Federal contract award
N0002418C2301
MMSC DETAILED DESIGN AND CONSTRUCTION
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NAVSEA HQ |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | 1905 — Combat Ships and Landing Vessels |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIXED PRICE INCENTIVE |
| Obligations | $3.4B |
| Current contract value | $4.0B |
| Potential contract value / ceiling | $4.0B |
| Start date | Mar 2, 2018 |
| Current end date | Feb 28, 2029 |
| Potential end date | Feb 28, 2029 |
| Latest award activity | Jun 10, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 121 of 121 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 10, 2026 | P00047 | $0 | FAR 52.222-90 INCORPORATION |
| May 28, 2026 | P00046 | $194.5K | INDIAN INCENTIVE PROGRAM EARNED INCENTIVE PAYMENTS |
| May 4, 2026 | P00045 | $7.0M | INCREMENTAL LEVEL OF EFFORT FUNDING |
| Apr 28, 2026 | P00044 | $0 | ADMIN UPDATE AND IPDME NO COST EXTENSION |
| Feb 26, 2026 | A00071 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Feb 11, 2026 | P00043 | $0 | DD254 UPDATE |
| Nov 5, 2025 | P00042 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 15, 2025 | A00070 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Sep 30, 2025 | A00069 | $-7.6K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Aug 19, 2025 | P00041 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jul 3, 2025 | A00068 | $590.6K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jun 30, 2025 | P00040 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jun 5, 2025 | A00067 | $-140.5K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Apr 30, 2025 | P00039 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Apr 22, 2025 | P00038 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Apr 14, 2025 | A00066 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Mar 13, 2025 | A00065 | $-15.0K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Feb 18, 2025 | P00037 | $21.8M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jan 30, 2025 | A00064 | $-11.5M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jan 14, 2025 | A00063 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Dec 10, 2024 | PZ0002 | $7.7M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 22, 2024 | A00062 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 19, 2024 | A00061 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 18, 2024 | P00036 | $143.5M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 30, 2024 | A00060 | $0 | REDUCED SCOPE ALTERNATE GEARS PROCUREMENT |
| Oct 10, 2024 | A00059 | $301.6K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 7, 2024 | A00058 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Sep 16, 2024 | P00035 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Aug 7, 2024 | A00057 | $-11.1M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jul 26, 2024 | P00034 | $95.1K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jun 11, 2024 | A00056 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| May 21, 2024 | P00033 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Apr 26, 2024 | P00032 | $9.0M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Mar 27, 2024 | P00031 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jan 19, 2024 | A00055 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jan 11, 2024 | A00054 | $-14.5K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Dec 26, 2023 | P00030 | $74.2M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Dec 18, 2023 | P00029 | $39.2M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Dec 8, 2023 | A00053 | $55.8K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 15, 2023 | A00052 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 18, 2023 | A00051 | $-24.2M | MMSC DEOBLIGATION MOD |
| Sep 1, 2023 | A00050 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Aug 21, 2023 | P00028 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jul 10, 2023 | P00027 | $510.0K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jun 28, 2023 | A00049 | $-10.4K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jun 21, 2023 | A00048 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jun 14, 2023 | A00047 | $260.8K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jun 8, 2023 | A00046 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| May 25, 2023 | P00026 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| May 12, 2023 | A00045 | $4.1M | FCS 57 WITH TOPLITE PROCUREMENT |
| Apr 24, 2023 | A00044 | $1.5M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Apr 13, 2023 | P00025 | $4.0M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Apr 10, 2023 | A00043 | $0 | MMSC BILLING PRICE AND WEIGHTING FACTORS |
| Mar 6, 2023 | A00042 | $-24.3K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Feb 24, 2023 | A00041 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Feb 15, 2023 | P00024 | $12.1M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Dec 15, 2022 | A00040 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 23, 2022 | A00039 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 2, 2022 | P00023 | $13.2M | MMSC DETAILED DESIGN AND CONSTRUCTION - FUNDING |
| Oct 28, 2022 | A00038 | $2.8M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 28, 2022 | P00022 | $0 | LM CAGE CODE UPDATE |
| Oct 26, 2022 | A00037 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 7, 2022 | A00036 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 6, 2022 | ARZ999 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Sep 26, 2022 | A00035 | $42.6M | MMSC ALTERNATE GEARS |
| Jul 28, 2022 | A00034 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jul 26, 2022 | A00033 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jul 1, 2022 | A00032 | $804.8K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| May 26, 2022 | A00030 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| May 25, 2022 | P00021 | $2.1M | MMSC DD&C FUNDING ACTION |
| May 4, 2022 | A00029 | $7.5M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Apr 29, 2022 | A00028 | $-53.7K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Mar 24, 2022 | A00027 | $2.5M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Mar 14, 2022 | A00026 | $-3.4K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Mar 7, 2022 | A00025 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jan 18, 2022 | P00020 | $5.3M | FUNDING AND CDRL UPDATE |
| Jan 11, 2022 | A00024 | $6.6M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Dec 21, 2021 | A00023 | $2.2M | PCW-0027R1 |
| Dec 9, 2021 | A00022 | $574.6K | PCW-0002R2 |
| Dec 3, 2021 | A00021 | $-13.6K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Dec 2, 2021 | P00019 | $5.2M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 24, 2021 | A00020 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 20, 2021 | A00019 | $1.7M | PCW-0009 |
| Oct 7, 2021 | A00018 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Sep 23, 2021 | A00017 | $0 | CORRECTION OF A00013 ATTACHMENT |
| Sep 20, 2021 | A00015 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Sep 20, 2021 | A00016 | $0 | CY20 EPA |
| Sep 15, 2021 | A00013 | $0 | 2Q21 REVISED BILLING |
| Sep 15, 2021 | A00014 | $1.5M | PCW-0014 AND PCW-0016 |
| Sep 14, 2021 | A00012 | $347.6K | PCW-0003R2 AND PCW-0012 |
| Sep 7, 2021 | P00018 | $0 | FUNDING REALIGNMENT |
| Aug 25, 2021 | A00011 | $2.6M | SHIPBOARD HELICOPTER HANDLING SYSTEM ORDER |
| Jun 17, 2021 | A00010 | $0 | 1Q21 REVISED BILLING |
| Jun 10, 2021 | A00009 | $0 | REQUEST FOR VARIANCES 005, 008 AND 009 |
| May 3, 2021 | A00008 | $0 | INDUSTRY PROCUREMENT OF UNNEEDED NAVY TEST EQUIPMENT |
| Apr 28, 2021 | P00017 | $0 | THE PURPOSE OF THIS MODIFICATION TO N00024-18-C-2301 IS TO MODIFY CDRL FORM DD 1423S, DELETE CDRL FORM DD 1423S, UPDATE SECTION C, AND ENACT CDRL SUBMITTAL AND REVIEW TIMELINE EXTENSIONS. |
| Apr 14, 2021 | A00007 | $0 | EPA 2019 |
| Mar 23, 2021 | A00005 | $0 | RFVS 001 & 002 |
| Mar 23, 2021 | A00006 | $0 | RFV 003 |
| Feb 11, 2021 | A00004 | $0 | 4TH QTR 2020 REVISED BILLING |
| Jan 15, 2021 | P00016 | $0 | ADMINISTRATIVE UPDATES |
| Nov 9, 2020 | A00003 | $0 | THIRD QUARTER 2020 REVISED BILLING AND WEIGHT FACTORS |
| Jul 14, 2020 | P00015 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jul 9, 2020 | P00014 | $220.0K | MMSC DETAILED DESIGN AND CONSTRUCTION |
| May 18, 2020 | P00013 | $9.0M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Mar 20, 2020 | P00012 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Dec 20, 2019 | PZ0001 | $2.3B | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 21, 2019 | P00011 | $18.7M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 22, 2019 | P00010 | $20.0M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Oct 17, 2019 | P00009 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Sep 26, 2019 | P00008 | $19.9M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Aug 27, 2019 | P00007 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Aug 14, 2019 | P00006 | $20.6M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Aug 1, 2019 | P00005 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Feb 21, 2019 | P00004 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Nov 16, 2018 | P00003 | $124.2M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Aug 24, 2018 | A00002 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Aug 14, 2018 | A00001 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jul 16, 2018 | P00002 | $225.4M | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Jun 19, 2018 | P00001 | $0 | MMSC DETAILED DESIGN AND CONSTRUCTION |
| Mar 2, 2018 | 0 | $240.6M | MMSC DETAILED DESIGN AND CONSTRUCTION |
Estimated positioning window
Feb 28, 2028 – Aug 28, 2028
60/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 60/100. Available recorded signals: 55 points.
- Contract end 2029-02-28 (857 days from calculation)
- +15 points
- 126 historical awards in this buyer and category group
- +15 points
- 121 recorded award transactions
- +10 points
- Latest award action: 2026-06-10
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-10-25 10:18:04.631876+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Oct 25, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.