Federal contract award

FA465425C0010

THE PROJECT REQUIRES REPAIR OF AIRFIELD PAVEMENTS AT GRISSOM AIR RESERVE BASE, INDIANA. WORK SHALL INCLUDE DEMOLITION OF EXISTING FAILED CONCRETE PAVEMENT SECTIONS, HAULING OF MATERIAL OFF-SITE AND PLACING AND FINISHING NEW CONCRETE PAVEMENT.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeFA4654 434 CONF LGC
NAICS237310 — Highway, Street, and Bridge Construction
PSCZ2BD — REPAIR OR ALTERATION OF AIRPORT RUNWAYS AND TAXIWAYS
Parent award / vehicleNot reported
Set-asideWOMEN OWNED SMALL BUSINESS
Pricing typeFIRM FIXED PRICE
Obligations$505.1K
Current contract value$505.1K
Potential contract value / ceiling$505.1K
Start dateOct 10, 2025
Current end dateMay 29, 2026
Potential end dateMay 29, 2026
Latest award activityApr 21, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 3 of 3 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 21, 2026P00002$265.7KTHE PROJECT REQUIRES REPAIR OF AIRFIELD PAVEMENTS AT GRISSOM AIR RESERVE BASE, INDIANA. WORK SHALL INCLUDE DEMOLITION OF EXISTING FAILED CONCRETE PAVEMENT SECTIONS, HAULING OF MATERIAL OFF-SITE AND PLACING AND FINISHING NEW CONCRETE PAVEMENT.
Apr 2, 2026P00001$0THE PROJECT REQUIRES REPAIR OF AIRFIELD PAVEMENTS AT GRISSOM AIR RESERVE BASE, INDIANA. WORK SHALL INCLUDE DEMOLITION OF EXISTING FAILED CONCRETE PAVEMENT SECTIONS, HAULING OF MATERIAL OFF-SITE AND PLACING AND FINISHING NEW CONCRETE PAVEMENT.
Sep 30, 20250$239.5KTHE PROJECT REQUIRES REPAIR OF AIRFIELD PAVEMENTS AT GRISSOM AIR RESERVE BASE, INDIANA. WORK SHALL INCLUDE DEMOLITION OF EXISTING FAILED CONCRETE PAVEMENT SECTIONS, HAULING OF MATERIAL OFF-SITE AND PLACING AND FINISHING NEW CONCRETE PAVEMENT.