Federal contract award

W52P1J08C0042

BASIC AWARD FOR 20MM PGU-SERIES AMMUNITION

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW0DA US ARMY SUSTAINMENT CMD
NAICS332993 — Ammunition (except Small Arms) Manufacturing
PSC1305 — Ammunition, through 30 mm
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$182.4M
Current contract value$182.4M
Potential contract value / ceiling$182.4M
Start dateMar 13, 2014
Current end dateJun 30, 2014
Potential end dateJun 30, 2014
Latest award activityMar 13, 2014
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 61 of 61 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 3, 2017A00001$0BASIC AWARD FOR 20MM PGU-SERIES AMMUNITION
Mar 3, 2017A00002$0BASIC AWARD FOR 20MM PGU-SERIES AMMUNITION. MODIFICATION A00002 WAS ISSUED TO MAKE MINOR ADJUSTMENTS TO THE ORDER QUANTITY AND OBLIGATIONS FOR TWO ITEMS TO REFLECT WHAT ACTUALLY SHIPPED AND ALLOW THE CONTRACT TO BE CLOSED.
Apr 7, 2014P00055$0MEDIUM CALIBER CARTRIDGES
Mar 13, 2014P00054$0MEDIUM CALIBER CARTRIDGES
Mar 4, 2014P00053$-0MEDIUM CALIBER CARTRIDGES
Feb 12, 2014P00052$0CHANGE DELIVERY SCHEDULE
Feb 12, 2014P00052$-6.0KCHANGE DELIVERY SCHEDULE
Nov 6, 2013P00050$0MEDIUM CALIBER CARTRIDGES
Aug 15, 2013P00049$0MEDIUM CALIBER CARTRIDGES
May 9, 2013P00047$-940INCORPORATE COST REDUCTIONS DUE TO NITROCELLULOSE RE-OPENER CLAUSE.
May 9, 2013P00047$-666INCORPORATE COST REDUCTIONS DUE TO NITROCELLULOSE RE-OPENER CLAUSE.
May 2, 2013P00048$0MEDIUM CALIBER CARTRIDGES
Dec 13, 2012P00046$99.3K20MM CARTRIDGES
Nov 5, 2012P00045$2.2KINCREASE CLIN 3001AE DUE TO FEWER AIR FORCE SAMPLE SHIPMENTS BEING REQUIRED.
Oct 23, 2012P00044$-2.2KCORRECT SHIPPING INFO FOR CLIN 4001AA AND UPDATE CLAUSES.
Aug 30, 2012P00043$22.9MEXERCISE OPTION 4.
Jul 18, 2012P00042$-21.5KREDUCE THE AMOUNT OF THE PGU-28/30 FAAT ON CLIN 3004AA DUE TO LESS TESTING BEING REQUIRED.
Jun 18, 2012P00041$0INCORPORATE ECP R12S5035.
Jun 13, 2012P00040$0ADD CLIN 9029AA FOR AIR FORCE SAMPOLE SHIPMENTS TO EGLIN AFB FROM CLIN 9002AA.
Jun 7, 2012ARZ998$0REVISE DELIVERY SCHEDULES. DELETE CDRL 0002. CHANGE DEPOT SHIP TO DOC NUMBERS. INCORPORATE ECP'S. INCORPORATE ESRS-SUBCONTRACTING REPORTING SYSTEM
Apr 11, 2012P00039$0INCORPORATE ENGINEERING CHANGE PROPOSAL R12S2008.
Mar 22, 2012P00038$0ADD CLINS FOR AIR FORCE SAMPLE SHIPMENTS TO EGLIN AFB.
Feb 29, 2012P00037$0ADD TAC FOR CLIN 3006AA.
Feb 15, 2012P00036$-174.8KREVISE DELIVERY SCHEDULE.
Feb 7, 2012P00035$2.3MAWARD TAIWAN FMS REQUIREMENT, CONSIDERATION ROUNDS FOR INVERTED PRIMERS, AND CHANGE TACS.
Jan 11, 2012P00034$-27DECREASE CLIN 2001AK BY 2 EACH TO ALLOW PGU-27/30S TO BE DELIVERED IN CORRECT RATIO OF 4:1.
Nov 29, 2011P00033$0INCORPORATE ECP R11U2027 - LOCTITE APPLICATION AND VERIFICATION.
Oct 13, 2011P00031$0INCORPORATE PROCESS CAPABILITY CONTROL AND IMPROVEMENT (PCCI) CLAUSE FOR M14A2N LINKS.
Sep 23, 2011P00032$58.7MAWARD 4,624,792 VARIOUS 20MM PGU-SERIES CARTRIDGES AS OPTION 3 TO THIS CONTRACT.
Aug 31, 2011P00030$0AWARD 287,713 20MM PGU-27S AND 58,400 20MM PGU-28S AS CONVERSION ROUNDS FUNDED WITH EXCESS FUNDS FROM BASE PERIOD AND OPTION 1 NEGOTIATED PRICES.
Jun 29, 2011P00029$0INCORPORATE COMMERCIAL ITEM DESCRIPTION A-A-59383.
May 24, 2011P00028$0REVISE DELIVERY SCHEDULE.
May 10, 2011P00027$0PROVIDE 5 EACH, 20MM FIRING CONTROL BOXES AS GOV'T FURNISHED TEST EQUIPMENT. INCOPRATE ECPS R10S2073, R10S5055, AND L09K2166.
Apr 28, 2011P00025$0INCORPORATE PERKINS ROUGE CALCIUM SILICIDE LOT C11208 FOR USE ON PRIMER MANUFACTURING FOR THIS CONTRACT.
Apr 28, 2011P00026$0CORRECT ERROR ON MOD P00019.
Mar 22, 2011P00024$0INCORPORATE ECPS R10J5096 AND 0043-E-0803.
Jan 13, 2011P00023$0ADD 1,750 REFERENCE ROUNDS TO CONTRACT AS GFM.
Dec 7, 2010P00022$0INCORPORATE CHANGES TO CLAUSE 52.210-4501 (RICC) "DRAWINGS/SPECIFICATIONS".
Nov 29, 2010P00021$0INCORPORATE CLIN 1001AZ TO ACCOUNT FOR AN OVER-SHIPMENT OF 5 EACH 20MM PGU-28/30 ON CLIN 0001AZ.
Nov 4, 2010P00020$0UPDATE TACS FOR NAVAIR REQUIREMENTS.
Oct 20, 2010P00019$0ADD NSNS, CORRECT SHIP TO ADDRESSES, REVISE DEL SCHED CLIN 2001AH, UPDATE CLAUSE.
Sep 8, 2010P00017$0DELIVERY SCHEDULE REVISION.
Aug 27, 2010P00018$100.3KINCORPORATE SYNTHETIC CALCIUM SILICIDE SOW.
Aug 20, 2010P00016$52.1M20MM PGU-SERIES AMMUNITION
Aug 20, 2010P00016$2.3M20MM PGU-SERIES AMMUNITION
May 12, 2010P00014$0CTG 20MM PGU-27A/B, PGU-30 A/B
May 12, 2010P00015$0CTG 20MM PGU-SERIES
Apr 9, 2010P00013$0CTG 20MM PGU-30 A/B (AA28)
Apr 2, 2010P00012$0CTG 20MM PGU SERIES
Mar 26, 2010P00011$0SWAPPING OF FUNDS
Mar 15, 2010P00010$0CTG 20MM PGU-28 A/B (AA22)
Mar 11, 2010P00009$0CTG 20MM PGU-28 A/B (AA22)
Nov 9, 2009P00008$0CTG 20MM PGU-28 A/B (AA22) CHANGE FOB POINT TO DESTINATION.
Nov 6, 2009P00007$0REVISE DELIVERY SCHEDULE FOR CLINS 0001AH, 0001AS, 0001AT, 0001AV, 0001AX, 0001AY, 001AZ, 0001BH, 0001BJ, AND 0001BN.
Sep 11, 2009P00006$0CHANGE SHIP-TO ADDRESS AND QUANTITY ON CLIN 0001AV. USG DIRECTS ATK TO SEND SPENT 20MM CARTRIDGE CASES FROM F&C LAT'S TO EGLIN AFB FOR FURTHER TESTING.
May 21, 2009P00005$23.4MOBLIGATION
Mar 24, 2009P00004$0REVISE DELIVERY SCHEDULE FOR CLINS 0010 AND 0011.
Feb 5, 2009P00001$-136.1KREVISE DELIVERY SCHEDULES. DELETE CDRL 0002. CHANGE DEPOT SHIP TO DOC NUMBERS. INCORPORATE ECP'S. INCORPORATE ESRS-SUBCONTRACTING REPORTING SYSTEM
Feb 5, 2009P00003$297.5KADD-ON CLINS 0010 AND 0011 FOR THE MANUFACTURE AND FABRICATION OF M52A3B1 ELECTRIC PRIMERS.
Sep 24, 20080$25.2MBASIC AWARD FOR 20MM PGU-SERIES AMMUNITION
Sep 24, 20080$361.4KUNDER BASIC AWARD FOR 20MM PGU-SERIES AMMUNITION. RQMT IS FMS

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.