Federal contract award
N0002414C2111
PY1 RCOH DEFUELING ADVANCE PLANNING
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | SUP OF SHIPBUILDING CONV AND REPAIR |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | 1905 — Combat Ships and Landing Vessels |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $801.1M |
| Current contract value | $832.3M |
| Potential contract value / ceiling | $832.3M |
| Start date | Aug 1, 2014 |
| Current end date | Sep 1, 2017 |
| Potential end date | Sep 1, 2017 |
| Latest award activity | May 8, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 168 of 168 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 8, 2026 | A00110 | $0 | CVN73 (AP): PERIODIC RELEASE MODIFICATION JANUARY 1, 2025 TO JUNE 31, 2025. |
| Jan 30, 2026 | A00109 | $0 | GOVERNMENT FURNISHED PROPERTY TRANSFER TO N00024-21-C-2106 AND N00024-24-C-2106 |
| Dec 19, 2025 | A00108 | $0 | TRANSFER OF GOVERNMENT PROPERTY FROM CVN73 AP TO CVN74 EX AND CVN75 AP. |
| Nov 19, 2025 | A00107 | $0 | CVN 73(AP):PERIODIC RELEASE MODIFICATION JULY 1,2024 TO DECEMBER 31, 2024. |
| Aug 28, 2025 | A00106 | $0 | GOVERNMENT PROPERTY TRANSFERRED FROM CONTRACT N00024-14-C-2111 TO CONTRACT N00024-24-C-2106. |
| Jul 31, 2025 | A00105 | $0 | FY15 RCOH ADVANCE PLANNING TRANSFER OF MATERIAL FROM CVN73 AP TO FACILITIES CONTRACT. |
| May 20, 2025 | A00104 | $0 | CVN 75(AP) 1 JAN 2024 TO 30 JUNE 2024 PERIODIC RELEASE MODIFICATION. |
| Dec 19, 2024 | A00103 | $0 | TRANSFER PROPERTY FROM CONTRACT N00024-14-C-2111 (CVN 73 ADVANCED PLANNING) TO CONTRACT N00024-24-C-2106 (CVN 75 ADVANCED PLANNING). |
| Nov 6, 2024 | A00102 | $0 | PERIODIC RELEASE MODIFICATION |
| Jul 26, 2024 | A00101 | $0 | TRANSFER OF MATERIAL FROM CVN73 ADVANCED PLANNING TO CVN75 ADVANCED PLANNING. |
| May 3, 2024 | A00100 | $0 | PRM 1 JAN - 30 JUN 2023 |
| Jan 24, 2024 | A00099 | $0 | CVN 73 EX TO CVN 74 EX- GOVERNMENT PROPERTY MODIFICATION |
| Nov 9, 2023 | A00098 | $0 | PERIODIC RELEASE MOD 1 JULY - 31 DECEMBER 2022 |
| Oct 31, 2023 | A00097 | $0 | GFP TRANSFER FROM N00024-14-C-2111 TO N00024-21-C-2106 |
| Sep 13, 2023 | A00096 | $0 | GFP MOD FROM N00024-14-C-2111 TO N00024-21-C-2106 |
| Aug 9, 2023 | A00095 | $0 | GFP TRANSFER FROM N00024-14-C-2111 TO N00024-21-C-2106. |
| May 16, 2023 | A00094 | $0 | CVN 73 AP TO CVN 74 EX GOV. PROPERTY MOD |
| May 12, 2023 | A00093 | $0 | PERIODIC RELEASE MOD 1JAN-30JUN 2022 |
| Apr 13, 2023 | A00092 | $0 | CVN 73 AP TO CVN 74 EX GOVERNMENT PROPERTY MOD |
| Mar 3, 2023 | A00091 | $0 | GOVERNMENT FURNISHED PROPERTY TRANSFER |
| Jan 25, 2023 | A00090 | $0 | CVN 73 AP GP MOD |
| Nov 23, 2022 | A00089 | $0 | FY15 REFUELING COMPLEX OVERHAUL ADVANCE PLANNING |
| Oct 25, 2022 | A00088 | $0 | GOVERNMENT PROPERTY TRANSFER |
| Aug 12, 2022 | A00087 | $0 | TRANSFERRING GOVERNMENT PROPERTY |
| Jun 10, 2022 | A00086 | $0 | FY15 REFUELING AND COMPLEX OVERHAUL ADVANCE PLANNING |
| May 27, 2022 | A00085 | $0 | FY15 REFUELING AND COMPLEX OVERHAUL ADVANCE PLANNING |
| May 17, 2022 | A00084 | $0 | GOVERNMENT PROPERTY TRANSFER |
| Mar 22, 2022 | A00083 | $0 | FY15 REFUELING AND COMPLEX OVERHAUL ADVANCE PLANNING ACTION |
| Mar 1, 2022 | P00058 | $-3.8M | FY15 RCOH ADVANCE PLANNING |
| Feb 10, 2022 | A00082 | $0 | FY15 REFUELING AND COMPLEX OVERHAUL ADVANCE PLANNING |
| Nov 12, 2021 | A00081 | $0 | PERIODIC RELEASE MODIFICATION |
| Aug 13, 2021 | A00080 | $0 | FY15 REFUELING COMPLEX OVERHAUL ADVANCE PLANNING |
| Jun 22, 2021 | P00057 | $0 | FY15 RCOH ADVANCE PLANNING |
| May 12, 2021 | P00056 | $-5.2M | FY15 RCOH ADVANCE PLANNING |
| May 7, 2021 | A00079 | $0 | FY15 RCOH ADVANCE PLANNING - PERIODIC RELEASE JAN - MAR 2020 |
| Apr 15, 2021 | P00055 | $-1.8M | DE-OBLIGATION OF UNLIQUIDATED FUNDS |
| Nov 4, 2020 | A00078 | $0 | PERIODIC RELEASE MODIFICATION FOR THE CYCLE JUL-DEC 2019 |
| Sep 24, 2020 | P00054 | $-5.5M | FY15 RCOH ADVANCE PLANNING |
| Sep 22, 2020 | A00077 | $0 | INCLUDE FAR 52.204-25 |
| Sep 15, 2020 | AB2001 | $0 | ESTABLISH CLAUSE ADD FAR 52.204-25 |
| May 6, 2020 | A00076 | $0 | PERIODIC RELEASE MOD 1/01/2019-06/30/2019 |
| Apr 16, 2020 | A00075 | $1.7M | CVN 73 RCOH HUNTINGTON HALL BERTHING AND MESSING FOR PERIOD 23 MARCH 2020 THROUGH 20 SEPTEMBER 2020 |
| Feb 18, 2020 | A00074 | $0 | CVN 73 RCOH HUNTINGTON HALL BERTHING AND MESSING ADMIN MOD |
| Nov 5, 2019 | A00073 | $0 | FY15 RCOH ADVANCE PLANNING |
| Nov 1, 2019 | P00053 | $-970.6K | FY15 RCOH ADVANCE PLANNING |
| Oct 3, 2019 | A00072 | $913.1K | CVN 73 RCOH HUNTINGTON HALL BERTHING AND MESSING FOR PERIOD 23 SEP 2019 THROUGH 22 MARCH 2020 |
| Sep 4, 2019 | P00052 | $-10.9M | CVN 73 RCOH AP DE-OBLIGATION CLIN 0015 |
| Jun 20, 2019 | P00051 | $-979.4K | FY15 RCOH ADVANCE PLANNING - DEOBLIGATION OF ULO FROM COMPLETED COST CLIN |
| May 21, 2019 | A00071 | $0 | FY15 RCOH ADVANCE PLANNING |
| Apr 12, 2019 | A00070 | $1.2M | CVN 73 RCOH HUNTINGTON HALL BERTHING AND MESSING FOR PERIOD 25 MARCH 2019 THROUGH 22 SEPTEMBER 2019 |
| Mar 29, 2019 | P00050 | $0 | FY15 RCOH ADVANCE PLANNING |
| Mar 13, 2019 | P00049 | $0 | FY15 RCOH ADVANCE PLANNING |
| Nov 6, 2018 | P00048 | $374.4K | FY15 RCOH ADVANCE PLANNING |
| Sep 28, 2018 | A00068 | $1.2M | CVN 73 RCOH HUNTINGTON HALL BERTHING AND MESSING FOR PERIOD 24 SEP 2018 THROUGH 24 MARCH 2019 |
| Aug 28, 2018 | P00047 | $0 | FY15 RCOH ADVANCE PLANNING |
| Aug 7, 2018 | P00046 | $0 | FY15 RCOH ADVANCE PLANNING CLIN 0006 POP EXTENSION |
| Jul 5, 2018 | P00045 | $0 | CVN 73 RCOH AP CONTRACT POP EXTENSION TO SUPPORT CVN 74 PRE-AP SHIP CHECKS |
| Jun 20, 2018 | P00044 | $0 | FY15 RCOH ADVANCE PLANNING |
| May 31, 2018 | P00043 | $0 | CVN 73 RCOH ADVANCE PLANNING CLIN 0019 POP EXTENSION |
| May 14, 2018 | P00042 | $553.8K | FY15 RCOH ADVANCE PLANNING MATERIAL |
| Apr 13, 2018 | P00041 | $62.7K | FY15 RCOH ADVANCE PLANNING |
| Apr 9, 2018 | A00067 | $1.2M | CVN 73 RCOH HUNTINGTON HALL BERTHING AND MESSING FOR PERIOD 26 MARCH 2018 THROUGH 23 SEPTEMBER 2018. |
| Feb 21, 2018 | P00040 | $0 | FY15 RCOH ADVANCE PLANNING |
| Feb 15, 2018 | A00066 | $0 | CVN 73 RCOH ADVANCE PLANNING, CANCELLATION OF E&S POOL FMR 74.00&FMR 79.00. |
| Feb 5, 2018 | P00039 | $-32.0M | FY15 RCOH ADVANCE PLANNING |
| Feb 2, 2018 | P00038 | $0 | FY15 RCOH ADVANCE PLANNING |
| Jan 26, 2018 | A00065 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSAL 72. |
| Jan 25, 2018 | A00064 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MATERIAL PROPOSAL 50 FOR FUKUSHIMA RELATED REMEDIATION OF PRIORITY 4 VENTILATION SYSTEMS. |
| Jan 11, 2018 | A00063 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF CLIN 0015 E&S POOL MATERIAL PROPOSALS 28A, 49A, 70, 71&42. |
| Dec 18, 2017 | P00037 | $15.6M | FY15 RCOH ADVANCE PLANNING |
| Dec 1, 2017 | P00035 | $0 | FY15 RCOH ADVANCE PLANNING |
| Nov 29, 2017 | A00062 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSALS 53, 56, 57, 65, 68&69. |
| Nov 7, 2017 | A00061 | $0 | CVN 73 RCOH ADVANCE PLANNING, NOC PERIODIC RELEASE MOD FOR PERIOD JAN 1, 2017 THROUGH JUNE 30, 2017. |
| Nov 1, 2017 | P00034 | $6.9M | FY15 RCOH ADVANCE PLANNING |
| Oct 12, 2017 | A00060 | $-2.5K | CVN 73 RCOH ADVANCE PLANNING, CLIN 0017 POP EXTENSION AND SOW REVISION. |
| Oct 6, 2017 | P00033 | $2.7M | IGF::CT::IGF RCOH ADVANCE PLANNING |
| Sep 30, 2017 | A00059 | $0 | CVN 73 RCOH ADVANCE PLANNING, UPDATE CONTRACT ATTACHMENTS K&L TO ACCOUNT FOR THE ADJUDICATION OF E&S POOL MRC PROPOSALS 61, 63, 64&67. |
| Sep 26, 2017 | A00058 | $0 | CANCEL AND SUPERSEDE A00056 |
| Sep 22, 2017 | A00057 | $1.1M | CVN 73 RCOH AP HUNTINGTON HALL BERTHING AND MESSING FOR PERIOD 25 SEP 17 THROUGH 25 MAR 18. |
| Sep 11, 2017 | A00056 | $0 | UPDATE DFARS 252.204-7012 |
| Aug 11, 2017 | P00032 | $31.0M | AUTHORIZATION OF WORK BEYOND PREPARATORY PHASE OF RCOH |
| Aug 4, 2017 | P00031 | $0 | CVN 73 RCOH ACCOMPLISHMENT |
| Jul 12, 2017 | A00055 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC #S 224&225. |
| Jul 6, 2017 | A00052 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC#S 149, 196, 218, 219, 220, 221, 222, 148, 217, 124, 223, 195, 211&212. |
| Jul 6, 2017 | A00053 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC#S 126&213-216. |
| Jul 6, 2017 | A00054 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC#S 206-209. |
| Jul 5, 2017 | P00030 | $9.7M | INCREASE TO EMERGENT&SUPPLEMENTAL MATERIAL |
| Jun 8, 2017 | A00051 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL FMR 167.00&FMR 168.00. |
| Jun 8, 2017 | P00029 | $2.9M | INCREMENTAL FUNDING AND ADMIN CORRECTION |
| Jun 6, 2017 | A00050 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC REQUEST #205. |
| Jun 1, 2017 | A00049 | $0 | CVN 73 RCOH ADVANCE PLANNING, NOC PERIODIC RELEASE MODIFICATION, PERIOD JULY 1, 2016 THROUGH DECEMBER 31, 2016. |
| May 12, 2017 | P00028 | $7.5M | FUND EARNED PLANNING YEAR 2 SPECIAL INCENTIVES |
| May 4, 2017 | A00047 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC #S 129, 197, 198, 199, 200, 201, 203&204. |
| May 4, 2017 | A00048 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC #S 156, 172, 177, 179, 182, 183, 185, 186, 187, 190, 192, 193&194. |
| May 4, 2017 | P00027 | $7.6M | ADDITIONAL FUNDING AND INCREASE TO EMERGENT AND SUPPLEMENTAL MATERIAL. |
| Apr 24, 2017 | A00046 | $0 | CVN 73 AP RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSAL 58 AND MRC PROPOSAL 60. |
| Apr 17, 2017 | A00045 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC #188. |
| Mar 30, 2017 | A00044 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSALS 54 AND 55. |
| Mar 29, 2017 | A00043 | $1.3M | CVN 73 RCOH ADVANCE PLANNING, CLIN 0018, HUNTINGTON HALL OFF-SHIP BERTHING AND MESSING FOR PERIOD 27 MARCH 2017 THROUGH 24 SEPTEMBER 2017. |
| Mar 27, 2017 | A00041 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC PROPOSALS 56&57 (I.E. MRCS 165, 175, 162, 164&184) |
| Mar 27, 2017 | A00042 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC 173. |
| Mar 14, 2017 | A00040 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC ITEM 181. |
| Mar 13, 2017 | A00039 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL FMR 138.00. |
| Mar 10, 2017 | A00038 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSALS 39, 47&49. |
| Mar 1, 2017 | A00037 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSALS 43, 46, 48, 51&52. |
| Feb 27, 2017 | A00036 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL FMR 121.00, FMR 122.00&FMR 123.00. |
| Feb 17, 2017 | P00026 | $4.3M | FY15 RCOH ADVANCE PLANNING |
| Feb 16, 2017 | A00035 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL FMR 120.00. |
| Feb 13, 2017 | A00034 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC 132. |
| Feb 10, 2017 | A00032 | $0 | FY15 RCOH ADVANCE PLANNING, AUTHORIZATION OF MRC 131 |
| Feb 10, 2017 | A00033 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MATERIAL PROPOSAL 50 FOR FUKUSHIMA RELATED DRY ICE CLEANING OF PRI 4 VENT SYSTEMS. |
| Feb 2, 2017 | A00031 | $0 | FY15 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL (FMR 79.00) |
| Jan 27, 2017 | A00030 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL (FMR 75.00&76.00 ) |
| Jan 17, 2017 | A00029 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL FMR 74.00. |
| Jan 6, 2017 | A00028 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSALS 38 AND 41. |
| Dec 22, 2016 | P00025 | $0 | ALLOTMENT OF FUNDS ADJUSTMENT FOR CLIN 0019 |
| Dec 16, 2016 | A00027 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSALS 13A, 29, 35, 37, 44 AND 45. |
| Dec 7, 2016 | A00026 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION TO PROCURE FUKUSHIMA REMEDIATION RELATED MATERIAL WITHIN THE E&S POOL. |
| Dec 6, 2016 | A00025 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL FMR 61.00, FMR 67.00&FMR 68.00 |
| Dec 5, 2016 | P00024 | $33.7M | THE PURPOSE OF THIS MODIFICATION IS TO 1) INCREASE THE LEVEL OF EFFORT OF ITEM 0006 BY 215,838 HOURS AND THE TOTAL COST BY $24,443,709 ($22,744,171 COST AND $1,699,538 FIXED FEE); 2) ESTABLISH CVN 74 PRE-ADVANCE PLANNING WORK ON ITEM 0019 WITH 97,216 HOURS AND TOTAL COST OF $10,822,888 ($10,069,245 COST AND $753,643 FIXED FEE); 3) INCREASE THE SECTION B NOTE C, EMERGENT AND SUPPLEMENTAL WORK, MATERIAL COST BY FROM $15,000,000 BY $5,000,000 TO $20,000,000 AND FIXED FEE FROM $1,125,000 BY $375,000 TO $1,500,00; 4) TRANSFER A TOTAL COST OF $377,037 ($350,732 COST AND 26,305 FIXED FEE) OF SUBCONTRACT EFFORT FROM ITEM 0015 TO 0006; AND 5) UPDATE APPLICABLE CONTRACT TERMS AND CONDITIONS. |
| Nov 9, 2016 | A00024 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSALS 36&40. |
| Nov 3, 2016 | A00023 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S POOL MRC PROPOSALS 18, 23A, 30, 31,&33 AND FMRS 9-29&35. |
| Oct 28, 2016 | A00022 | $0 | CVN 73 RCOH ADVANCE PLANNING, AUTHORIZATION OF E&S POOL MRC 116&MRC 117. |
| Oct 13, 2016 | A00020 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL MRC #82 AUTHORIZATION. |
| Oct 13, 2016 | A00021 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL, ADJUDICATION OF MRC PROPOSALS 26, 27, 28 AND FMRS 7.00, 8.00 AND 34.00. |
| Oct 5, 2016 | A00018 | $1.1M | CVN 73 RCOH ADVANCE PLANNING, CLIN 0018 ESTABLISHED/FUNDED FOR HUNTINGTON HALL OFF-SHIP BERTHING AND MESSING REQUIREMENTS. |
| Oct 5, 2016 | A00019 | $0 | CVN 73RCOH ADVANCE PLANNING, E&S POOL MRC #80, #92 AND #99 AUTHORIZATION. |
| Sep 29, 2016 | A00017 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 52.00 |
| Sep 28, 2016 | A00016 | $3.3M | CVN 73 RCOH ADVANCE PLANNING, ESTABLISH CLIN 0017 FOR FUKUSHIMA RELATED REMEDIATION. |
| Sep 22, 2016 | P00023 | $0 | FY15 RCOH ADVANCE PLANNING |
| Aug 30, 2016 | A00015 | $0 | CVN 73 RCOH ADVANCE PLANNING, ADJUDICATION OF E&S MRC PROPOSALS 21, 22&23. |
| Aug 20, 2016 | A00013 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 35.00 |
| Aug 20, 2016 | A00014 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL MRC ITEM #56 |
| Aug 15, 2016 | A00007 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 14.00&FMR 15.00 |
| Aug 15, 2016 | A00008 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 16.00, FMR 17.00&FMR 18.00 |
| Aug 15, 2016 | A00009 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 19.00, FMR 20.00, FMR 21.00&FMR 22.00 |
| Aug 15, 2016 | A00010 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 23.00, FMR 24.00, FMR 25.00&FMR 26.00 |
| Aug 15, 2016 | A00011 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 27.00, FMR 28.00&FMR 29.00 |
| Aug 15, 2016 | A00012 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 34.00 |
| Aug 6, 2016 | A00005 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMRS 9.00 - 12.00 |
| Aug 6, 2016 | A00006 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 13.00 |
| Jul 25, 2016 | A00004 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL MRC 41A, 56, 58&59 |
| Jul 22, 2016 | P00022 | $221.3M | ESTABLISH THE REQUIREMENT FOR FUKUSHIMA REMEDIATION OF CVN 73 DURING THE RCOH ADVANCE PLANNING AND EXTEND THE PERIOD OF PERFORMANCE FOR CLIN 0006 THROUGH 04 AUGUST 2017 TO COINCIDE WITH THE START OF THE CVN 73 RCOH EXECUTION. |
| Jul 19, 2016 | A00002 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 7.00 |
| Jul 19, 2016 | A00003 | $0 | CVN 73 RCOH ADVANCE PLANNING, E&S POOL FMR 8.00 |
| Jun 23, 2016 | P00021 | $0 | ESTABLISH NEW MATERIAL REQUIREMENTS IN SUPPORT OF CVN 73 RCOH ADVANCE PLANNING EFFORT. |
| Jun 1, 2016 | P00020 | $17.0M | ESTABLISH NEW MATERIAL REQUIREMENT AND ESTABLISH MATERIAL POOL FOR EMERGENT AND SUPPLEMENTAL MATERIAL REQUIREMENTS. |
| May 23, 2016 | A00001 | $0 | TRANSFER OF GOVERNMENT PROPERTY TO THE CVN 73. |
| Apr 19, 2016 | P00019 | $3.3M | PY1 INCENTIVE FEE EARNED |
| Apr 18, 2016 | P00018 | $0 | MATERIAL PROPOSAL #10 |
| Feb 26, 2016 | P00017 | $185.3M | THE PURPOSE OF THIS MODIFICATION IS TO 1) UNDER SECTION B, INCREASE THE TOTAL COST OF LINE ITEM 0006 BY $198,151,883 ($184,402,666 COST AND $13,749,217 FIXED FEE) AND THE TOTAL HOURS BY 1,726,132; 2) INCREASE THE TOTAL COST OF LINE ITEM 0010 BY $193,351,254 ($179,924,059 COST AND $13,427,195 FIXED FEE) AND THE TOTAL HOURS BY 34,053; 3) INCREASE THE TOTAL COST OF LINE ITEM 0015 BY $2,359,369 ($2,194,762 COST AND $164,607 FIXED FEE); 4) UPDATE THE B-9, B-10, AND B-11 INCENTIVES ACCORDINGLY; 5) UNDER SECTION F, AMEND LINE ITEM 0006 END DATE; 6) UNDER SECTION G, INCREMENTALLY FUND LINE ITEM 0006XX IN THE AMOUNT OF $139,937,515 ($130,174,433 COST AND $9,763,082 FIXED FEE) AND LINE ITEM 0015XX IN THE AMOUNT OF $12,299,313 ($11,441,222 COST AND $858,091 FIXED FEE); 7) UNDER SECTION H, UPDATE 5252.232-9104 AND 5252.216-9122 ACCORDINGLY; 8) UNDER SECTION I, UPDATE 52.222-2 ACCORDINGLY; AND 9) UNDER SECTION J, UPDATE THE EXHIBITS A, B, C, AND D, ATTACHMENT B AND ATTACHMENT K ACCORDINGLY. |
| Feb 4, 2016 | P00016 | $11.7M | EXERCISE PLANNING YEAR 2 AND INCENTIVES; ESTABLISH MAN-HOURS, PRICING, AND PROVIDE FUNDING FOR BRIDGING RCOH PLANNING SERVICES; EXTEND CLIN 0014 PERIOD OF PERFORMANCE; UPDATE ATTACHMENT K AND DISTRIBUTION LIST FOR CONTRACT DATA REQUIREMENTS LIST. |
| Jan 20, 2016 | P00015 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO 1) UNDER SECTION B, TRANSFER CEILING AND FUNDING FROM LINE ITEM 0001 IN THE AMOUNT OF $17,631 ($16,401 IN COST, $1,230 IN FIXED FEE) ASSOCIATED WITH PY1 FREIGHT TO LINE ITEM 0015; 2) INCREASE THE TOTAL COST OF LINE ITEM 0015 BY $1,809,693 ($1,683,435 IN COST, $126,258 IN FIXED FEE) INCLUDING THE ABOVE CEILING TRANSFER; 3) UPDATE THE B-9, B-10, AND B-11 INCENTIVES ACCORDINGLY (LINE ITEMS 0002, 0003, 0004, AND 0011); 4) UNDER SECTION C, REVISE LINE ITEM 0015 SOW TO INCLUDE DELIVERY OF MATERIAL; 5) UNDER SECTION G, DECREASE SUB LINE ITEM 000102 FUNDING (ACRN AB) BY $17,631 AND INCREMENTALLY FUND SUB LINE ITEM 001502 IN THE AMOUNT OF $17,631; AND 6) UNDER SECTION H, UPDATE THE ALLOTMENT OF FUNDS CLAUSE ACCORDINGLY. |
| Nov 23, 2015 | P00014 | $0 | INCREASE CLIN 0015 FOR ADDITIONAL MATERIAL REQUIREMENTS (MATERIAL PROPOSAL #5 - HARD SIDED CONTAINMENTS AND CLAMPS) |
| Oct 28, 2015 | P00013 | $20.3M | INCREAS PY1 LOE BY 161,500 MHS AND CLIN 0015 MATERIAL REQUIREMENTS |
| Oct 2, 2015 | P00012 | $0 | CVN 73 RCOH ADVANCE PLANNING MATERIAL (TG ROTORS) |
| Sep 28, 2015 | P00011 | $0 | THE PURPOSE OF THIS MODFIICATION IS TO 1) UNDER SECTION B, INCREASE LINE ITEM 0001 COST BY $8,969 AND FIXED FEE BY $673; 2) UPDATE INCENTIVES B-9, B-10, AND B-11 ACCORDINGLY; AND 3) UNDER SECTION J, UPDATE ATTACHMENT B - EXCEPTIONS AND CLARIFICATIONS. |
| Jul 31, 2015 | P00010 | $280.0K | THE PURPOSE OF THIS MODIFICATION IS TO INCORPORATE ITEM 473 (LSTR CUSTOM CUTTING SYSTEM - NNPN 17899878) UNDER ATTACHMENT K; INCREASE THE CONTRACT COST AND TOTAL FUNDED AMOUNT BY $280,006; AND UPDATE CLAUSES B-9, B-10, AND B-11 ASSOCIATED WITH THIS MODIFICATION. |
| May 6, 2015 | P00009 | $160.1M | COST REDUCTION INITIATIVES, FUNDING, AND ADMIN CHANGES |
| Feb 23, 2015 | P00008 | $0 | ADMIN CHANGE TO REFLECT THE APPROPRIATE CONTRACT VALUE. |
| Feb 4, 2015 | P00007 | $57.5M | PLANNING YEAR 1 OF CVN 73 RCOH ADVANCE PLANNING AND CVN 73 RCOH MATERIAL |
| Jan 28, 2015 | P00006 | $0 | REVISE SECTION B CLIN 0001 AND TABLE B-1 MAN HOURS TO ACCOUNT FOR INCREASED MATERIAL COSTS FOR FY2015 SHIP CHECKS. |
| Dec 17, 2014 | P00005 | $0 | UPDATE SOW TO INCLUDE SHIPCHECK EFFORTTS |
| Dec 5, 2014 | P00004 | $0 | MAN-HOUR TO MATERIAL EXCHANGE TO SUPPORT THE CVN 73 SHIP CHECKS |
| Nov 12, 2014 | P00003 | $0 | REVISE SECTION B CLIN 0001 AND TABLE B-1 MAN HOURS TO ACCOUNT FOR INCREASED MATERIAL COSTS FOR FY2015 SHIP CHECKS. |
| Oct 16, 2014 | P00002 | $0 | UPDATE STATEMENT OF WORK TO INCLUDE SOFT START ITEMS. |
| Sep 25, 2014 | P00001 | $0 | SHIP CHECK PREPARATION AND COST REDUCTION INITIATIVES |
| Aug 1, 2014 | 0 | $49.6M | PY1 RCOH DEFUELING ADVANCE PLANNING |