Federal contract award

N0002418C2406

LPD 30 LLTM

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeSUP OF SHIPBUILDING CONV AND REPAIR
NAICS336611 — Ship Building and Repairing
PSC1905 — Combat Ships and Landing Vessels
Parent award / vehicleNot reported
Set-asideNO SET ASIDE USED.
Pricing typeFIXED PRICE INCENTIVE
Obligations$4.7B
Current contract value$5.2B
Potential contract value / ceiling$5.2B
Start dateAug 2, 2018
Current end dateMar 1, 2031
Potential end dateMar 1, 2031
Latest award activityJun 2, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 200 of 357 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Jun 2, 2026A00321$0LDP 30 REQUEST FOR WAIVER (RFW) 0838 PROPULSION SHAFTING CORROSION AND PITTING- NO COST
May 28, 2026A00320$0LPD 32 DETAIL DESIGN AND CONSTRUCTION
May 18, 2026AZ0012$649.9KHEADQUARTERS MODIFICATION REQUEST (HMR) 450 LPD 31 ENGINEERING CHANGE REQUEST (ECR) 2645 REV 1 UNITED STATES MARINE CORP (USMC) SPACE SAVER LOCKERS, DEFINITIZATION OF A00243
May 13, 2026A00319$1.8MN00024-18-C-2406 HANDLING WATERFRONT TASK AUTHORIZATION (WTA) OVER THRESHOLD IN ALIGNMENT WITH ECR STANDARDS HMR 492, LPD 30, ACRN TA, CLIN 0001 HMR 488, LPD 31, ACRN TB, CLIN 0401 HMR 493, LPD 32, ACRN TE, CLIN 0501
Apr 24, 2026A00317$0LPD 30 DETAIL DESIGN AND CONSTRUCTION REQUEST FOR WAIVER (RFW) 0810 DECK TOLERANCES (DECK HEIGHT) CONTRACT LINE ITEM NUMBER 0001
Apr 24, 2026A00318$0HEADQUARTERS MODIFICATION REQUEST 319 LPD 30 WATERFRONT TASK AUTHORIZATION POOL CHANGES 1ST QUARTER 2026
Apr 22, 2026A00316$0HEADQUARTERS MODIFICATION REQUEST 353 LPD 31 WATERFRONT TASK AUTHORIZATION POOL CHANGES 1ST QUARTER 2026
Mar 31, 2026P00023$79.4MLPD 32 DETAIL DESIGN AND CONSTRUCTION
Mar 27, 2026A00315$0LPD 30 REQUEST FOR WAIVER(RFWQ) 0831 TWISTED TEE FLANGES. NO COST.
Mar 20, 2026A00314$8.8MLPD 31 DETAIL DESIGN AND CONSTRUCTION CONTRACT LINE ITEM NUMBER (CLIN) 0401 UNPRICED CHANGE ORDER (UCO) FOR ENGINEERING CHANGE REQUEST (ECR) 2724 REPLACE HIGH TEMPERATURE SUPERCONDUCTING DEGAUSSING WITH COPPER DEGAUSSING
Mar 18, 2026A00313$0LPD 30 DETAIL DESIGN AND CONSTRUCTION REQUEST FOR WAIVER (RFW) 0818 VEHICLE MINIMUM CLEARANCE - NO COST
Mar 17, 2026A00312$0THIS MODIFICATION INCORPORATES TECHNICALLY APPROVED, NO COST REQUEST FOR WAIVER (RFW) 0837 LPD 30 PASSAGEWAY CLEARANCE 2-80-5-L-ES 98 DUCTING.
Mar 13, 2026A00310$5.1MLPD 32 UNPRICED CHANGE ORDER (UCO) ENGINEERING CHANGE REQUEST (ECR) 2724 REPLACE HIGH TEMPERATURE SUPERCONDUCTING (HTS) DEGAUSSING WITH COPPER DEGAUSSING CONTRACT LINE ITEM NUMBER 0501
Mar 13, 2026A00311$0LPD 30 REQUEST FOR WAIVER 0832 (FIRE DETECTION SYSTEM SHORT CIRCUIT ISOLATORS AND CABLING) NO COST CONTRACT LINE ITEM NUMBER 0001
Mar 6, 2026A00309$-546.2KHEADQUARTERS MODIFICATION REQUEST (HMR) 353 WATERFRONT TASK AUTHORIZATION (WTA) POOL DECREASE FOR LPD 31
Feb 19, 2026A00308$0LPD 31 WATERFRONT TASK AUTHORIZATION (WTA) POOL 4TH QUARTER 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR 353)
Feb 4, 2026A00307$0LPD 30 REQUEST FOR WAIVER (RFW) 0834 NO. 1 EXHAUST BELLOW INSTALLATION MISALIGNMENT
Jan 6, 2026A00306$-1.0MLPD 30 CONTRACT LINE ITEM NUMBER 0001 HEADQUARTERS MODIFICATION REQUEST ENGINEERING CHANGE REQUEST 2707 DEGAUSSING SYSTEM STOP WORK
Dec 18, 2025A00305$0LPD 30 DETAIL DESIGN AND CONSTRUCTION REQUEST FOR WAVIER (RFW) 0835 (MEDICAL WARD CURTAIN RAILING HEIGHT)
Dec 17, 2025A00303$0LPD 30 WATERFRONT TASK AUTHORIZATION (WTA) POOL CHANGES QUARTER 3 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR) 319
Dec 17, 2025A00304$0HEADQUARTERS MODIFICATION REQUEST (HMR) 423 LPD 32 QUARTER 3 2025 WATERFRONT TASK AUTHORIZATION (WTA)
Dec 15, 2025A00301$3.7MLPD 30 DETAIL DESIGN AND CONSTRUCTION UNPRICED CHANGE ORDER (UCO) FOR ENGINEERING CHANGE REQUEST (ECR) 2728 ADVANCED DEGAUSSING SYSTEM MATERIAL PURCHASE CONTRACT LINE ITEM NUMBER (CLIN) 0001
Dec 15, 2025A00302$0LPD 31 WATERFRONT TASK AUTHORIZATION (WTA) POOL 2ND QUARTER 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR 353)
Oct 7, 2025A00300$1.9MLPD 30 HEADQUARTERS MODIFICATION REQUEST (HMR) 461 CONSOLIDATED SHIPBOARD ALLOWANCE LIST INCREMENT 4. CONTRACT LINE ITEM NUMBER 0005
Oct 6, 2025A00299$689.0KENGINEERING CHANGE REQUEST 2655 LPD 31 32 CONTRACT LINE ITEM NUMBERS 0401 0501 - FIRE SAFETY CHANGES - HEADQUARTERS MODIFICATION REQUEST 471
Oct 2, 2025A00298$-774.9KLPD 30 WATERFRONT TASK AUTHORIZATION POOL DEOB
Sep 30, 2025A00297$0FIELD MODIFICATION REQUEST (FMR) 1950 NO COST MODIFICATION THAT INCORPORATES VARIOUS CONDITION REPORTS (CRS)
Sep 11, 2025A00296$0LPD 32 2ND QUARTER 2025 REWEIGHTS AND BILLINGS
Sep 8, 2025A00295$0ADMIN MOD TO A00272
Sep 3, 2025A00294$-505.9KLPD 32 WATERFRONT TASK AUTHORIZATION POOL DECREASE - HEADQUARTERS MODIFICATION REQUEST 423
Aug 15, 2025A00293$0INCORPORATE LPD 30 REQUEST FOR WAIVER (RFW) 0824 - BOAT AND CARGO CRANE INTO THE BASE CONTRACT AT NO COST - CONTRACT LINE ITEM NUMBER 0001
Aug 1, 2025A00292$0HEADQUARTERS MODIFICATION REQUEST 423 LPD 32 QUARTER 2 2025 WATERFRONT TASK AUTHORIZATION CONTRACT LINE ITEM 0501
Jul 31, 2025A00291$2.5MLPD 31 AND 32 ENGINEERING CHANGE REQUEST 2650: MORIAH WIND SYSTEM BOUNDARY DEFENSE NETWORK RACK - HEADQUARTERS MODIFICATION REQUEST 463 CONTRACT LINE ITEM NUMBERS 0401 AND 0501
Jul 11, 2025A00290$0LPD 31 DETAIL DESIGN AND CONSTRUCTION WATERFRONT TASK AUTHORIZATION (WTA)POOL 2ND QUARTER 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR) 353
Jul 9, 2025A00289$0LPD 30 WATERFRONT TASK AUTHORIZATION (WTA) POOL CHANGES QUARTER 2 2025 - HEADQUARTERS MODIFICATION REQUEST (HMR) 319
Jul 8, 2025P00022$19.2MLPD 32 DETAIL DESIGN AND CONSTRUCTION
Jul 2, 2025A00288$0RFW 0829 NO COST
Jun 26, 2025A00287$86.2KLPD 31 AND 32 ENGINEERING CHANGE REQUEST 2685 - HEADQUARTERS MODIFICATION REQUEST (HMR) 458: ADD HEAT DETECTORS TO COLLECTIVE PROTECTION SYSTEM (CPS) FAN ROOM DIRTY SIDE, CONTRACT LINE ITEM NUMBERS (CLIN) 0401 AND 0501
Jun 25, 2025P00021$45.0MLPD 32 DETAIL DESIGN AND CONSTRUCTION
Jun 18, 2025A00286$10.6MLPD 31 AND 32 DETAIL DESIGN AND CONSTRUCTION UNPRICED CHANGE ORDER FOR HEADQUARTERS MODIFICATION REQUEST 469 ENGINEERING CHANGE REQUEST 2697 ADD ADDITIONAL AC PLANT - CONTRACT LINE ITEM NUMBERS 0401 AND 0501
Jun 6, 2025A00285$720.9KHEADQUARTERS MODIFICATION REQUEST (HMR) 466 ENGINEERING CHANGE REQUEST (ECR) 2693 LPD 30-32 MAIN PROPULSION DIESEL ENGINE (MPDE) ALIGNMENT. CONTRACT LINE ITEM NUMBER (CLIN) 0001 LPD 30 CLIN 0401 LPD 31 CLIN 0501 LPD 32
May 30, 2025A00284$30.8KLPD 31 AND 32 FIELD MODIFICATION REQUEST (FMR) 1925 ENGINEERING CHANGE REQUEST (ECR) 2692: 12CK INSTALLATION AS INTERCOMMUNICATION ANNOUNCING SYSTEM CONTRACT LINE ITEM NUMBER (CLIN) 0401 0501
May 29, 2025P00020$-200.4KLPD 32 DETAIL DESIGN AND CONSTRUCTION
May 27, 2025A00281$0LPD 30 REQUEST FOR WAIVER (RFW) 0821 (FILLER COMPOUND-FAIRWATER) NO COST.
May 27, 2025A00282$1.0MHMR 423 FUNDING PLUS UP $1M WTA LPD 32
May 27, 2025A00283$23.6KFIELD MODIFICATION REQUEST (FMR) 1926 ENGINEERING CHANGE REQUEST (ECR) 2702 LPD 32 REPLACEMENT OF AN/UPX-45 (C) WITH AN/UPX-50 - CONTRACT LINE ITEM NUMBER 0501
May 21, 2025A00280$800.0KLPD 30 HMR 319 CLIN 0001 FUNDING PLUS UP
May 13, 2025A00279$404.5KWTA 30176 (NCDS AND ICDN UPDATES PART 2)
May 7, 2025A00278$0REQUEST FOR WAIVER (RFW) 0823 NO COST WAIVER LPD 30: WELD DEFECTS ON THE BACK UP STRUCTURE FOR THE STERN GATE HYDRAULIC POWER UNIT (HPU) ASSEMBLY
May 2, 2025A00277$17.5KLPD 31 ENGINEERING CHANGE REQUEST 2711 ADDITIONAL DEGAUSSING CABLE CONDUITS - CONTRACT LINE ITEM 0401 - FIELD MODIFICATION REQUEST 1927
Apr 29, 2025A00275$0WATERFRONT TASK AUTHORIZATION (WTA)POOL QUARTER 4 2024 HEADQUARTERS MODIFICATION REQUEST (HMR) 353 LPD 31
Apr 29, 2025A00276$0HEADQUARTER MODIFICATION REQUEST 423 LPD 32 WATERFRONT TASK AUTHORIZATION POOL CHANGES 4TH QUARTER 2024
Apr 28, 2025A00274$0HEADQUARTER MODIFICATION REQUEST (HMR) 319 LPD 30 WATERFRONT TASK AUTHORIZATION Q4 2024
Mar 19, 2025A00273$0FIELD MODIFICATION REQUEST (FMR) 1928 VARIOUS CONDITION REPORTS (CR) CR 23030, CR 24015, CR 24018, CR 24019, CR 24020 LPD 30-32
Mar 13, 2025A00272$-43.1KHMR 319 LPD 30 WTA POOL DECREASE
Feb 24, 2025A00271$0ADMIN MOD TO A00268. NO COST MODIFICATION.
Feb 21, 2025A00270$0REQUEST FOR WAIVER (RFW) 0816 TANKLESS ELECTRIC WATER HEATER LPD 30, 31, AND 32
Feb 19, 2025A00269$-361.4KLPD 30 WTA POOL DECREASE
Feb 11, 2025A00268$1.3MHMR 457 ENGINEERING CHANGE REQUEST 2640 REPRICE 2 LPD 31 32 PHYSICAL SECURITY REQUIREMENTS UPDATE
Jan 21, 2025A00267$0LPD 30 RFW 0822 AT NO COST TO THE BASE CONTRACT
Dec 19, 2024A00266$-36.0KHEADQUARTERS MODIFICATION REQUEST (HMR) 459 ENGINEERING CHANGE REQUEST (ECR) 2690 REV- LPD 32 MK 53 DECOY LAUNCHING SYSTEM, INTRODUCTION OF THE MK54 DECOY LAUNCH MESSAGE CONVERTOR
Dec 9, 2024A00264$469.1KHEADQUARTERS MODIFICATION REQUEST (HMR) 455 ENGINEERING CHANGE REQUEST (ECR) 2661 CONFLAGRATION VIDEO MONITORING LPD 31 & 32
Dec 9, 2024A00265$107.7KHEADQUARTERS MODIFICATION REQUEST (HMR) 456 ENGINEERING CHANGE REQUEST (ECR) 2664 LPD 30-32 ADD MEDICAL STOREROOM IN CPS ZONE
Dec 6, 2024A00263$0LPD 32 DETAIL DESIGN AND CONSTRUCTION REWEIGHTS AND BILLING 3RD QUARTER 2024
Nov 25, 2024A00262$500.0KLPD 30 DETAIL DESIGN AND CONSTRUCTION WATERFRONT TASK AUTHORIZATION (WTA) HEADQUARTER MODIFICATION REQUEST (HMR)319 POOL INCREASE
Nov 21, 2024A00260$0VARIOUS CONDITION REPORTS. THIS IS A NO COST CHANGE. FIELD MODIFICATION REQUEST 1921
Nov 21, 2024A00261$231.9KHEADQUARTERS MODIFICATION REQUEST (HMR) 452 ENGINEERING CHANGE REQUEST (ECR) 2674 LPD 31/32 NEW WATER MIST RELIEF VALVE
Nov 4, 2024P00019$4.8MLPD 32 DETAIL DESIGN AND CONSTRUCTION
Oct 23, 2024A00257$0LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319 CLIN 0001
Oct 23, 2024A00258$0LPD 31 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 353 CLIN 0401
Oct 23, 2024A00259$0LPD 32 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 423 CLIN 0501
Oct 8, 2024AZ0011$138.3KUNPRICED CHANGE ORDER (UCO)DEFINITIZATION OF MODIFICATION A00225. ENGINEERING CHANGE REQUEST (ECR)2658 REV 1 LPD 30 STUD MAST STRENGTHENING MODIFICATIONS. CLIN 0001
Sep 26, 2024A00256$0FIELD MODIFICATION REQUEST (FMR) 1915 NO COST MODIFICATION THAT INCORPORATES VARIOUS CONDITION REPORTS.
Sep 24, 2024P00018$0LPD 32 DETAIL DESIGN AND CONSTRUCTION
Sep 16, 2024A00253$-105.1KHEADQUARTERS MODIFICATION REQUEST (HMR) 449 EMERGENT CHANGE REQUEST (ECR) LPD 32 REPLACE AN/URN-32 TACAN/OE-4691 ANTENNA GROUP WITH AN/URN-33 TACAN SYSTEM SCOPE DECREASE
Sep 16, 2024A00254$80.3KENGINEERING CHANGE REQUEST (ECR) 2668 ARMORY DOOR ISSUE POINT LPD 31 & 32 HEADQUARTERS MODIFICATION REQUEST (HMR) 447
Sep 16, 2024A00255$0TO INCORPORATE LPD 30 REQUEST FOR WAIVER (RFW) 0812: FCA 14 MATERIAL INTO THE BASE CONTRACT AT NO COST.
Sep 3, 2024A00252$02024 2ND QUARTER REWEIGHTS AND REBILLINGS LPD 32
Aug 19, 2024A00251$0FIELD MODIFICATION REQUEST (FMR) 1908 CONDITION REPORTS 23031, 24003, 24004, 24005, 24006 FOR LPD 30, 31, AND 32
Aug 16, 2024A00250$800.0KHEADQUARTERS MODIFICATION REQUEST (HMR) 319 LPD 30 WATERFRONT MOD POOL INCREASE
Aug 6, 2024A00249$0LPD 30, 31, AND 32 NO COST CONDITION REPORTS 23004 REV A, 23022, 23025, 23026, 23029
Aug 5, 2024A00248$0LPD 30, 31, AND 32 REQUEST FOR WAIVER 0800 REVISION 1 IMPRESSED CURRENT CATHODIC PROTECTION SYSTEM CLINS 0001, 0401, AND 0501
Jul 25, 2024A00247$0LPD 32 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 423 CLIN 0501
Jul 18, 2024A00246$1.7MLPD 30 COORDINATED SHIPBOARD ALLOWANCE LIST (COSAL) 3RD INCREMENT HEADQUARTERS MODIFICATION REQUEST (HMR) 426 - CLIN 0005
Jul 15, 2024A00245$0REQUEST FOR WAIVER (RFW) 0805 - LPD 30-32 SWITCHBOARD EMI
Jun 17, 2024A00244$269.9KLPD 31 AND 32 ENGINEERING CHANGE REQUEST 2643 REV 1 UPGRADE OF ELECTRONIC CHART DISPLAY AND INFORMATION SYSTEM (ECDIS) EQUIPMENT
May 31, 2024A00243$1.2MLPD 31 ENGINEERING CHANGE REQUEST (ECR) 2465 REVISION 1: USMC SPACE SAVER LOCKER, UNPRICED CHANGE ORDER (UCO) CLIN 0401 - HEADQUARTERS MODIFICATION REQUEST (HMR) 450
May 29, 2024A00241$377.4KHEADQUARTERS MODIFICATION REQUEST (HMR) 434 ENGINEERING CHANGE REQUEST (ECR) 2654 LPD 31 AND 32 AC PLANT ASW HELLAN STRAINER ISOLATION VALVES
May 29, 2024A00242$0MAY 2024 1ST QUARTER REWEIGHTS AND REBILLINGS LPD 31 & 32
May 28, 2024A00240$204.8KHEADQUARTERS MODIFICATION REQUEST (HMR) 443 ENGINEERING CHANGE REQUEST (ECR) 2659 STUB MAST STRENGTHENING MODIFICATIONS FOR LPD 31 AND 32
Apr 29, 2024A00238$0LPD 32 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 423
Apr 29, 2024A00239$0LPD 30 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319
Apr 10, 2024A00237$0LPD 32 DETAIL DESIGN AND CONSTRUCTION FIELD MODIFICATION REQUEST (FMR) 1860: CONDITION REPORT (CR) 22024 REV B AND CR 23010 REV A
Mar 28, 2024P00017$1.0MLPD 32 DETAIL DESIGN AND CONSTRUCTION
Mar 6, 2024A00236$0LPD 30, 31, AND 32 NO COST CONDITION REPORTS 23012 REV C 23013 REV A, 23020, 23024, 23027
Feb 7, 2024P00016$551.4KLPD 32 DETAIL DESIGN AND CONSTRUCTION
Jan 19, 2024A00233$0LPD 31 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 353
Jan 19, 2024A00234$0FIELD MODIFICATION REQUEST (FMR) 1856 LPD 32 CONDITION REPORTS (CR) 21058 REV A, 22015 REV A, 23002, 23021, 23022
Jan 19, 2024A00235$0FIELD MODIFICATION REQUEST (FMR) 1855 LPD 30 & 31 CONDITION REPORTS (CR) 21058 REV C, CR 22024 REV B, CR 23002, CR 23010 REV A, CR 23021
Dec 22, 2023A00230$0DECEMBER 2023 3RD QUARTER REWEIGHTS AND REBILLINGS LPD 31 & 32
Dec 22, 2023A00231$254.4KHEADQUARTERS MODIFICATION REQUEST (HMR) 427 LPD 32 ECR 2635 SHIP SERVICE DIESEL GENERATOR EUI CONVERSION
Dec 22, 2023A00232$2.4MLPD 30 COORDINATED SHIPBOARD ALLOWANCE LIST (COSAL) 2ND INCREMENT HEADQUARTERS MODIFICATION REQUEST (HMR) 418
Oct 23, 2023A00229$0FIELD MODIFICATION REQUEST (FMR) 1863 CONDITION REPORTS (CR) 21019 REV A, 22042 REV A, 22046 REV E, 22057 REV A, 23016 REV A
Oct 10, 2023A00226$0LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319
Oct 10, 2023A00227$0LPD 31 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MODIFICATION (SEPTEMBER 2023) HEADQUARTERS MODIFICATION REQUEST (HMR) 353
Oct 10, 2023A00228$0LPD 32 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MODIFICATION (SEPTEMBER 2023) HEADQUARTERS MODIFICATION REQUEST (HMR) 423
Sep 14, 2023A00225$68.0KLPD 30 DETAIL DESIGN AND CONSTRUCTION UNPRICED CHANGE ORDER (UCO) FOR ENGINEERING CHANGE REQUEST 2658 REVISION 1: STUB MAST STRENGTHENING MODIFICATIONS
Sep 13, 2023A00224$02023 2ND QUARTER REWEIGHTS AND REBILLINGS LPD 30,31, & 32.
Sep 7, 2023A00223$0ADMINISTRATIVE MODIFICATION TO REVISE MODIFICATION A00208 BY REMOVING CONDITION REPORT (CR) 22054 REVISION A FROM BOX 14 ON PAGE ONE OF THE MODIFICATION DOCUMENT AND FROM THE SUBJECT LINE AND SECTION 1A OF THE SF 30 BLOCK 14 CONTINUATION PAGE.
Aug 30, 2023A00222$0LPD 32 DETAIL DESIGN AND CONSTRUCTION FIELD MODIFICATION REQUESTS 1841 & 1842 CONDITION REPORTS
Aug 23, 2023A00221$0REQUEST FOR WAIVER (RFW) 0788 LPD 30-32 BOAT AND CARGO ELECTROMAGNETIC INTERFACE (EMI)
Jul 12, 2023A00218$0LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319
Jul 12, 2023A00219$0LPD 31 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MODIFICATION (JUNE 2023) HEADQUARTERS MODIFICATION REQUEST (HMR) 353
Jul 12, 2023A00220$500.0KHEADQUARTERS MODIFICATION REQUEST (HMR) 423 WTA ESTABLISHING FUNDING POOL LPD 32
Jul 10, 2023A00217$0FIELD MODIFICATION REQUEST (FMR) 1831 LPD 30/31 CONDITION REPORTS (CR): CR 23006 CR 23007 CR 23009 CR 23011 CR 23014
Jun 27, 2023A00216$56.8KFIELD MODIFICATION REQUEST (FMR) 1823 ENGINEERING CHANGE REQUEST (ECR) 2642 LPD 30 AND 31 RELOCATION OF THE DIGITABLE FLUXGATE MAGNETIC COMPASS
Jun 21, 2023A00215$0REQUEST FOR WAIVER (RFW) 0795 REVISION 1 LPD 30-32 UNDERCOUNTER DISHWASHER
Jun 14, 2023A00214$1.1MLPD 31 HEADQUARTERS MODIFICATION REQUEST (HMR) 415 ENGINEERING CHANGE REQUEST (ECR) 2606 REVISION 2 CANES HARDWARE 2.0 AND 4.0
Jun 12, 2023A00211$55.2KLPD 31 ENGINEERING CHANGE REQUEST 2639: INTER-SPACE CABLE ROUTING GFI UPDATE
Jun 12, 2023A00212$43.3KLPD 31 ENGINEERING CHANGE REQUEST 2641 REVISION 1: PROVIDE AN/SPQ-9B VIDEO TO THE PILOT HOUSE
Jun 12, 2023A00213$18.5KLPD 31 ENGINEERING CHANGE REQUEST (ECR) REPLACE TACAN ANTENNA GROUP
May 9, 2023P00015$0ADD AN CLIN FOR INSURANCE CLAIMS
Apr 20, 2023A00209$0LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST (HMR) 319
Apr 20, 2023A00210$0LPD 31 WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MOD (MARCH 2023) HEADQUARTERS MODIFICATION REQUEST (HMR) 353
Apr 6, 2023A00208$0FIELD MODIFICATION REQUEST (FMR) 1812 LPD 30 & 31 CONDITION REPORTS (CR) 22045 REV D, 22054 REV A, 22061, 23001 REV A, 23003
Mar 31, 2023P00014$1.3BLPD 32 DETAIL DESIGN AND CONSTRUCTION
Mar 24, 2023A00207$0INCORPORATES CONDITION REPORTS AT NO COST TO THE CONTRACT
Feb 6, 2023A00206$0LPD 30 & 31 FIELD MODIFICATION REQUEST (FMR) 1694 CONDITION REPORTS
Feb 2, 2023A00205$0REQUEST FOR WAIVER (RFW) 0785 LPD 30 AIR RECEIVER VOLUME
Jan 26, 2023A00204$0LPD 31 HEADQUARTERS MODIFICATION REQUEST (HMR) WATERFRONT AGREEMENT ADMINISTRATIVE QUARTERLY MOD - DECEMBER 2022
Jan 25, 2023A00203$0LPD 30 WATERFRONT CHANGE ADMINISTRATIVE QUARTERLY CONTRACT MODIFICATION FOR HEADQUARTERS MODIFICATION REQUEST 294
Jan 23, 2023A00201$-7.3KFIELD MODIFICATION REQUEST (FMR) 1788 ENGINEERING CHANGE REQUEST (ECR) 2632 INSTALL AN/USQ-T52A T52 GOVERNMENT GIVEBACK
Jan 23, 2023A00202$30.7KLPD 31 ENGINEERING CHANGE PROPOSAL REVISION 1: SHIP SELF DEFENSE SYSTEM (SSDS) MK 2 MOD 2E TI-16TR COMMAND CONTROL GROUP AND MAINTENANCE CONSOLE UPGRADE
Nov 14, 2022A00200$0LPD 30 & 31 FIELD MODIFICATION REQUEST (FMR) 1779 - MOD TO INCORPORATE NO COST CONDITION REPORTS
Nov 4, 2022A00199$0FIELD MODIFICATION REQUEST (FMR) 1776 CONDITION REPORTS (CR) CR 22014 REV A (LPD 30/31) CR 22027 REV B (LPD 30/31) CR 22029 (LPD 30/31) CR 22030 REV. B (LPD 30/31) CR 22035 (LPD 30/31)
Nov 3, 2022AZ0009$297.5KHEADQUARTERS MODIFICATION REQUEST (HMR) 400 ENGINEERING CHANGE REQUEST (ECR) 2621 MPDE STARTING AIR RECEIVER ADDITION. DEFINITIZATION FOR UNPRICED CHANGE ORDER (UCO) MODIFICATION A00170 DATED 11 MAR 2022
Nov 3, 2022AZ0010$220.7KHEADQUARTERS MODIFICATION REQUEST (HMR 407) ENGINEERING CHANGE REQUEST (ECR) 2621 LPD 31 MPDE STARTING AIR RECEIVER ADDITION AND DEFINITIZATION OF UNPRICED CHANGE ORDER (UCO) MODIFICATION A00187 DATED 29 AUG 2022.
Oct 24, 2022A00198$96.2KLPD 31 DD&C UNPRICED CHANGE ORDER DEFINITIZATION TO CONTRACT MODIFICATION A00189 ENGINEERING CHANGE REQUEST 2627 (MAIN PROPULSION DIESEL ENGINE EXHAUST BELLOWS NORDLOCK HARDWARE UPGRADE ACCOMPLISH
Oct 19, 2022A00197$315.3KLPD 30 & 31 DD&C ENGINEERING CHANGE REQUEST 2620 SHIP SELF DEFENSE SYSTEM (SSDS) MK 2 MOD 2E ADDITION OF SYCHRO GENERATORS AND IFF VIDEO INVERTERS
Oct 17, 2022A00196$120.1KENGINEERING CHANGE REQUEST (ECR) 2619 UPDATE RAM MK MOD 3 GUIDED MISSILE WEAPON SYSTEM TO RAM MK 31 MOD 5 GMWS FIELD MODIFICATION REQUEST (FMR) 1744
Oct 12, 2022A00194$0LPD 31 WTA POOL ADMIN QTR MOD
Oct 12, 2022A00195$0LPD 30 WTA POOL QTR MOD
Sep 28, 2022A00192$1.2MLPD 30 & 31 ENGINEERING CHANGE REQUEST 2586 - ENTERPRISE AIR SURVEILLANCE RADAR (EASR) INSTALLATION AND DEFINITIZES CONTRACT MODIFICATION A00144.
Sep 28, 2022A00193$0LPD 30 REQUEST FOR WAIVER (RFW) 0782 PROPELLER SHAFT OVERSIZED BORE TO THE BASE CONTRACT AT NO COST FOR LPD 30.
Sep 26, 2022A00189$85.8KUNPRICED CHANGE ORDER (UCO) ENGINEERING CHANGE REQUEST (ECR) 2627, RELOCATE FWD SPS-72(V)18 NGSSR ANTENNA HEADQUARTERS MODIFICATION REQUEST (HMR) 405
Sep 26, 2022A00190$0LPD 31 ADMIN MOD TO CORRECT A00181
Sep 26, 2022A00191$0LPD 31 ADMIN MOD TO A00182
Sep 7, 2022A00188$0ADMINSTRATIVE MODIFICATION TO CORRECT MODIFICATION A00186
Aug 29, 2022A00187$153.2KUNPRICED CHANGE ORDER (UCO) ENGINEERING CHANGE REQUEST (ECR) 2621,MAIN PROPULSION DIESEL ENGINE (MPDE) AIR RECEIVER HEADQUARTERS MODIFICATION REQUEST (HMR) 407
Aug 26, 2022A00186$-36.4KENGINEERING CHANGE REQUEST (ECR) 2612 LPD 30AF HYDRA ICD UPDATES-DEOB
Aug 26, 2022P00013$0SECTION J UPDATE
Aug 17, 2022A00185$0FIELD MODIFICATION REQUEST (FMR) 1762 CONDITION REPORTS (CRS) 22008 REV A, 22013 REV B, 22028, 22032, 22036 REV A
Aug 8, 2022A00183$0FIELD MODIFICATION REQUEST (FMR) 1750 CONDITION REPORTS 21090 REVISION A, 22005 REVISION A, 22016 REVISION A, 22020 REVISION A, 22026 REVISION A
Aug 8, 2022A00184$02022 2ND QUARTER REWEIGHTS AND REBILLINGS LPD 30 & 31
Jul 11, 2022A00181$0LPD 30 WATERFRONT AGREEMENT (WTA) DEFINITIZATIONS UNDER HMR 319, LPD 30 WTA POOL
Jul 11, 2022A00182$0LPD 31 HEADQUARTERS MODIFICATION REQUEST 353 QUARTER 2 WATERFRONT AGREEMENT POOL (JUNE 2022)
Jun 17, 2022A00180$154.1KLPD 31 DD&C ENGINEERING CHANGE REQUEST 2566 ENGINEERING CONTROL SYSTEM DATA ACQUISITION REDUCTION
Jun 16, 2022P00012$240.0MLPD 32 LONG LEAD TIME MATERIAL & DD&C PRICED OPTION
Jun 15, 2022A00179$0LPD 30 & 31 DD&C - FIELD MODIFICATION REQUEST 1742 CONDITION REPORT (CR) 21073 REV B (LPD 30/31) CR 22009 (LPD 30/31) CR 22011 (LPD 30/31) CR 22012 (LPD 30/31) CR 22022 REV A (LPD 30/31)
Jun 14, 2022P00011$0LPD 31 NOTE O UPDATE
Jun 7, 2022A00177$36.1KLPD 31 DD&C
Jun 7, 2022A00178$0LPD 30 & 31 DD&C Q1 2022 BILLING PRICE AND REWEIGHTS
Jun 3, 2022A00176$0LPD 31 DD&C REQUEST FOR WAIVER 0771 REVISION 1 PIPE HANGER FASTENERS - NO COST
May 23, 2022A00174$0LPD 31 DD&C - CONDITION REPORTS (CR) CR 21068 REV A (LPD 30/31) CR 21093 REV C (LPD 30/31) CR 22004 (LPD 30/31) CR 22006 (LPD 30/31) CR 22010 (LPD 30/31)
May 23, 2022A00175$-69.1KLPDS 30 & 31 DD&C ENGINEERING CHANGE REQUEST 2614 (IDENTIFICATION FRIEND OR FOE (IFF) SOFTWARE AND CONFIGURATION UPDATES GOVERNMENT GIVE-BACK
Apr 1, 2022A00171$0LPD 30 DD&C HEADQUARTER MODIFICATION REQUEST (HMR) 319 QUARTER 1 WATERFRONT AGREEMENT POOL
Apr 1, 2022A00172$0LPD 31 DD&C HEADQUARTERS MODIFICATION REQUEST (HMR) 353 Q1 WATERFRONT AGREEMENT POOL
Apr 1, 2022A00173$0FIELD MODIFICATION REQUEST (FMR) 1716 CONDITION REPORTS: 21062, 21089, 21095, 22002, 22003 - LPD 30/31
Mar 11, 2022A00170$282.9KLPD 30 DD&C MODIFICATION A00170 UNPRICED CHANGE ORDER ECR 2621, HEADQUARTERS MODIFICATION REQUEST (HMR) 400
Feb 25, 2022P00010$0LPD 31 DD&C
Feb 7, 2022A00167$0LPD 31 DD&C - FMR 1690 (CONDITION REPORTS)
Feb 7, 2022A00168$0LPD 30/31 DETAIL DESIGN & CONSTRUCTION REPORTS
Feb 7, 2022A00169$02021 4TH QUARTER REWEIGHTS AND REBILLING LPD 30 & 31
Jan 31, 2022A00166$0LPD 31 DD&C REQUEST FOR WAIVER 0747 REVISION 1 (STERN TUBE SHAFT P4 BORE DIAMETER)
Jan 21, 2022A00165$0LPD 31 DD&C FLUSH CLOVER-LEAF VEHICLE TIE-DOWN CUP WELD DEFICIENCIES REQUEST FOR WAIVER 0742R3
Jan 14, 2022AZ0008$2.7MLPD 31 DD&C ENGINEERING CHANGE REQUEST 2589 CANES RACK CONFIGURATION UNPRICED CHANGE ORDER (UCO) DEFINITIZATION
Jan 13, 2022A00162$0LPD 31 DD&C WATERFRONT CHANGE QUARTERLY MOD
Jan 13, 2022A00163$0LPD 31 DD&C
Jan 13, 2022A00164$0REQUEST FOR WAIVER 0762 LPD 31 FIRE PUMP DISCHARGE PRESSURE PERFORMANCE
Dec 17, 2021A00161$0LPD 31 DD&C
Dec 8, 2021A00160$134.0KLPD 31 DD&C
Dec 8, 2021AZ0007$67.3KLPD 31 DD&C UNPRICED CHANGE ORDER DEFINITIZATION TO CONTRACT MODIFICATION A00149 ENGINEERING CHANGE REQUEST 2551 (FOAL DRAWER)
Dec 7, 2021AZ0006$239.5KLPD 31 DD&C
Nov 19, 2021A00159$0LPD 31 DD&C-CONDITION REPORTS
Nov 10, 2021AZ0005$-965.3KLPD 31 DD&C
Nov 9, 2021A00158$0LPD 31 DD&C
Oct 27, 2021A00157$-2.0MLPD 31 DD&C
Oct 18, 2021A00155$0LPD 31 DD&C
Oct 18, 2021A00156$0LPD 31 DD&C
Oct 13, 2021A00154$-1.4MLPD 31 DD&C
Oct 12, 2021A00153$0LPD 31 DD&C
Oct 5, 2021A00152$0LPD 31 DD&C
Oct 4, 2021A00151$0LPD 31 DD&C
Sep 28, 2021A00149$165.9KLPD 31 DD&C
Sep 28, 2021A00150$522.1KLPD 31 DD&C
Sep 15, 2021A00148$0LPD 31 DD&C
Sep 8, 2021A00147$-62.0KLPD 31 DD&C
Aug 25, 2021A00144$1.0MLPD 31 DD&C
Aug 25, 2021A00145$-1.8MLPD 31 DD&C
Aug 25, 2021A00146$-596.0KLPD 31 DD&C

Estimated positioning window

Mar 1, 2030 – Sep 1, 2030

Recompete signal:
50/100

Why this recompete signal

Contract timing and recorded acquisition signals at the time of calculation.

Stored score: 50/100. Available recorded signals: 45 points.

Contract end 2031-03-01 (1588 days from calculation)
+5 points
21 historical awards in this buyer and category group
+15 points
357 recorded award transactions
+10 points
Latest award action: 2026-06-02
+5 points
Parent award identifier recorded
+0 points
Solicitation identifier recorded
+10 points
Linked official forecast
+0 points
Calculated on
2026-10-25 10:18:04.631876+00:00

The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.

Rule-based research score; it does not measure your chance of winning.

This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.

USAspending award record

. Rule-based research score; positioning dates are estimates.

Recompete score calculated Oct 25, 2026.

Research next steps

  1. Check the linked forecast or SAM for a confirmed solicitation and current timing.
  2. Check the stated set-aside against the solicitation and current certifications.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.