Federal contract award

W9123822C0003

TULE RIVER BASIN PHASE 2

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeW075 ENDIST SACRAMENTO
NAICS237990 — Other Heavy and Civil Engineering Construction
PSCY1LC — CONSTRUCTION OF TUNNELS AND SUBSURFACE STRUCTURES
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIRM FIXED PRICE
Obligations$55.5M
Current contract value$55.5M
Potential contract value / ceiling$56.0M
Start dateDec 10, 2021
Current end dateApr 30, 2025
Potential end dateApr 30, 2025
Latest award activityJul 12, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jul 12, 2025P00010$12.9MTULE RIVER BASIN PHASE 2 - GLOBAL SETTLEMENT
Feb 21, 2025A00010$230.2KTULE RIVER BASIN PHASE 2
Jan 31, 2025P00009$1.6MTULE RIVER BASIN PHASE 2
Dec 20, 2024A00009$466.2KTULE RIVER BASIN PHASE 2 R16/A9 CD011, CD14, CD016
Nov 21, 2024A00008$0TULE RIVER BASIN PHASE 2 R15/A8 CD0012 AND CD0020 LEFT AND RIGHT-SIDE EXCAVATION SOLUTION.
Oct 10, 2024A00007$214.6KTULE RIVER BASIN PHASE 2, R14/A7, CD6 FRENCH DRAIN, CD13 ANCHOR LAYOUT IMPACTS, CD15 WATERSTOP BETWEEN TRAINING WALL AND APRON.

Research next steps

  1. Check the stated set-aside against the solicitation and current certifications.