Federal contract award

N0002413C2108

RCOH DELIVERY PERFORMANCE INCENTIVE

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeSUP OF SHIPBUILDING CONV AND REPAIR
NAICS336611 — Ship Building and Repairing
PSC1905 — Combat Ships and Landing Vessels
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeCOST PLUS INCENTIVE FEE
Obligations$2.6B
Current contract value$2.7B
Potential contract value / ceiling$2.7B
Start dateMar 29, 2013
Current end dateNov 29, 2016
Potential end dateNov 29, 2016
Latest award activityMay 5, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 200 of 2,535 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 5, 2026A00086$0CVN 72 N00024-13-C-2108 PERIODIC RELEASE MOD FOR THE PERIOD OF JANUARY 1, 2025 - JUNE 30, 2025.
Nov 17, 2025A00085$0CVN 72 (EXE) N00024-13-C-2108 PERIODIC RELEASE MOD FOR THE PERIOD JULY 1, 2024 THROUGH DECEMBER 31, 2024.
May 9, 2025A00084$0CVN 72 N00024-13-C-2108 PERIODIC RELEASE MOD 1 JANUARY 2024 - 30 JUNE 2024
Nov 7, 2024A00083$0FY13 RCOH ACCOMPLISHMENT
Aug 29, 2024A00082$0FY13 RCOH ACCOMPLISHMENT
May 3, 2024A00081$0PRM 1 JAN - 30 JUN 2023
Apr 19, 2024A00080$0CVN 72 GFP TO FACILITY USE CONTRACT
Nov 9, 2023A00079$0PERIODIC RELEASE MOD 1 JUL - 31 DEC 2022
May 12, 2023A00078$0PERIODIC RELEASE MOD 1JAN-30JUN 2022
Nov 23, 2022A00077$0FY13 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Oct 25, 2022A00076$0FY13 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Sep 16, 2022A00075$0GOVERNMENT PROPERTY TRANSFER
May 27, 2022A00074$0FY13 REFUELING AND COMPLEX OVERHAUL ACCOMPLISHMENT
Dec 18, 2021A00073$0PERIODIC ADJUDICATION OF CHANGES
Nov 17, 2021A00072$0PERIODIC RELEASE MODIFICATION IN ACCORDANCE WITH (IAW) 5252.243-9105 NOTIFICATION OF CHANGES (CT) (JAN 1983)
Sep 8, 2021A00071$0CVN 72 GOVERNMENT PROPERTY TRANSFER FOR THE REFUELING COMPLEX OVERHAUL CONTRACT.
Aug 17, 2021A00070$0GOVERNMENT FURNISHED PROPERTY TRANSFER
Nov 4, 2020A42363$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Aug 26, 2020A42362$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 5, 2020A42361$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Feb 22, 2020A00069$0GFP TRANSFER TO N00024-18-C-2106 TO SUPPORT PROPULSION STEAM PLANT DRYDOWN.
Feb 22, 2020A00069$0GFP PROPERTY TRANSFER
Nov 4, 2019A42360$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 14, 2019A42359$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Feb 19, 2019A42358$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jan 31, 2019A42357$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Nov 13, 2018A42356$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Sep 19, 2018P00029$0RCOH DELIVERY PERFORMANCE INCENTIVE
Sep 19, 2018P00029$0FY13 RCOH ACCOMPLISHMENT BILLABLE FEE ADJUSTMENT
Sep 6, 2018A00068$0CORRECT CLIN 0003 ERP ERROR
Sep 6, 2018A00068$0CORRECT CLIN 0003 ERP ERROR
Aug 20, 2018A00067$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 2 MAY THRU 2 AUG 2018.
Aug 20, 2018A00067$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 2 MAY THRU 2 AUG 2018.
Aug 13, 2018A00066$0CVN 72 RCOH CLIN 0003 FUNDING AND ADJUDICATION MODIFICATION.
Aug 13, 2018A00066$0CVN 72 RCOH CLIN 0003 FUNDING AND ADJUDICATION MODIFICATION.
Aug 3, 2018A42355$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 18, 2018A42347$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 18, 2018A42348$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 18, 2018A42349$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 18, 2018A42350$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 18, 2018A42351$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 18, 2018A42352$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 18, 2018A42353$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 18, 2018A42354$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2018A00065$0DE-OBLIGATION OF CLIN 0005
Jun 13, 2018A00065$-448.7KDE-OBLIGATION OF CLIN 0005
May 11, 2018A00064$0CVN72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 10 FEB 18 - 1 MAY 18.
May 11, 2018A00064$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 10 FEB 18 - 1 MAY 18.
May 8, 2018A42346$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Mar 12, 2018A00063$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 27 JAN 18 - 9 FEB 18.
Mar 12, 2018A00063$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 27 JAN 18 - 9 FEB 18.
Mar 6, 2018A42345$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Feb 6, 2018A00062$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 8 NOV 2017 THRU 26 JAN 2018.
Feb 6, 2018A00062$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 8 NOV 2017 THRU 26 JAN 2018.
Feb 6, 2018A42344$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jan 10, 2018A00061$-1.4MDE-OBLIGATION OF CLIN 0005&CLIN 0009
Jan 10, 2018A00061$-2.0MDE-OBLIGATION OF CLIN 0005&CLIN 0009
Nov 16, 2017A00060$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 21 SEP 2017 THRU 7 NOV 2017 AS A RESULT OF THE RELEASE OF CLAIMS MODIFICATION.
Nov 16, 2017A00060$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 21 SEP 2017 THRU 7 NOV 2017 AS A RESULT OF THE RELEASE OF CLAIMS MODIFICATION.
Nov 14, 2017A42341$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Nov 14, 2017A42343$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Nov 8, 2017A00059$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 22 DEC 2016 THRU 20 SEP 2017 AS A RESULT OF THE RELEASE OF CLAIMS MODIFICATION.
Nov 8, 2017A00059$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 22 DEC 2016 THRU 20 SEP 2017 AS A RESULT OF THE RELEASE OF CLAIMS MODIFICATION.
Nov 7, 2017A00058$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 2 NOV 2016 THRU 26 JUN 2017 AS A RESULT OF THE RELEASE OF CLAIM MODIFICATION.
Nov 7, 2017A00058$0CVN 72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 2 NOV 2016 THRU 26 JUN 2017 AS A RESULT OF THE RELEASE OF CLAIM MODIFICATION.
Nov 2, 2017P00028$0IGF::CT::IGF CVN72 PD/CIA EXECUTION
Nov 2, 2017P00028$4.0MIGF::CT::IGF FY13 RCOH ACCOMPLISHMENT
Oct 31, 2017A00057$0CVN72 RCOH ADJUDICATION MODIFICATION FRO THE PERIOD OF 02-27-2014 THRU 11-01-2016. THE AUTHORIZATIONS WERE RELEASED FROM DELAY ON CONTRACT MODIFICATION N00024-13-C-2108-P00027.
Oct 31, 2017A00057$0CVN72 RCOH ADJUDICATION MODIFICATION FRO THE PERIOD OF 02-27-2014 THRU 11-01-2016. THE AUTHORIZATIONS WERE RELEASED FROM DELAY ON CONTRACT MODIFICATION N00024-13-C-2108-P00027.
Oct 2, 2017P00027$0CVN72 PD/CIA EXECUTION
Oct 2, 2017P00027$0FY13 RCOH ACCOMPLISHMENT
Sep 11, 2017A00056$-723.8KPROVIDE FINANCE WITH LOA FOR MODIFICATION N00024-13-C-2108-A00055
Sep 11, 2017A00056$0PROVIDE FINANCE WITH LOA FOR MODIFICATION N00024-13-C-2108-A00055
Sep 8, 2017A42342$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Sep 6, 2017A00055$0DE-OBLIGATION OF TYCOM FUNDING ON CLIN 0008&CLIN 0010
Sep 6, 2017A00055$0DE-OBLIGATION OF TYCOM FUNDING ON CLIN 0008&CLIN 0010
Aug 31, 2017A42339$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Aug 15, 2017A42335$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Aug 15, 2017A42336$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Aug 15, 2017A42337$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Aug 15, 2017A42338$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Aug 14, 2017A00054$0CVN72 PD/CIA PERIOD OF PERFORMANCE EXTENSION
Aug 14, 2017A00054$0CVN72 PD/CIA PERIOD OF PERFORMANCE EXTENSION
Aug 10, 2017A42334$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Aug 7, 2017A42333$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Aug 2, 2017A00053$0CVN72 PD/CIA FUNDING TRANSFERRED FROM CLIN 0007 TO CLIN 0008&0010.
Aug 2, 2017A00053$0CVN72 PD/CIA FUNDING TRANSFERRED FROM CLIN 0007 TO CLIN 0008&0010.
Jul 31, 2017A00052$0CVN 72 RCOH DAMAGE OR LOSS MODIFICATION FRO 09/24/2016 TO 0726/2017.
Jul 31, 2017A00052$0CVN 72 RCOH DAMAGE OR LOSS MODIFICATION FRO 09/24/2016 TO 0726/2017.
Jul 25, 2017A00051$0CVN72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 1 JUNE 2017 THROUGH 20 JULY 2017
Jul 25, 2017A00051$0CVN72 RCOH ADJUDICATION MODIFICATION FOR THE PERIOD OF 1 JUNE 2017 THROUGH 20 JULY 2017
Jul 19, 2017A00049$1.2MCVN72 PD/CIA DEFINITIZE EXECUTION CLIN 0005 AND 0008
Jul 19, 2017A00049$273.0KCVN72 PD/CIA DEFINITIZE EXECUTION CLIN 0005 AND 0008
Jul 19, 2017A00050$0CVN72 PD/CIA EXECUTION CLIN 0009 M/H TO MATERIAL CONVERSION
Jul 19, 2017A00050$0CVN72 PD/CIA EXECUTION CLIN 0009 M/H TO MATERIAL CONVERSION
Jul 17, 2017A42332$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 10, 2017A42330$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jul 10, 2017A42331$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 15, 2017A00046$0RCOH CVN72 ADJUDICATION MODIFICATION FOR THE PERIOD OF 1 APR THRU 31 MAY 2017.
Jun 15, 2017A00046$0RCOH CVN72 ADJUDICATION MODIFICATION FOR THE PERIOD OF 1 APR THRU 31 MAY 2017.
Jun 15, 2017A00047$2.1MPD CIA FUNDING CLIN 0009, CPFF TERM
Jun 15, 2017A00047$0PD CIA CLIN 0009 FUNDING, CPFF TERM
Jun 15, 2017A00048$1.1MCVN72 PD CIA FUNDING CLIN 0010 TYCOM NEW/EMERGENT WORK, CPFF TERM
Jun 15, 2017A00048$0PD CIA FUNDING TYCOM'S CLIN 0010 FOR NEW/EMERGENT WORKS, CPFF TERM
Jun 15, 2017A42327$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 15, 2017A42328$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 15, 2017A42329$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42314$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42315$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42316$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42317$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42318$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42319$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42320$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42321$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42322$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42323$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42324$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42325$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 13, 2017A42326$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 9, 2017A00045$0CVN 72 PD CIA CLIN 0008 FUNDING WITH PROVISION, CPFF
Jun 9, 2017A00045$0CVN72 PD CIA CLIN 008 FUNDING WITH PROVISION CPFF
Jun 6, 2017A42313$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Jun 5, 2017A42312$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 23, 2017A42311$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42280$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42281$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42282$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42283$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42284$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42285$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42286$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42287$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42288$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42289$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42290$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42291$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42292$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42293$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42294$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 18, 2017A42295$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42296$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42297$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42298$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42299$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42300$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42301$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42302$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42303$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42304$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42305$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42306$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42307$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42308$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42309$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 17, 2017A42310$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 15, 2017A42240$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 12, 2017A00044$0CVN72 PD/CIA CPFF CONTRACT, ADMIN MOD AUTHORIZING TI CVN72-ETI-0005-001.
May 12, 2017A00044$0CVN72 PD/CIA T.I. AUTHORIZATION, CPFF TERM
May 9, 2017A42278$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 8, 2017A42279$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 4, 2017A42274$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 4, 2017A42275$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 4, 2017A42276$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 4, 2017A42277$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 1, 2017A42269$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 1, 2017A42271$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 1, 2017A42272$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
May 1, 2017A42273$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 28, 2017A00043$0EXERCISE OPTION; FUNDING EXECUTION CLIN 0005 BY $9,800,000.
Apr 28, 2017A42267$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 28, 2017A42268$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 28, 2017A42270$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 27, 2017A00042$0RCOH CVN 72 PD/CIA MODIFICATION (MOD) TO CORRECT PREVIOUS MOD.
Apr 27, 2017A42262$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 27, 2017A42263$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 27, 2017A42264$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 27, 2017A42265$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 27, 2017A42266$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 26, 2017A42259$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 26, 2017A42261$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 25, 2017A00041$750.1KPD/CIA CPFF
Apr 25, 2017A42257$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 25, 2017A42258$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 25, 2017A42260$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 21, 2017A42254$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 21, 2017P00025$0DEOBLIGATE FUNDING
Apr 21, 2017P00025$-1DEOBLIGATE FUNDING
Apr 20, 2017A42253$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 20, 2017A42255$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 20, 2017A42256$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 19, 2017A42251$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 19, 2017A42252$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 14, 2017A42246$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 14, 2017A42250$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 13, 2017A00040$0RCOH CVN 72 ADJUDICATION MODIFICATION FOR THE PERIOD OF 20 JAN THRU 31 MAR 2017.
Apr 13, 2017A00040$0RCOH CVN 72 ADJUDICATION MODIFICATION FOR THE PERIOD OF 20 JAN THRU 31 MAR 2017.
Apr 13, 2017A42247$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 13, 2017A42248$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT
Apr 13, 2017A42249$0CVN 72 REFUELING COMPLEX OVERHAUL ACCOMPLISHMENT