOSE TO GET VACCINATED |
| Apr 15, 2021 | 621 | $194.6M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Apr 12, 2021 | 619 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.3, SITE SERVICE AND INTERFACE REQUIREMENTS MATRIX TO ALLOW FOR DAY ONE OPERATIONS OF THE NEW 222-S LABORATORY CONTRACT |
| Apr 8, 2021 | 618 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NOT-TO-EXCEED FOR $600,000 FOR THE LOW-LEVEL WASTE OFFSITE DISPOSAL FISCAL YEAR 2021 SCOPE OF WORK. |
| Apr 5, 2021 | 617 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTION J, ATTACHMENT J.2 TO UPDATE DOE ORDER 442.1A TO 442.1B |
| Mar 31, 2021 | 616 | $99.9M | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION B TO: (1) OBLIGATE INCREMENTAL FUNDS (2) INCORPORATE FY21 PEMP REV. 1 AND (3) UPDATE TABLE B.4-1 AVAILABLE FEE FOR FY20 AND FY21. |
| Mar 29, 2021 | 615 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE FISCAL YEAR 2021 CONTRACT EXTENSION AND UPDATE CONTRACT SECTION B. |
| Mar 22, 2021 | 613 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO (1) DEFINITIZE WTP SPARE PARTS AND (2) UPDATE CONTRACT SECTIONS B AND J.17 TO UPDATE NEGOTIATED COST AND FEE. |
| Mar 18, 2021 | 614 | $0 | COVID-19 - THE PURPOSE OF THIS CONTRACT MODIFICATION TO REVISE CONTRACT SECTION H, CLAUSE H-61. |
| Mar 10, 2021 | 612 | $37.7M | THE PURPOSE OF THIS CONTRACT MODIFICATION TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A). |
| Mar 8, 2021 | 610 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE: (1) SECTION J, ATTACHMENT J.3, HANFORD SITE SERVICES AND INTERFACE REQUIREMENTS MATRIX AND (2) SECTION J, ATTACHMENT J.13, HANFORD SITE STRUCTURE LIST. |
| Feb 17, 2021 | 611 | $0 | THE PURPOSE OF THIS ADMINISTRATIVE MODIFICATION IS TO UPDATE CONTRACT SECTION J, LIST OF ATTACHMENTS, ATTACHMENT J.10, WAGE DETERMINATIONS SERVICE CONTRACT ACT AND DAVIS BACON ACT. |
| Jan 27, 2021 | 609 | $0 | THE PURPOSE OF THIS ADMINISTRATIVE MODIFICATION IS TO CORRECT CONTRACT SECTION H, SPECIAL CONTRACT REQUIREMENTS |
| Jan 26, 2021 | 607 | $79.3M | THE PURPOSE OF THIS CONTRACT MODIFICATION TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A). |
| Jan 25, 2021 | 608 | $0 | THE PURPOSE OF THIS ADMINISTRATIVE MODIFICATION IS TO REVISE CONTRACT SECTION H, SPECIAL CONTRACT REQUIREMENTS, AND CONTRACT SECTION J, ATTACHMENT J.5, PERFORMANCE GUARANTEE AGREEMENT. |
| Jan 20, 2021 | 606 | $0 | THE PURPOSE OF THIS CONTRACT MODIFICATION TO ISSUE A FORMALIZE A NOT-TO-EXCEED OF $100,000 FOR WTP SPARE PARTS ACQUISITION. |
| Jan 15, 2021 | 604 | $987.0K | THE PURPOSE OF THIS CONTRACT MODIFICATION TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A). |
| Jan 13, 2021 | 605 | $0 | THE PURPOSE OF THIS CONTRACT MODIFICATION TO UPDATE CONTRACT SECTION J, ATTACHMENT J.6, SMALL BUSINESS SUBCONTRACTING PLAN |
| Dec 30, 2020 | 603 | $0 | COVID-19 - THE PURPOSE OF THIS CONTRACT MODIFICATION TO REVISE CONTRACT SECTION H, CLAUSE H-61. |
| Dec 23, 2020 | 602 | $0 | COVID-19 - THE PURPOSE OF THIS CONTRACT MODIFICATION TO REVISE CONTRACT SECTION H, CLAUSE H-61. |
| Dec 14, 2020 | 601 | $0 | COVID-19 - THE PURPOSE OF THIS CONTRACT MODIFICATION TO REVISE CONTRACT SECTION H, CLAUSE H-61. |
| Dec 9, 2020 | 600 | $61.2M | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A). |
| Dec 3, 2020 | 599 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION H, SPECIAL CONTRACT REQUIREMENTS, REQUIREMENT H.57, LIST OF CONTRACTING OFFICERS REPRESENTATIVES DESIGNATED FOR THIS CONTRACT. |
| Nov 24, 2020 | 598 | $200.0K | THE PURPOSE OF THIS MODIFICATION IS OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3.(A). |
| Nov 17, 2020 | 597 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, LIST OF ATTACHMENTS, ATTACHMENT J.2, REQUIREMENT SOURCES AND IMPLEMENTING DOCUMENTS. |
| Nov 6, 2020 | 593 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO (1) DEFINITIZE COST AND FEE FOR THE ETF AND (2) UPDATE CONTRACT SECTION B. |
| Nov 6, 2020 | 594 | $500.0K | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS AND UPDATE CONTRACT SECTION B.3(A). |
| Nov 5, 2020 | 596 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J.2, REQUIREMENT SOURCES AND IMPLEMENTING DOCUMENTS TO ADD DOE ORDER 486.1A, FOREIGN GOVERNMENT SPONSORED OR AFFILIATED ACTIVITIES. |
| Nov 4, 2020 | 595 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NOT-TO-EXCEED FOR THE 241-TX TANK FARM BARRIER. |
| Oct 29, 2020 | 592 | $1.3M | THE PURPOSE OF THIS MODIFICATION IS TO (1) OBLIGATE INCREMENTAL FUNDS, (2) CHANGE THE LEAD CONTRACTING OFFICER, AND (3) UPDATE CONTRACT SECTION B.3(A)&SECTION G. |
| Oct 15, 2020 | 591 | $80.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS |
| Oct 1, 2020 | 590 | $0 | COVID-19 - THE PURPOSE OF THIS CONTRACT MODIFICATION TO REVISE CONTRACT SECTION H, CLAUSE H-61. |
| Sep 30, 2020 | 588 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE THE PERFORMANCE EVALUATION AND MEASUREMENT PLAN (PEMP) FOR FISCAL YEAR (FY) 2021. THIS MODIFICATION REPLACES SECTION J, ATTACHMENT J.4, IN ITS ENTIRETY. |
| Sep 25, 2020 | 589 | $0 | COVID-19 - THE PURPOSE OF THIS CONTRACT MODIFICATION IS ADMINISTRATIVE, PER FAR 43.103 (B)(3), TO PROVIDE INFORMATION ALLOWING THE PARTIAL STOP WORK ORDER TO EXPIRE ON SEP 30, 2020. |
| Sep 24, 2020 | 587 | $0 | THE PURPOSE OF THIS CONTRACT MODIFICATION IS TO DECREASE FY 2020 SCOPE AND COST FOR TANK-SIDE CESIUM REMOVAL SYSTEM DEMONSTRATION SUBPROJECT AND UPDATE CONTRACT SECTION B. |
| Sep 23, 2020 | 586 | $6.2M | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS INCLUDING COVID-19 FUNDS AND UPDATE CONTRACT SECTION B.3(A). |
| Sep 22, 2020 | 584 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE FOR UP TO ONE YEAR, PROVIDE A NOT-TO-EXCEED OF $266M FOR THIS EXTENSION, AND MAKE AN ADMINISTRATIVE CHANGE TO PARAGRAPH B.2. |
| Sep 22, 2020 | 585 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE REVISION 3 OF THE PERFORMANCE EVALUATION AND MEASUREMENT PLAN (PEMP) FOR FISCAL YEAR 2020. |
| Sep 18, 2020 | 583 | $4.2M | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE INCREMENTAL FUNDING, OBLIGATE COVID-19 INCREMENTAL FUNDS, OBLIGATE INCREMENTAL FUNDS, AND UPDATE CONTRACT SECTION B.3(A). |
| Sep 17, 2020 | 582 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE LOW LEVEL WASTE (LLW) OFFSITE DISPOSAL (TEST BED INITIATIVE) AND UPDATE CONTRACT SECTION B, TABLE B.4-1, CONTRACT COST AND CONTRACT FEE. |
| Aug 20, 2020 | 581 | $117.8M | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO (1) OBLIGATE COVID-19 INCREMENTAL FUNDS, (2) OBLIGATE IDAHO LFRG SUPPORT FUNDS, AND (3) UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Aug 17, 2020 | 580 | $-81.7M | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO (1) DE-OBLIGATE FUNDS SO THEY CAN BE RECODED FOR COVID-19 (2) OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND (3) UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Aug 12, 2020 | 579 | $0 | THE PURPOSE OF THIS MODIFICATION IS DEFINITIZE THE LIQUID EFFLUENT RETENTION FACILITY (LERF) DOCUMENTED SAFETY ANALYSIS (DSA) AND UPDATE CONTRACT SECTION B. |
| Jul 27, 2020 | 578 | $182.7M | THE PURPOSE OF THIS MODIFICATION IS ADD INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B.3(A), OBLIGATION AND AVAILABILITY OF FUNDS. |
| Jul 21, 2020 | 577 | $0 | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PARTIAL STOP WORK ORDER THAT WAS INCORPORATED INTO THE CONTRACT IN MODIFICATION NUMBER 575 FOR AN ADDITIONAL 70 DAYS, THROUGH 9/30/2020. |
| Jun 26, 2020 | 576 | $700.0K | THE PURPOSE OF THIS MODIFICATION IS ADD INCREMENTAL FUNDING AND INCORPORATE NEW SPECIAL FINANCIAL INSTITUTE ACCOUNT AGREEMENT CONTRACT SECTION J.9. |
| Jun 22, 2020 | 574 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE REVISION 2 OF THE PERFORMANCE EVALUATION AND MEASUREMENT PLAN (PEMP) FOR FISCAL YEAR 2020. |
| Jun 17, 2020 | 575 | $0 | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PARTIAL STOP WORK ISSUED PURSUANT TO FAR 52.242-15, STOP WORK ORDER (AUG 1989) - ALTERNATE 1 (APR 1984). |
| Jun 16, 2020 | 572 | $0 | COVID-19 - THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTIONS H TO INCLUDE THE COVID 19 CARES ACT CLAUSE. |
| May 20, 2020 | 573 | $3.3M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B |
| Apr 30, 2020 | 571 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE TANK SIDE CESIUM REMOVAL (TSCR) DEMONSTRATION PROJECT ADDITIONAL FILTER TESTING AND UPDATE CONTRACT SECTION B. |
| Apr 23, 2020 | 569 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO REVISE CONTRACT SECTIONS H TO INCLUDE THE COVID 19 CARES ACT CLAUSE. |
| Apr 23, 2020 | 570 | $7.2M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Apr 21, 2020 | 568 | $0 | THE PURPOSE OF THIS ADMIN MODIFICATION IS TO UPDATE SECTION F, DELIVERIES OR PERFORMANCE; SECTION H CONTRACTING OFFICER LIST; AND SECTION J.6 SMALL BUSINESS SUBCONTRACTING PLAN |
| Apr 8, 2020 | 560 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE SECTION J LIST OF ATTACHMENTS, ATTACHMENT J.3, HANFORD SITE SERVICES AND INTERFACE REQUIREMENTS MATRIX. |
| Apr 8, 2020 | 567 | $295.2M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Apr 6, 2020 | 565 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE COST&FEE FOR UNDISTRIBUTED BUDGET DELETIONS AND UPDATE CONTRACT SECTION B. |
| Apr 1, 2020 | 566 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO FORMALIZE THE NOT-TO-EXCEED ISSUED TO WASHINGTON RIVER PROTECTION SOLUTIONS, LLC FOR THE ADDITIONAL EFFLUENT TEST FACILITY FISCAL YEAR 2020 SCOPE OF WORK. |
| Mar 30, 2020 | 564 | $2.3M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Mar 27, 2020 | 551 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO: (1) UPDATE SECTION J, ATTACHMENT J.13, HANFORD SITE STRUCTURE LIST AND (2) UPDATE SECTION J, ATTACHMENT J.14, HANFORD WASTE SITE ASSIGNMENT LIST. |
| Mar 19, 2020 | 562 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE REQUEST FOR EQUITABLE ADJUSTMENT (REA) REGARDING THE VAPOR IMPACTS ON THE SX FARM BARRIER CONSTRUCTION. |
| Mar 16, 2020 | 561 | $27.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Mar 12, 2020 | 563 | $0 | THE PURPOSE OF THIS MODIFICATION IS FORMALIZE A NOT-TO-EXCEED ISSUED PREVIOUSLY VIA ORP LETTER 20-TPD-0007, DATED 2/5/2020. |
| Mar 2, 2020 | 557 | $0 | THE PURPOSE OF THIS MODIFICATION IS FORMALIZE A NOT-TO-EXCEED ISSUED PREVIOUSLY VIA ORP CONTRACTING OFFICER EMAIL. |
| Feb 26, 2020 | 559 | $59.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Feb 24, 2020 | 558 | $2.2M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Feb 11, 2020 | 552 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO UPDATE CONTRACT SECTION J, LIST OF ATTACHMENTS, ATTACHMENT J.10 WAGE DETERMINATIONS - SERVICE CONTRACT ACT AND DAVIS-BACON ACT. |
| Feb 5, 2020 | 556 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE THE FISCAL YEAR 2020 CONTRACT EXTENSION AND ADDITIONAL FY20 WORK SCOPE, INCORPORATE PEMP REV 1, DELETE J.17 TABLE, AND UPDATE SECTION B. |
| Jan 28, 2020 | 554 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE TWO NEGOTIATED CHANGES (CYBER SECURITY AND LERF BASIN 41) AND UPDATE CONTRACT SECTION B, COST&FEE. |
| Jan 28, 2020 | 555 | $62.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Jan 21, 2020 | 553 | $9.0M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Jan 7, 2020 | 550 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A NOT-TO-EXCEED INCREASE OF $58M FOR THE FY2020 CONTRACT EXTENSION. |
| Dec 19, 2019 | 549 | $50.7M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |
| Nov 20, 2019 | 548 | $1.9M | THE PURPOSE OF THIS MODIFICATION IS TO OBLIGATE INCREMENTAL FUNDS TO THE CONTRACT AND UPDATE CONTRACT SECTION B. |