Federal contract award
1630J219C0003
WOODSTOCK JCC AWARD MTC 1630J2-19-C-0003
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Labor |
| Office | DOL - JCAS EAST PROCUREMENT |
| NAICS | 611519 — Other Technical and Trade Schools |
| PSC | M1CZ — OPERATION OF OTHER EDUCATIONAL BUILDINGS |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $67.2M |
| Current contract value | $89.2M |
| Potential contract value / ceiling | $112.6M |
| Start date | Dec 27, 2018 |
| Current end date | Sep 30, 2024 |
| Potential end date | Sep 30, 2024 |
| Latest award activity | Aug 24, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 55 of 55 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Aug 24, 2026 | P00054 | $53.3K | WOODSTOCK JOB CORPS CENTER |
| Jul 7, 2026 | P00053 | $-1.8M | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS IN THE AMOUNT OF $1,799,622.86 FROM ORDER 1630J2-19-C-0003. |
| Dec 5, 2025 | P00052 | $839.4K | WOODSTOCK JCC WITH OA/CTS |
| Sep 22, 2025 | P00051 | $-184.7K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS IN THE AMOUNT OF $184,652.00 FROM CONTRACT 1630J2-19-C-0003. |
| Nov 19, 2024 | P00050 | $-5.5K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS IN THE AMOUNT OF $5,529.20 FROM CONTRACT 1630J2-19-C-0003. |
| May 9, 2024 | P00049 | $-665 | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS IN THE AMOUNT OF $665.00 FROM CONTRACT NUMBER 1630J2-19-C-0003. |
| Feb 16, 2024 | P00048 | $61.1K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDING IN THE AMOUNT OF -$791,237.00 IN CRA FUNDS AND $-93,000.00 |
| Jan 31, 2024 | P00047 | $-884.2K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDING IN THE AMOUNT OF -$791,237.00 IN CRA FUNDS AND $-93,000.00 |
| Dec 4, 2023 | P00046 | $45.2K | THE PURPOSE OF THIS MODIFICATION IS TO FUND REA |
| Jul 31, 2023 | P00045 | $93.0K | THE PURPOSE OF THIS MODIFICATION IS TO FUND CTST |
| Jul 19, 2023 | P00044 | $-6.2K | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS IN THE AMOUNT OF $6,225.00 FROM CONTRACT NUMBER 1605JE-20-C-0003. |
| Jun 28, 2023 | P00043 | $550.0K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00043 THE PURPOSE OF THIS MODIFICATION IS TO FUND CRA |
| Jun 20, 2023 | P00042 | $8.6M | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00041 THE PURPOSE OF THIS MODIFICATION IS TO ADJUST ESTIMATED COST FOR CY4 VALUE FOR CLIN 2003, ADD INCREMENTAL FUNDING AND INCORPORATE WD RATES. |
| Apr 17, 2023 | P00041 | $2.5K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00041 THE PURPOSE OF THIS MODIFICATION IS TO FUND EQUIPMENT |
| Mar 30, 2023 | P00040 | $8.8K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00040 THE PURPOSE OF THIS MODIFICATION IS TO FUND EQUIPMENT |
| Mar 6, 2023 | P00039 | $180.5K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00039 TTHE PURPOSE OF THIS MODIFICATION IS TO UPDATE THE VALUE AND FUNDING FOR CONTRACT YEAR 3 OPS AND CTS. |
| Nov 28, 2022 | P00038 | $72.0K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00036 THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: THIS MODIFICATION IS HEREBY ISSUED TO CHANGE THE MINIMUM WAGE RATE FROM $15.00 PER HOUR TO $16.20 PER HOUR EFFECTIVE JANUARY 1, 2023. FUND CRA |
| Nov 4, 2022 | P00037 | $28.8K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00036 THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: THE PURPOSE OF THIS MODIFICATION IS TO FUND OPS, OA, CTS, CRA AND EQUIPMENT. |
| Oct 20, 2022 | P00036 | $9.1M | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00036 THE PURPOSE OF THIS MODIFICATION IS AS FOLLOWS: THE PURPOSE OF THIS MODIFICATION IS TO FUND OPS, OA, CTS, CRA AND EQUIPMENT. |
| Oct 12, 2022 | P00035 | $50.0K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00035 THE PURPOSE OF THIS MODIFICATION IS TO FUND CRA. |
| Sep 22, 2022 | P00034 | $0 | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00034 THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION YEAR 2. |
| Aug 31, 2022 | P00033 | $2.6M | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00033 THE PURPOSE OF THIS MODIFICATION IS TO FUND OPS, O/A, AND CTS, AND CRA. |
| Aug 9, 2022 | P00032 | $0 | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00032 THE PURPOSE OF THIS MODIFICATION IS TO MEMORIALIZE PIN 21-12. |
| Jun 24, 2022 | P00031 | $388.9K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00031 THE PURPOSE OF THIS MODIFICATION IS TO FUND CRA. |
| Jun 17, 2022 | P00030 | $165.8K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00030 THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE FUNDING FOR THE CONTRACTORS TECHNICAL INCENTIVE FEE FOR CY1 AS REFERENCED ON THE PREVIOUS MODIFICATION. |
| Jun 14, 2022 | P00029 | $0 | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00029 THE PURPOSE OF THIS MODIFICATION IS TO MEMORIALIZE CONTRACTORS ARRIVAL ENROLLMENT PLAN, AND TO RECONCILE THE CONTRACTORS TECHNICAL INCENTIVE FEE FOR CY1 AND CY2. |
| May 25, 2022 | P00028 | $145.6K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00028 THE PURPOSE OF THIS MODIFICATION IS TO INCREASE CLIN 1014 CONSTRUCTION REHAB AND ACQUISITION FUNDING BY $145,555. |
| Apr 12, 2022 | P00027 | $5.7M | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00027 THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING FOR OPS, OA AND CTS. |
| Apr 1, 2022 | P00026 | $112.2K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00026 INCREASE CLIN 1014 CONSTRUCTION REHAB AND ACQUISITION FUNDING BY $24,300, INCREASE CLIN 1015 EQUIPMENT FOR REGIONAL RESERVE FUNDING BY $6,000 |
| Feb 14, 2022 | P00025 | $96.8K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00025 - FUND CLIN 1014 CRA FOR FOP #266, CRA EMERGENCY LEVEL 2: DEF #140029, RECEIVER TANK; AND FOP #272, CRA EMERGENCY LEVEL 1: DEF #142353, BOILER TUBES (77) |
| Feb 11, 2022 | P00024 | $0 | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD P00024 - INCORPORATE REVISED FAR CLAUSE 52.222-55, INCREASING THE MINIMUM WAGE FOR FEDERAL CONTRACTORS (JAN 2022). |
| Nov 29, 2021 | P00023 | $208.6K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 23 INCREASE CLIN 1014 CONSTRUCTION REHAB AND ACQUISITION FUNDING BY $208,594 |
| Oct 28, 2021 | P00022 | $0 | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 22 THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE FAR CLAUSE 52.223-99 ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS FOR FEDERAL CONTRACTORS (OCT 2021) (DEVIATION). INCORPORATION OF THIS CLAUSE IS IN |
| Sep 17, 2021 | P00021 | $8.4M | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 21 THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTION YEAR 1, 10/1/2021 THROUGH 9/30/2022 |
| Aug 6, 2021 | P00020 | $80.2K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 19 THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING FOR OPS, CTS AND CTST, AND TO FUND CRA. THERE IS A CURRENT NEED FOR FUNDS. 1. PROVIDE INCREMENTAL FUNDING FOR CENTER OPS AS FOLLO |
| Jul 21, 2021 | P00019 | $4.1M | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 19 THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE INCREMENTAL FUNDING FOR OPS, CTS AND CTST, AND TO FUND CRA. THERE IS A CURRENT NEED FOR FUNDS. 1. PROVIDE INCREMENTAL FUNDING FOR CENTER OPS AS FOLLO |
| Jun 22, 2021 | P00018 | $357.6K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 17. THE PURPOSE OF THIS MODIFICATION IS TO MEMORIALIZE THE FOLLOWING CHANGE ORDER INFORMATION AND INCREASE FUNDING: 1. THIS MODIFICATION DEFINITIZES THE CHANGE ORDER ISSUED ON DECEMBER 1, 2020, WHICH |
| Jun 15, 2021 | P00017 | $122.1K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 17. THE PURPOSE OF THIS MODIFICATION IS TO MEMORIALIZE THE FOLLOWING CHANGE ORDER INFORMATION AND INCREASE FUNDING: 1. THIS MODIFICATION DEFINITIZES THE CHANGE ORDER ISSUED ON DECEMBER 1, 2020, WHICH |
| May 19, 2021 | P00016 | $54.1K | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 16. THE PURPOSE OF THIS MODIFICATION IS TO MEMORIALIZE WOODSTOCK COST INCENTIVE RECONCILIATIONS, AND FUND CRA. |
| Apr 8, 2021 | P00015 | $4.0M | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 15. THE PURPOSE OF THIS MODIFICATION IS PROVIDE INCREMENTAL FUNDING FOR CY2 CENTER OPERATIONS, FUND NTC EQUIPMENT FUNDING FOR PRE-APPRENTICESHIP TRAINING, AND MAKE ADMINISTRATIVE CHANGES TO CTT OFFER |
| Nov 10, 2020 | P00014 | $5.8M | WOODSTOCK/9371/MTC, CY2/1630J219C0003, MOD 14. INCREMENTAL FUNDING IS PROVIDED FOR CONTRACT YEAR 2 (BASE YEAR). THERE IS A CURRENT NEED FOR FUNDING. WOODSTOCK/9371/MTC, 1630J219C0003 - P00013 1. INCREMENTAL FUNDING INCREASE CLIN 0002 CE |
| Sep 24, 2020 | P00013 | $794.4K | WOODSTOCK/9371/MTC, 1630J219C0003 - P00013 1. INCREMENTAL FUNDING INCREASE CLIN 0002 CENTER OPERATIONS FUNDING BY $750,000 2. INCREASE CLIN 0014 CONSTRUCTION/REHAB FUNDING BY $44,357 (FOP #122, CFR 34955 - STORM DRAIN, $44,357). |
| Aug 25, 2020 | P00012 | $90.1K | WOODSTOCK/9371/MTC, 1630J219C0003 - P00012 1. INCREASE CLIN 0014 CONSTRUCTION/REHAB FUNDING BY $90,069 (FOP #90, CFR 34386 - STORM DRAIN, $29,765)(FOP #96, CFR 34570 - FLOOR TILE REPLACEMENT, $54,369) (FOP #97, CFR 34603 - PATIO CEILING DOOR, |
| Aug 7, 2020 | P00011 | $292.0K | WOODSTOCK/9371/MTC, 1630J219C0003 - P00011 1. INCREMENTAL FUNDING IS PROVIDED FOR CONTRACT YEAR 1. THERE IS A CURRENT NEED FOR FUNDING. INCREASE CLIN 0002 CENTER OPERATIONS FUNDING BY $200,000 2. INCREASE CLIN 0016 CTST ESTIMATED COST AND FUN |
| Jun 30, 2020 | P00010 | $3.4M | WOODSTOCK/9371/MTC, 1630J219C0003 - P00010 THIS MODIFICATION HEREBY FINALIZES THE EQUITABLE ADJUSTMENT FOR THE CHANGE ORDER LETTER UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. WOODSTOCK/93 |
| May 19, 2020 | P00009 | $4.8M | WOODSTOCK/9371/MTC, 1630J219C0003 - P00002 (1) NOTICE TO PROCEED; PERIOD OF PERFORMANCE UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. WOODSTOCK/9371/MTC, CY1/1630J219C0003, MOD 3. 364,540.00 1. |
| May 12, 2020 | P00008 | $6.0K | WOODSTOCK/9371/MTC, 1630J219C0003 - P00002 (1) NOTICE TO PROCEED; PERIOD OF PERFORMANCE UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. WOODSTOCK/9371/MTC, CY1/1630J219C0003, MOD 3. 364,540.00 1. |
| Mar 6, 2020 | P00007 | $88.6K | WOODSTOCK/9371/MTC, 1630J219C0003 - P00002 (1) NOTICE TO PROCEED; PERIOD OF PERFORMANCE UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. WOODSTOCK/9371/MTC, CY1/1630J219C0003, MOD 3. 364,540.00 1. |
| Dec 19, 2019 | P00006 | $62.0K | WOODSTOCK/9371/MTC, 1630J219C0003 - P00002 (1) NOTICE TO PROCEED; PERIOD OF PERFORMANCE UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. WOODSTOCK/9371/MTC, CY1/1630J219C0003, MOD 3. 364,540.00 1. |
| Nov 29, 2019 | P00005 | $0 | WOODSTOCK/9371/MTC, 1630J219C0003 - P00002 (1) NOTICE TO PROCEED; PERIOD OF PERFORMANCE UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. WOODSTOCK/9371/MTC, CY1/1630J219C0003, MOD 3. 364,540.00 1. |
| Nov 18, 2019 | P00004 | $64.0K | WOODSTOCK/9371/MTC, 1630J219C0003 - P00002 (1) NOTICE TO PROCEED; PERIOD OF PERFORMANCE UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. WOODSTOCK/9371/MTC, CY1/1630J219C0003, MOD 3. 364,540.00 1. |
| Nov 4, 2019 | P00003 | $364.5K | WOODSTOCK/9371/MTC, 1630J219C0003 - P00002 (1) NOTICE TO PROCEED; PERIOD OF PERFORMANCE UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. WOODSTOCK/9371/MTC, CY1/1630J219C0003, MOD 3. 364,540.00 1. |
| Sep 19, 2019 | P00002 | $7.7M | WOODSTOCK/9371/MTC, 1630J219C0003 - P00002 (1) NOTICE TO PROCEED; PERIOD OF PERFORMANCE UPDATE 10/1/2019-9/30/2024 (2) INCREMENTAL FUNDING FOR CY1. THERE IS A CURRENT NEED FOR FUNDS. |
| Mar 26, 2019 | P00001 | $-8.7M | IGF::CT::IGF WOODSTOCK JCC MTC 1630J2-19-C-0003 |
| Dec 27, 2018 | 0 | $8.9M | WOODSTOCK JCC AWARD MTC 1630J2-19-C-0003 |