Federal contract award

N0002416C2427

DETAIL DESIGN AND CONSTRUCTION (DD&C) FOR LHA 8 (INITIAL EFFORT LIMITED TO PLANNING, ADVANCED ENGINEERING AND PROCUREMENT OF LONG LEAD TIME MATERIAL)

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeSUP OF SHIPBUILDING CONV AND REPAIR
NAICS336611 — Ship Building and Repairing
PSC1905 — Combat Ships and Landing Vessels
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIXED PRICE INCENTIVE
Obligations$3.4B
Current contract value$3.5B
Potential contract value / ceiling$3.5B
Start dateJun 30, 2016
Current end dateDec 31, 2026
Potential end dateDec 31, 2026
Latest award activityMay 26, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 200 of 676 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
May 26, 2026A00585$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 6, 2026A00584$1.0MLHA 8 DETAIL DESIGN AND CONSTRUCTION
May 4, 2026A00583$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 27, 2026A00582$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 22, 2026A00581$10.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 8, 2026P00077$53.7MFPDS-NG VALUE TO ALLOW POSTING
Mar 31, 2026A00580$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 16, 2026P00075$70.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 16, 2026P00076$4.8MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 11, 2026A00579$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 30, 2026P00074$40.0MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 28, 2026A00578$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 16, 2026A00577$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 16, 2025A00576$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 11, 2025A00575$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 10, 2025P00073$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 4, 2025A00574$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 17, 2025A00572$365.7KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 17, 2025A00573$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 12, 2025A00571$2.4MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 3, 2025A00570$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 23, 2025A00568$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 23, 2025A00569$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 24, 2025A00567$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 23, 2025A00566$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 16, 2025A00565$8.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 8, 2025A00564$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 25, 2025A00562$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 25, 2025A00563$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 20, 2025A00561$-8.6KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 14, 2025A00559$-16.7KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 14, 2025A00560$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 13, 2025A00558$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 12, 2025A00557$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 31, 2025A00555$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 31, 2025A00556$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 14, 2025A00554$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 14, 2025P00072$350.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 10, 2025A00553$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 26, 2025P00071$79.4MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 11, 2025A00552$10.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 5, 2025A00551$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 28, 2025A00550$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 27, 2025AZ0012$64.7KLHA 8 DETAIL DESIGN AND CONSTRUCTION
May 20, 2025A00549$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 19, 2025A00548$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 25, 2025P00070$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 26, 2025A00547$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 24, 2025A00546$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 17, 2025A00545$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 28, 2025A00544$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 24, 2025P00069$270.0KFUNDING MOD
Feb 13, 2025A00542$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 13, 2025A00543$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 31, 2025A00541$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 28, 2025A00540$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 23, 2025A00539$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 22, 2025A00537$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 22, 2025A00538$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 17, 2025A00536$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 13, 2025A00533$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 13, 2025A00534$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 13, 2025A00535$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 20, 2024A00532$3.1MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 17, 2024A00531$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 17, 2024P00068$117.5KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 9, 2024A00530$500.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 21, 2024A00529$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 20, 2024A00528$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 13, 2024A00527$8.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 6, 2024P00067$250.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 31, 2024A00526$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 29, 2024A00525$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 15, 2024A00523$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 15, 2024A00524$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 7, 2024A00522$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 1, 2024A00521$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 12, 2024A00520$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 12, 2024P00066$-41.8KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 28, 2024P00065$108.2KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 27, 2024A00519$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 16, 2024A00518$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 7, 2024A00517$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 31, 2024A00516$3.4MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 24, 2024A00515$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 16, 2024A00514$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 10, 2024A00513$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 1, 2024A00511$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 1, 2024A00512$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 18, 2024A00510$8.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 17, 2024A00509$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 11, 2024A00508$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 4, 2024A00507$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 21, 2024A00506$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 9, 2024A00505$203.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 30, 2024P00064$340.8KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 23, 2024A00504$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 10, 2024A00503$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 26, 2024A00501$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 26, 2024A00502$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 20, 2024A00500$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 18, 2024AZ0011$592.9KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 5, 2024A00499$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 29, 2024A00497$390.2KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 29, 2024A00498$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 28, 2024A00496$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 21, 2024P00063$131.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 13, 2024AZ0010$155.7KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 8, 2024A00495$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 30, 2024A00494$10.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 30, 2024AZ0009$280.4KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 24, 2024A00493$1.3MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 24, 2024AZ0008$277.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 12, 2024A00492$1.0MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 9, 2024A00491$1.4MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 19, 2023A00490$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 13, 2023A00487$112.5KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 13, 2023A00488$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 13, 2023A00489$77.1KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 6, 2023A00486$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 30, 2023A00485$138.7KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 30, 2023P00062$4.7MLHA 8 DETAIL DESIGN AND CONSTRUCTION. LAUNCH INCENTIVE FUNDING SLIN 000306.
Nov 28, 2023A00483$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 28, 2023A00484$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 16, 2023A00482$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 16, 2023P00061$276.9KLHA 8 DETAIL DESIGN AND CONSTRUCTION. INCENTIVE FUNDING AND SPECIAL STUDIES FUNDING.
Oct 31, 2023A00481$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 30, 2023A00480$843.5KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 19, 2023A00478$76.2KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 19, 2023A00479$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 17, 2023A00477$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 10, 2023A00475$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 10, 2023A00476$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 10, 2023P00060$0LHA 8 DETAIL DESIGN AND CONSTRUCTION, SHIFT HOURS UNDER CLINS AND CHANGE POP
Sep 20, 2023A00474$3.3MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 19, 2023A00472$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 19, 2023A00473$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 13, 2023A00471$87.3KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 7, 2023A00470$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Sep 1, 2023P00059$0LHA 8 DETAIL DESIGN AND CONSTRUCTION SECTION B INCENTIVES UPDATE
Aug 30, 2023AZ0006$96.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 30, 2023AZ0007$22.7KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 25, 2023AZ0005$196.5KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 23, 2023A00469$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 18, 2023A00467$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 18, 2023A00468$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 17, 2023AZ0004$72.2KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Aug 10, 2023A00466$10.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 27, 2023P00058$-61.3KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 26, 2023A00465$41.3KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 25, 2023A00463$194.3KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 25, 2023A00464$131.2KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jul 12, 2023A00462$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 20, 2023A00461$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 14, 2023P00057$240.9KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 13, 2023A00460$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 7, 2023A00459$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jun 6, 2023A00458$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 31, 2023A00456$483.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
May 31, 2023A00457$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 23, 2023AZ0003$266.7KLHA 8 DETAIL DESIGN AND CONSTRUCTION
May 18, 2023A00455$662.2KLHA 8 DETAIL DESIGN AND CONSTRUCTION
May 18, 2023P00056$710.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
May 12, 2023A00454$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
May 11, 2023A00453$2.8MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 25, 2023A00452$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 24, 2023A00451$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 21, 2023P00055$400.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 7, 2023A00449$1.0MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 7, 2023A00450$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Apr 4, 2023A00448$18.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 28, 2023A00447$2.9MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 27, 2023P00054$589.6KLHA 8 SNUBBERS MATERIAL ONLY
Mar 17, 2023A00446$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Mar 9, 2023P00053$1.6MFUNDING ONLY
Feb 24, 2023A00445$391.5KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 22, 2023A00444$10.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 15, 2023A00443$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 14, 2023A00442$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Feb 9, 2023A00441$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 30, 2023A00440$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 25, 2023A00439$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 23, 2023A00437$1.6MLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 23, 2023A00438$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 17, 2023A00436$-76.4KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Jan 10, 2023P00052$100.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION. DEOB AND OBLIGATION OF FUNDING. CHANGE OF COR INFO UNDER SECTION G.
Dec 22, 2022A00435$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 15, 2022A00434$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 12, 2022A00433$332.2KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Dec 5, 2022A00432$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 23, 2022A00431$283.2KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 21, 2022A00430$395.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 14, 2022A00428$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 14, 2022A00429$211.4KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Nov 7, 2022P00051$1.1MEXERCISE OPTION CLIN 0011, FUNDING CLIN 0003 AND 0011.
Nov 4, 2022A00427$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 25, 2022A00426$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 18, 2022A00425$12.0KLHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 5, 2022A00424$0LHA 8 DETAIL DESIGN AND CONSTRUCTION
Oct 3, 2022A00423$0LHA 8 DETAIL DESIGN AND CONSTRUCTION

Estimated positioning window

Nov 1, 2026 – Jan 30, 2027

Recompete signal:
80/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 80/100. Available recorded signals: 75 points.

Contract end 2026-12-31 (60 days from calculation)
+35 points
21 historical awards in this buyer and category group
+15 points
676 recorded award transactions
+10 points
Latest award action: 2026-05-26
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-11-01 10:17:53.997580+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Nov 1, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.