Federal contract award
N0002419C6402
PRODUCTION OF FMS BOATS U1, U2, AND U3
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NAVSEA HQ |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | 1990 — Miscellaneous Vessels |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIRM FIXED PRICE |
| Obligations | $183.9M |
| Current contract value | $184.1M |
| Potential contract value / ceiling | $218.5M |
| Start date | Sep 27, 2019 |
| Current end date | May 25, 2029 |
| Potential end date | Sep 25, 2029 |
| Latest award activity | Jun 3, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 109 of 109 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 3, 2026 | P00058 | $0 | ADMIN |
| May 26, 2026 | P00057 | $9.1M | FUNDING |
| Feb 25, 2026 | P00055 | $2.6M | PIO 10 AND OTHER FUNDING |
| Feb 25, 2026 | P00055 | $750.7K | PIO 10 AND OTHER FUNDING |
| Feb 25, 2026 | P00056 | $0 | PIO 10 AND OTHER FUNDING |
| Feb 25, 2026 | P00056 | $1.7M | PIO 10 AND OTHER FUNDING |
| Dec 17, 2025 | P00054 | $2.8M | CDR-B ECP INCORPORATION |
| Dec 17, 2025 | P00054 | $0 | CDR-B ECP INCORPORATION |
| Dec 1, 2025 | P00053 | $0 | DELIVERY EXTENSIONS |
| Dec 1, 2025 | P00053 | $0 | DELIVERY EXTENSIONS |
| Sep 26, 2025 | P00052 | $0 | AWARD OF PIO SPARES NO. 9 |
| Sep 26, 2025 | P00052 | $42.9M | AWARD OF PIO SPARES NO. 9 |
| Sep 23, 2025 | P00051 | $9.8M | 4 YEAR EXTENSION |
| Sep 23, 2025 | P00051 | $-9.8M | SWCS 4 YEAR EXTENSION |
| Aug 12, 2025 | P00050 | $0 | FUND CLINS 0013, 0014, AND 0016 |
| Aug 12, 2025 | P00050 | $-37.9M | FUNDING OF CLINS 0013, 0014, AND 0016 (NON-FMS) |
| May 29, 2025 | P00049 | $942.7K | ESS |
| Mar 3, 2025 | P00048 | $1.1M | PRODUCTION OF FMS U1, U2, AND U3 |
| Feb 21, 2025 | A00002 | $-701.6K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Dec 5, 2024 | P00047 | $4.0M | PRODUCTION OF FMS U1, U2, AND U3 |
| Sep 23, 2024 | P00046 | $1.2M | PRODUCTION OF FMS U1, U2, AND U3 |
| Jul 24, 2024 | A00001 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Jun 28, 2024 | P00044 | $2.3M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Jun 28, 2024 | P00045 | $51.4M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Apr 16, 2024 | P00043 | $1.3M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Feb 29, 2024 | P00042 | $0 | ENGINEERING SERVICES (FMS) |
| Feb 29, 2024 | P00042 | $592.2K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Jan 11, 2024 | P00041 | $3.1M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Nov 30, 2023 | P00040 | $400.0K | MK 1110 EARLY ACCEPTANCE. |
| Nov 17, 2023 | P00039 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Sep 19, 2023 | P00038 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Sep 19, 2023 | P00038 | $920.0K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Jul 31, 2023 | P00037 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Jul 31, 2023 | P00037 | $2.1M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| May 8, 2023 | P00036 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| May 8, 2023 | P00036 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Apr 24, 2023 | P00035 | $5.2M | PRODUCTION OF FMS U1, U2, AND U3 |
| Apr 24, 2023 | P00035 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Mar 15, 2023 | P00034 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Mar 15, 2023 | P00034 | $9.5M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Nov 30, 2022 | P00033 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Nov 30, 2022 | P00033 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Nov 29, 2022 | P00032 | $-3.0K | PRODUCTION OF FMS U1, U2, AND U3 |
| Nov 29, 2022 | P00032 | $2.1M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Nov 28, 2022 | P00031 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Nov 28, 2022 | P00031 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Aug 12, 2022 | P00030 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Aug 12, 2022 | P00030 | $-554.0K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Aug 11, 2022 | P00029 | $1.4M | PRODUCTION OF FMS U1, U2, AND U3 |
| Aug 11, 2022 | P00029 | $1.4M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Jun 27, 2022 | P00028 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Jun 27, 2022 | P00028 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Jun 3, 2022 | P00027 | $300.0K | PRODUCTION OF FMS U1, U2, AND U3 |
| Jun 3, 2022 | P00027 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Apr 28, 2022 | P00026 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Apr 28, 2022 | P00026 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Apr 22, 2022 | P00025 | $583.5K | PRODUCTION OF FMS U1, U2, AND U3 |
| Apr 22, 2022 | P00025 | $590.1K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Apr 8, 2022 | P00024 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Apr 8, 2022 | P00024 | $2.8M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Feb 10, 2022 | P00023 | $719.7K | PRODUCTION OF FMS U1, U2, AND U3 |
| Feb 10, 2022 | P00023 | $1.4M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Dec 22, 2021 | P00022 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Dec 22, 2021 | P00022 | $140.0K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Nov 9, 2021 | P00021 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Nov 9, 2021 | P00021 | $713.6K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Oct 22, 2021 | P00020 | $39.2M | PRODUCTION OF FMS U1, U2, AND U3 |
| Oct 22, 2021 | P00020 | $-38.3M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Oct 6, 2021 | P00019 | $-39.8M | PRODUCTION OF FMS U1, U2, AND U3 |
| Oct 6, 2021 | P00019 | $39.8M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Sep 14, 2021 | P00018 | $20.0K | PRODUCTION OF FMS U1, U2, AND U3 |
| Sep 14, 2021 | P00018 | $160.2K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Sep 8, 2021 | P00017 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| Sep 8, 2021 | P00017 | $3.8M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Jun 7, 2021 | P00016 | $1.8M | PRODUCTION OF FMS U1, U2, AND U3 |
| Jun 7, 2021 | P00016 | $1.5M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| May 27, 2021 | P00015 | $0 | PRODUCTION OF FMS U1, U2, AND U3 |
| May 27, 2021 | P00015 | $1.8M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Apr 12, 2021 | P00014 | $606.1K | PRODUCTION OF FMS U1, U2, AND U3 |
| Apr 12, 2021 | P00014 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Mar 25, 2021 | P00013 | $292.3K | PRODUCTION OF FMS U1, U2, AND U3 |
| Mar 25, 2021 | P00013 | $565.6K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Jan 14, 2021 | P00012 | $39.2M | PRODUCTION OF FMS U1, U2, AND U3 |
| Jan 14, 2021 | P00012 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Dec 18, 2020 | P00011 | $0 | ENGINEERING SERVICES (FMS) |
| Dec 18, 2020 | P00011 | $5.5M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Nov 27, 2020 | P00010 | $0 | ENGINEERING SERVICES (FMS) |
| Nov 27, 2020 | P00010 | $2.7M | FUNDING MOD |
| Sep 29, 2020 | P00009 | $37.7K | FUNDING MOD |
| Sep 29, 2020 | P00009 | $92.0K | FUNDING MOD |
| Sep 15, 2020 | P00008 | $0 | ENGINEERING SERVICES (FMS) |
| Sep 15, 2020 | P00008 | $1.6M | PIO SPARE PARTS |
| Sep 3, 2020 | P00007 | $0 | ENGINEERING SERVICES (FMS) |
| Sep 3, 2020 | P00007 | $2.3M | FUNDING MOD |
| Jul 28, 2020 | P00006 | $0 | ENGINEERING SERVICES (FMS) |
| Jul 28, 2020 | P00006 | $1.1M | FUNDING MOD |
| Apr 14, 2020 | P00005 | $1.1M | ENGINEERING SERVICES (FMS) |
| Apr 14, 2020 | P00005 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Apr 2, 2020 | P00004 | $0 | ENGINEERING SERVICES (FMS) |
| Apr 2, 2020 | P00004 | $499.9K | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Mar 27, 2020 | ARZ999 | $0 | COVID-19 DIB. PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Feb 26, 2020 | P00003 | $0 | FUNDING ACTION |
| Feb 26, 2020 | P00003 | $499.9K | FUNDING ACTION |
| Dec 20, 2019 | P00002 | $0 | EXERCISE OPTION YEAR 1 |
| Dec 20, 2019 | P00002 | $27.2M | EXERCISE OPTION FOR PRODUCTION OF MK1109 AND MK1110. |
| Oct 15, 2019 | P00001 | $483.9K | ENGINEERING SERVICES (FMS) |
| Oct 15, 2019 | P00001 | $0 | PRODUCTION OF MK1106, MK1107, AND MK1108 |
| Sep 27, 2019 | 0 | $0 | PRODUCTION OF FMS BOATS U1, U2, AND U3 |
| Sep 27, 2019 | 0 | $41.4M | PRODUCTION OF MK1106, MK1107, AND MK1108 |
Estimated positioning window
Sep 25, 2028 – Mar 25, 2029
45/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 45/100. Available recorded signals: 40 points.
- Contract end 2029-09-25 (1059 days from calculation)
- +15 points
- 1 historical awards in this buyer and category group
- +0 points
- 109 recorded award transactions
- +10 points
- Latest award action: 2026-06-03
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Verify whether remaining options may extend performance beyond the current end date.
- Check the stated set-aside against the solicitation and current certifications.