Federal contract award

W9123621C2005

CONSTRUCTION OF AIR FORCE TARGETING CENTER AT JOINT BASE LANGLEY-EUSTIS.

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW2SD ENDIST NORFOLK
NAICS236220 — Commercial and Institutional Building Construction
PSCY1JZ — CONSTRUCTION OF MISCELLANEOUS BUILDINGS
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$51.1M
Current contract value$51.1M
Potential contract value / ceiling$53.8M
Start dateMay 21, 2021
Current end dateJul 31, 2025
Potential end dateJul 31, 2025
Latest award activityApr 16, 2026
Source loadedSep 26, 2026

Funding and modification history

Showing the latest 31 of 31 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 16, 2026A00021$10.4KLANGLEY AIR FORCE BASE - TARGETING CENTER PROJECT MODIFICATION A00021 - CHILLER CONTROL SOLUTION EXECUTED 16 APR 2026
Feb 18, 2026A00020$11.5KRFI-0320 - EF-5 MOTOR CHANGE CONTRACT FOR FY 17 TARGETING CENTER FACILITY AT LANGLEY AFB IN HAMPTON, VAREFERENCE NO. R00029
Dec 12, 2025A00019$118.0KLANGLEY AIR FORCE BASE - TARGETING CENTER BUILDING PROJECT MODIFICATION A00019 - M0029, M0052, M0054, M0055, M0056 EXECUTED 25 NOV 2025
Aug 20, 2025P00009$3.2MTARGETING CENTER BUILDING, JBLE PAYMENT OF SETTLEMENT AGREEMENT
Aug 4, 2025A00018$1.6KLANGLEY AIR FORCE BASE - AF TARGETING CENTER PROJECT MODIFICATION A00018 - CHANGE GLASS FILM ON PARTITIONS EXECUTED 23 MAY 2025
May 7, 2025P00008$0TARGETING CENTER BUILDING P00008 TIME IMPACTS ASSOCIATED WITH A00015 / ASI006
Apr 28, 2025A00017$79.5KTARGETING CENTER BUILDING RFI-0228G & DESCOPE DG-1
Apr 25, 2025P00007$0AIR FORCE TARGETING CENTER ASI002/ASI002R SETTLEMENT
Apr 4, 2025A00016$0LANGLEY AIR FORCE BASE - AF TARGETING CENTER PROJECT MODIFICATION A00016 - SUSPENSION OF WORK - AIR SHOW - APR2025 EXECUTED 04 APR 2025
Feb 25, 2025A00015$186.8KLANGLEY AIR FORCE BASE - TARGETING CENTER BUILDING PROJECT MODIFICATION A00015 - M0041, M0042, M0044, M0046, EXECUTED 25 FEB 2025
Nov 21, 2024A00014$131.6KLANGLEY AIR FORCE BASE - TARGETING CENTER BUILDING PROJECT MODIFICATION A00014 - M0022, M0023, M0027, M0030, M0033, M0040 EXECUTED 20 NOV 2024
Nov 18, 2024P00006$-110.9KAIR FORCE TARGETING CENTER JBLE RFP0014 ASI002 / ASI002R DIRECT MATERIALS MODIFICATION
Nov 7, 2024A00013$64.5KLANGLEY AIR FORCE BASE - TARGETING CENTER BUILDING PROJECT MODIFICATION A00013 - M0015, M0026, M0028 & M0038 EXECUTED 06 NOV 2024
Apr 29, 2024A00011$38.4KTARGETING CENTER BUILDING
Apr 29, 2024A00012$70.7KTARGETING CENTER BUILDING
Apr 15, 2024A00010$73.6KLANGLEY AIR FORCE BASE - TARGETING CENTER FACILITY PROJECT MODIFICATION A00010 - FOUR IN ONE MOD EXECUTED 15 APR 2024
Feb 12, 2024A00009$18.0KLANGLEY AIR FORCE BASE - TARGETING CENTER PROJECT MODIFICATION A00009 - RFI-0211G - EAST LOBBY WINDOW EXECUTED 12 FEB 2024
Jan 30, 2024A00008$193.3KLANGLEY AIR FORCE BASE - TARGETING CENTER PROJECT MODIFICATION A00008 - RFI-0202 EXTERIOR WALL BENT PLATE EXECUTED 26 JAN 2024
Jan 24, 2024P00005$405.9KMODIFICATION TO EXPEDITE PDU PROCUREMENT (ASI-002R)
Sep 7, 2023A00007$190.2KLANGLEY AIR FORCE BASE - TARGETING CENTER PROJECT MODIFICATION A00007 - RFI-0142 STEEL DETAILS EXECUTED 07 SEP 2023
May 12, 2023A00006$0LANGLEY AIR FORCE BASE - TARGETING CENTER BUILDING PROJECT MODIFICATION A00006 - AIRSHOW SUSPENSION OF WORK EXECUTED 12 MAY 2023
May 11, 2023A00005$35.1KLANGLEY AIR FORCE BASE - TARGETING CENTER BUILDING PROJECT MODIFICATION A00005 - UTILITIES DIFFERING SITE CONDITIONS EXECUTED 11 MAY 2023
May 4, 2023P00004$0TARGETING CENTER BUILDING
Mar 23, 2023A00004$95.5KLANGLEY AIR FORCE BASE - TARGETING CENTER PROJECT MODIFICATION A00004 - STRUCTURAL STEEL CHANGES EXECUTED 21 MAR 2023
Jan 31, 2023A00003$403.0KLANGLEY AIR FORCE BASE - TARGETING CENTER PROJECT MODIFICATION A00003 - EXPEDITE EATON SWITCHGEAR EXECUTED 27 JAN 2023
Nov 22, 2022A00002$269.9KLANGLEY AIR FORCE BASE - TARGETING CENTER FACILITY PROJECT MODIFICATION A00002 - REA - DIG PERMIT, UXO & SWPPP DELAYS EXECUTED 09 NOV 2022
May 11, 2022A00001$20.5KLANGLEY AIR FORCE BASE - TARGETING CENTER FACILITY PROJECT MODIFICATION A00001 - GRADE BEAMS AT COOLING TOWERS EXECUTED 10 MAY 2022
May 10, 2022P00003$-851.7KTHE PURPOSE OF THIS MODIFICATION IS TO DEFINITIZE WHITING TURNERS VALUE ENGINEERING CHANGE PROPOSAL
Aug 26, 2021P00002$0MOD P00002 CONSTITUTES GOVERNMENT ACCEPTANCE OF THE WHITING TURNER CONTRACTING COMPANY'S VALUE ENGINEERING CHANGE PROPOSAL SUBMITTED ON 25 MAY 2021.
Jun 9, 2021P00001$0TARGETING CENTER BUILDING - NOTICE TO PROCEED
May 11, 20210$46.4MCONSTRUCTION OF AIR FORCE TARGETING CENTER AT JOINT BASE LANGLEY-EUSTIS.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.