Federal contract award
N0002419C2125
SUBMARINE PLANNING YARD
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | SUP OF SHIPBUILDING GROTON |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | 1905 — Combat Ships and Landing Vessels |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | COST PLUS FIXED FEE |
| Obligations | $1.4B |
| Current contract value | $1.4B |
| Potential contract value / ceiling | $1.4B |
| Start date | Jul 11, 2019 |
| Current end date | Dec 31, 2028 |
| Potential end date | Dec 31, 2028 |
| Latest award activity | May 29, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 200 of 294 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| May 29, 2026 | A00059 | $0 | EXTEND END DATE TO PROCURE DIGITAL VOLTAGE REGULATOR SYSTEM |
| May 21, 2026 | P00225 | $-1.4M | DEOB MOD |
| Apr 6, 2026 | P00224 | $-3.0M | FUNDING DEOB MOD |
| Feb 23, 2026 | P00223 | $0 | CEILING REALIGNMENT |
| Jan 29, 2026 | A00058 | $0 | PERIODIC RELEASE OF CLAIMS |
| Jan 27, 2026 | A00057 | $0 | EXTENSION OF PERIOD OF PERFORMANCE OF THE DIGITAL VOLTAGE REGULATOR SYSTEM. |
| Oct 28, 2025 | A00055 | $0 | EXTEND PERIOD OF PERFORMANCE OF UPGRADE MATERIAL KITS AND COMPONENT SPARES. |
| Oct 28, 2025 | A00056 | $0 | PERIOD OF PERFORMANCE EXTENSION OF SWING SET MATERIAL KITS |
| Sep 30, 2025 | AZ0010 | $1.9M | VIRGINIA CLASS TECHNICAL INSTRUCTION FOR MATERIAL PROCUREMENT IN SUPPORT OF BACKFITTING CIRCUIT D COMPONENTS |
| Sep 25, 2025 | P00222 | $-500.0K | POP EX & FUNDING |
| Sep 23, 2025 | AZ0009 | $5.2M | ADJUDICATING PROCUREMENT OF FOUR SHIPSETS OF INTERNAL COMMUNICATION SYSTEMS. |
| Aug 28, 2025 | P00221 | $-1.6M | FY21 - OPN (FY20) - PHNSY |
| Aug 8, 2025 | AZ0008 | $1.7M | PROCURE FOUR HIGH PRESSURE AIR DEHYDRATORS |
| Aug 4, 2025 | P00220 | $-4.9M | DEOBLIGATION |
| Jul 15, 2025 | A00054 | $0 | RELEASE OF CLAIMS AS OF 30 JUNE 2024 |
| Jul 2, 2025 | P00219 | $309.6K | CEILING XFER & FUNDING MODIFICATION |
| May 27, 2025 | P00218 | $-1.5M | DEOBLIGATION MODIFICATION |
| May 22, 2025 | AZ0007 | $703.0K | PROCUREMENT OF SHIP CONTROL BACKFITS |
| May 15, 2025 | P00217 | $-2.1M | DEOB MODIFICATION |
| May 5, 2025 | P00216 | $609.0K | FUNDING ACTION |
| May 2, 2025 | A00052 | $0 | PERIOD OF PERFORMANCE EXTENSION ORDER 423AJ1 |
| May 2, 2025 | A00053 | $0 | PERIOD OF PERFORMANCE EXTENSION |
| Apr 21, 2025 | A00051 | $0 | PERIOD OF PERFORMANCE EXTENSION |
| Apr 18, 2025 | P00215 | $804.5K | FUNDING |
| Apr 14, 2025 | P00214 | $-3.0M | DEOB |
| Mar 6, 2025 | A00050 | $0 | ADDED ENGINEERING CHANGE INSTRUCTION TO THE TECHNICAL INSTRUCTION |
| Mar 6, 2025 | P00213 | $678.0K | FUNDING ACTION |
| Jan 28, 2025 | P00212 | $-4.3M | DEOB AND AMDIN |
| Dec 13, 2024 | A00049 | $886.5K | MATERIAL PROCUREMENT IN SUPPORT OF SHIP CONTROL BACKFIT UPGRADE |
| Dec 10, 2024 | P00211 | $1.1M | FUNDING MOD |
| Dec 6, 2024 | A00048 | $0 | RELEASE OF CLAIMS |
| Dec 2, 2024 | A00047 | $3.0M | PROCUREMENT OF FOUR VIRGINIA CLASS BLOCK I-III HIGH PRESSURE AIR DEHYDRATORS (HPADS) |
| Nov 26, 2024 | P00210 | $-1.2M | DEOB MOD |
| Sep 30, 2024 | A00046 | $3.0M | PROCURE SHIPSETS OF SHIP ALTERATION MATERIAL |
| Sep 25, 2024 | P00209 | $-87.8K | INC FUNDING & DEOB |
| Sep 19, 2024 | AZ0006 | $7.5M | PROCUREMENT OF ROTATABLE POOL MATERIAL SET OF CHILL WATER AND SHIP SERVICE HYDRAULIC PUMPS |
| Sep 10, 2024 | P00208 | $1.5M | POP EX & INC FUNDING |
| Sep 6, 2024 | A00045 | $0 | PERIOD OF PERFORMANCE EXTENSION |
| Aug 30, 2024 | A00044 | $0 | RELEASE OF CLAIMS 30 JUN 23 |
| Aug 28, 2024 | P00207 | $3.7M | INC FUNDING |
| Aug 20, 2024 | P00206 | $7.3M | INC FUNDING, CEILING TRANSFER, AND POP EXTENSION |
| Aug 6, 2024 | P00205 | $11.5M | INC FUNDING |
| Jul 30, 2024 | P00204 | $33.0M | POP EXT, FUNDING AND CEILING |
| Jul 25, 2024 | A00043 | $16.6M | MATERIAL PROCUREMENT IN SUPPORT OF SHIP ALTERATION |
| Jul 10, 2024 | P00203 | $12.8M | POP EXTENSION + FUNDING |
| Jul 1, 2024 | P00202 | $0 | POP EXTENSION |
| Jun 21, 2024 | P00201 | $8.5M | FUNDING MOD |
| Jun 20, 2024 | A00042 | $0 | HYDRAULIC ACTUATORS FOR VIRGINIA ROTATABLE POOL MATERIAL |
| Jun 14, 2024 | P00200 | $11.4M | FUNDING ACTION |
| Jun 7, 2024 | AZ0005 | $1.3M | HYDRAULIC ACTUATORS FOR VIRGINIA ROTATABLE POOL MATERIAL |
| Jun 5, 2024 | P00199 | $27.5M | FUNDING ACTION |
| May 17, 2024 | P00198 | $11.9M | FUNDING ACTION |
| May 8, 2024 | P00197 | $6.7M | FUNDING ACTION |
| May 6, 2024 | P00196 | $0 | PRICING INCREASE FOR BOW DOME EFFORT |
| Apr 25, 2024 | P00195 | $10.6M | FUNDING ACTION |
| Apr 10, 2024 | P00194 | $7.9M | FUNDING ACTION |
| Apr 2, 2024 | P00193 | $341.9K | FUNDING ACTION AND POP EXT OF CLINS |
| Mar 26, 2024 | P00192 | $16.4M | FUNDING ACTION |
| Mar 21, 2024 | P00191 | $3.2M | FUNDING/CEILING INCREASE |
| Mar 7, 2024 | A00041 | $3.2M | PROVIDE ADDITIONAL FUNDING |
| Feb 12, 2024 | P00190 | $77.2K | FY21 - OPN (FY20) - PHNSY |
| Feb 7, 2024 | A00040 | $0 | RELEASE OF CLAIMS 30 JUN 22 |
| Feb 1, 2024 | P00189 | $7.3M | FUNDING ACTION |
| Jan 26, 2024 | A00039 | $0 | RELEASE OF CLAIMS |
| Jan 26, 2024 | P00188 | $18.0M | FUNDING ACTION |
| Jan 19, 2024 | A00038 | $0 | HYDRAULIC ACTUATORS FOR VIRGINIA ROTATABLE POOL MATERIAL |
| Dec 14, 2023 | P00187 | $12.3M | FUNDING ACTION |
| Dec 12, 2023 | P00186 | $501.1K | FUNDING ACTION ONLY |
| Dec 5, 2023 | P00185 | $6.0M | FUNDING ACTION |
| Dec 4, 2023 | A00037 | $11.5M | ROTATABLE POOL MATERIAL PURCHASE FOR FUTURE VIRGINIA REPAIR AVAILABILITIES |
| Nov 29, 2023 | A00036 | $0 | CHANGE IN DEFINITIZATION SCHEDULE TO ORDER 443CB4 |
| Nov 28, 2023 | A00035 | $730.7K | PROCURE HYDRAULIC PUMP |
| Nov 16, 2023 | P00184 | $17.3M | FUNDING ACTION |
| Nov 6, 2023 | A00034 | $4.8M | HYDRAULIC ACTUATORS FOR VIRGINIA ROTATABLE POOL MATERIAL |
| Oct 31, 2023 | P00183 | $7.1M | FUNDING ACTION |
| Oct 19, 2023 | P00182 | $2.2M | FUNDING ACTION |
| Oct 17, 2023 | P00181 | $898.0K | FUNDING ACTION |
| Oct 6, 2023 | AZ0004 | $679.2K | DEFINITIZATION OF ORDER 453AB1 WATERBORNE ENCLOSURE |
| Sep 29, 2023 | P00180 | $12.3M | FUNDING ACTION |
| Sep 25, 2023 | A00033 | $0 | MATERIAL FOR IN-SERVICE SYSTEM UPGRADE |
| Sep 21, 2023 | P00179 | $10.2M | FUNDING MOD |
| Sep 13, 2023 | A00032 | $0 | 443CB4 DEFINITIZATION SCHEDULE REVISION |
| Sep 1, 2023 | P00178 | $10.6M | FUNDING MOD AND POP EXTENSION |
| Aug 18, 2023 | P00177 | $8.2M | FUNDING MOD AND POP EXT |
| Aug 14, 2023 | A00031 | $7.8M | PROCUREMENT OF CHILL WATER PUMPS AND MOTORS |
| Aug 4, 2023 | A00030 | $4.1M | PROCUREMENT OF DIGITAL VOLTAGE REGULATOR SYSTEMS |
| Jul 31, 2023 | A00029 | $982.5K | MATERIAL PROCUREMENT OF THE WATERBORNE DECK ENCLOSURE |
| Jul 28, 2023 | P00176 | $19.2M | FUNDING MOD |
| Jul 24, 2023 | P00175 | $5.7M | FUNDING MOD |
| Jul 11, 2023 | P00174 | $6.7M | FUNDING MOD |
| Jul 6, 2023 | A00028 | $0 | RELEASE OF CLAIMS 31 DEC 2021 |
| Jun 30, 2023 | P00173 | $22.2M | FUNDING MOD |
| Jun 13, 2023 | P00172 | $6.6M | FUNDING MOD |
| May 31, 2023 | P00171 | $-14.1M | FUNDING MOD |
| May 25, 2023 | A00027 | $636.1K | BOW DOME PROCUREMENT |
| May 25, 2023 | AZ0003 | $1.3M | INTERIOR COMMUNICATION SYSTEM BACKFIT KITS |
| May 16, 2023 | P00170 | $10.4M | FY23 |
| May 3, 2023 | A00026 | $766.5K | HYDRAULIC PUMP ROTOR MODIFICATION |
| Apr 25, 2023 | P00169 | $4.3M | FUNDING MOD |
| Apr 6, 2023 | P00168 | $7.6M | FUNDING ONLY ACTION |
| Mar 29, 2023 | P00167 | $29.5M | FUNDING MOD |
| Mar 16, 2023 | P00166 | $21.3M | FUNDING MOD |
| Mar 2, 2023 | P00165 | $8.4M | FUNDING MOD |
| Feb 21, 2023 | P00164 | $-7.6M | FUNDING ACTION |
| Feb 9, 2023 | P00163 | $9.8M | FUNDING ACTION |
| Feb 6, 2023 | P00162 | $6.9M | FUNDING MOD |
| Jan 20, 2023 | P00161 | $6.0M | FUNDING MOD |
| Jan 9, 2023 | P00160 | $4.0M | FUNDING MOD |
| Dec 22, 2022 | P00159 | $1.3M | FUNDING MOD |
| Dec 15, 2022 | P00158 | $1.6M | FY23 |
| Dec 12, 2022 | P00157 | $5.3M | FUNDING MOD |
| Dec 9, 2022 | A00025 | $778.0K | TECHNICAL INSTRUCTION FOR HANDLING MATERIAL PROCUREMENT |
| Dec 6, 2022 | P00156 | $8.1M | FUNDING MOD |
| Nov 17, 2022 | P00155 | $3.6M | FUNDING MOD |
| Nov 8, 2022 | P00154 | $4.9M | FUNDING MOD |
| Oct 26, 2022 | P00153 | $3.4M | FUNDING MOD |
| Oct 19, 2022 | P00152 | $8.4M | FUNDING MOD |
| Sep 28, 2022 | P00151 | $31.2M | FUNDING MOD |
| Sep 26, 2022 | A00024 | $0 | REPLACING FY21 FUNDS FOR FY20 EXPIRING FUNDS |
| Sep 26, 2022 | P00150 | $1.9M | FY23 FUNDING ACTION |
| Sep 16, 2022 | P00149 | $2.9M | FUNDING ACTION MOD |
| Sep 13, 2022 | A00023 | $0 | COST ACCOUNTING STANDARDS CORRECTION |
| Sep 8, 2022 | P00148 | $2.4M | FUNDING ACTION MOD |
| Aug 26, 2022 | A00022 | $1.5M | FUNDING INCREASE OF LIMITATION OF LIABILITY |
| Aug 26, 2022 | P00147 | $5.9M | FUNDING MOD ACTION |
| Aug 18, 2022 | A00021 | $0 | TRANSFER OF GP |
| Aug 16, 2022 | P00146 | $9.0M | FUNDING MOD |
| Aug 10, 2022 | P00144 | $5.5M | EXERCISING AN OPTION |
| Aug 10, 2022 | P00145 | $7.0M | FUNDING MOD |
| Aug 1, 2022 | P00143 | $7.4M | FUNDING MOD |
| Jul 13, 2022 | P00142 | $5.7M | FUNDING MOD |
| Jul 6, 2022 | P00141 | $7.5M | FUNDING MOD |
| Jun 28, 2022 | P00140 | $14.9M | FUNDING ACTION MOD |
| Jun 24, 2022 | P00139 | $12.6M | FUNDING MOD |
| Jun 10, 2022 | P00138 | $4.2M | FUNDING MOD |
| Jun 7, 2022 | P00137 | $900.0K | FUNDING MOD |
| May 31, 2022 | P00136 | $6.2M | FUNDING MOD |
| May 24, 2022 | P00135 | $3.5M | FUNDING MOD |
| May 17, 2022 | P00134 | $2.1M | FUNDING MOD |
| May 9, 2022 | P00133 | $3.7M | FUNDING MOD |
| May 4, 2022 | P00132 | $3.7M | FY22 |
| Apr 21, 2022 | P00131 | $17.2M | FUNDING MOD |
| Apr 18, 2022 | A00020 | $0 | PERIODIC RELEASE OF CLAIMS 30JUN2020 |
| Apr 7, 2022 | A00019 | $0 | PERIODIC RELEASE FOR 31 DEC 2020 |
| Apr 6, 2022 | P00130 | $1.8M | FUNDING MOD |
| Apr 1, 2022 | P00129 | $2.0M | FUNDING MOD |
| Mar 25, 2022 | P00128 | $9.1M | FUNDING MODIFICATION |
| Mar 18, 2022 | P00127 | $1.9M | FUNDING MOD |
| Mar 14, 2022 | P00126 | $2.7M | FUNDING MOD |
| Mar 4, 2022 | P00125 | $1.2M | FUNDING MOD |
| Feb 28, 2022 | P00124 | $4.0M | FUNDING MOD |
| Feb 18, 2022 | P00123 | $6.3M | FUNDING MOD |
| Feb 11, 2022 | P00122 | $2.8M | FUNDING MODIFICATION |
| Feb 8, 2022 | P00121 | $147.0K | FUNDING MODIFICATION |
| Feb 7, 2022 | A00018 | $1.5M | DELIVERY OF SHIPSET #3 DIGITAL VOLTAGE REGULATOR SYSTEM (DVRS) |
| Jan 31, 2022 | P00120 | $5.2M | FUNDING MODIFICATION |
| Jan 24, 2022 | P00119 | $2.2M | INCREMENTAL FUNDING |
| Jan 18, 2022 | P00118 | $5.7M | FUNDING MODIFICATION |
| Jan 6, 2022 | P00117 | $677.2K | FY22 |
| Dec 20, 2021 | P00116 | $5.7M | PMS392 SUBMARINES |
| Dec 14, 2021 | P00115 | $3.6M | SUBMARINES PMS392 |
| Dec 10, 2021 | A00017 | $3.0M | LONG LEAD MATERIAL |
| Dec 3, 2021 | P00114 | $4.7M | SUBMARINES PMS392 |
| Nov 19, 2021 | P00113 | $14.3M | SUBMARINES PMS392 |
| Nov 17, 2021 | P00112 | $4.8M | SUBMARINES PMS392 |
| Nov 9, 2021 | P00111 | $2.2M | SUBMARINES |
| Nov 5, 2021 | A00016 | $0 | GAINING MOD TO RECEIVE GFP FROM N00024-99-C-2900 |
| Oct 28, 2021 | P00110 | $6.0M | SUBMARINES PMS392 |
| Oct 25, 2021 | P00109 | $540.0K | SUBMARINES PMS392 |
| Oct 18, 2021 | P00108 | $3.9M | SUBMARINES PMS392 |
| Sep 29, 2021 | P00107 | $5.2M | SUBMARINES PMS392 |
| Sep 23, 2021 | P00106 | $5.2M | SUBMARINES PMS392 |
| Sep 21, 2021 | A00015 | $-187.2K | DEFINITIZE ORDER 423AJ3 REV B |
| Sep 21, 2021 | AZ0002 | $846.3K | DEFINITIZE ORDER 423AJ2 |
| Sep 15, 2021 | P00105 | $1.3M | SUBMARINES PMS392 |
| Sep 9, 2021 | A00013 | $1.3M | DEFINITIZE ORDER 423AJ1 |
| Sep 4, 2021 | P00104 | $426.9K | SUBMARINES PMS392 |
| Aug 30, 2021 | P00103 | $1.5M | SUBMARINES PMS392 |
| Aug 24, 2021 | P00102 | $1.7M | SUBMARINES PMS392 |
| Aug 16, 2021 | P00101 | $5.8M | SUBMARINES PMS392 |
| Aug 12, 2021 | P00100 | $7.7M | SUBMARINES PMS392 |
| Aug 2, 2021 | P00099 | $3.1M | PMS392 SUBMARINES |
| Jul 26, 2021 | P00098 | $1.1M | SUBMARINES PMS392 |
| Jul 22, 2021 | P00097 | $4.2M | SUBMARINES PMS392 |
| Jul 21, 2021 | A00012 | $91.7K | COST INCREASE ORDER 423AJ3 REV A |
| Jul 19, 2021 | P00096 | $3.3M | SUBMARINES PMS392 |
| Jul 7, 2021 | P00095 | $12.4M | PMS392 SUBMARINES 2410A |
| Jul 6, 2021 | A00011 | $0 | THE PURPOSE OF THIS MODIFICATION IS TO IMPLEMENT NAVSEA 0400-AD-URM-010 (TAG OUT USERS MANUAL), REV 7, ACN 1/A AND ACN 2/A. |
| Jun 30, 2021 | P00094 | $8.3M | SUBMARINES PMS392 |
| Jun 17, 2021 | P00093 | $-32.0K | PMS392 SUBMARINES |
| Jun 10, 2021 | P00092 | $1.1M | SUBMARINES PMS392 |
| May 27, 2021 | P00091 | $2.3M | SUBMARINES PMS392 |
| May 24, 2021 | P00090 | $1.7M | PMS392 SUBMARINES |
| May 18, 2021 | P00089 | $2.4M | PMS392 SUBMARINES |
| May 7, 2021 | P00088 | $690.6K | PMS392 SUBMARINES |
| May 3, 2021 | A00010 | $0 | GAINING MOD TO RECEIVE GFP FROM N00024-04-C-2100 |
| Apr 29, 2021 | P00087 | $4.7M | PMS392 SUBMARINES |
| Apr 28, 2021 | A00009 | $529.3K | ORDER 423AB1 ADJUDICATING MOD |
| Apr 22, 2021 | P00086 | $4.1M | PMS392 SUBMARINES |
| Apr 15, 2021 | P00085 | $33.4K | FY21 - PMS392 |
Estimated positioning window
Dec 31, 2027 – Jun 30, 2028
60/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 60/100. Available recorded signals: 55 points.
- Contract end 2028-12-31 (791 days from calculation)
- +15 points
- 11 historical awards in this buyer and category group
- +15 points
- 294 recorded award transactions
- +10 points
- Latest award action: 2026-05-29
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.