| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | NAVSEA HQ |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | 1905 — Combat Ships and Landing Vessels |
| Parent award / vehicle | Not reported |
| Set-aside | NO SET ASIDE USED. |
| Pricing type | FIXED PRICE INCENTIVE |
| Obligations | $3.0B |
| Current contract value | $3.9B |
| Potential contract value / ceiling | $6.2B |
| Start date | Apr 30, 2020 |
| Current end date | May 31, 2034 |
| Potential end date | May 31, 2034 |
| Latest award activity | Apr 16, 2026 |
| Source loaded | Sep 19, 2026 |
Funding and modification history
Showing the latest 79 of 79 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Apr 16, 2026 | P00052 | $65.1M | DETAIL DESIGN & CONSTRUCTION |
| Apr 2, 2026 | P00051 | $-70.0M | DEOBLIGATIONS |
| Feb 17, 2026 | P00050 | $309.6M | PARTIAL TERMINATION FRAMEWORK EXECUTION |
| Dec 5, 2025 | P00049 | $-1.2B | DEOBLIGATIONS OF CLINS 0300-0600 (FFG 63-FFG67) TERMINATION FOR CONVENIENCE |
| Oct 20, 2025 | A00024 | $-1.9K | RFV 0133 & RFV 0053 |
| Sep 17, 2025 | A00023 | $0 | 1Q2025 FFG RBP |
| Sep 9, 2025 | A00022 | $410.2K | CONVERT THE EXISTING WATER MIST AND AFFF FIRE SUPPRESSION SYSTEM TO CARBON DIOXIDE (CO2). |
| Aug 8, 2025 | P00048 | $18.3M | DETAIL DESIGN & CONSTRUCTION |
| Jul 28, 2025 | P00047 | $39.8M | DETAIL DESIGN & CONSTRUCTION |
| Jun 9, 2025 | P00046 | $18.4M | DETAIL DESIGN & CONSTRUCTION |
| May 12, 2025 | A00021 | $0 | DETAIL DESIGN & CONSTRUCTION |
| May 1, 2025 | P00045 | $13.1M | DETAIL DESIGN & CONSTRUCTION |
| Apr 28, 2025 | A00020 | $104.5K | FFG 4Q2024 RBP AND DANIEL DOBBINS CAC/DEERS OFFICE |
| Apr 14, 2025 | A00019 | $0 | HMR00011 - ECP-0023 |
| Mar 14, 2025 | P00044 | $129.7K | DETAIL DESIGN & CONSTRUCTION |
| Mar 4, 2025 | A00018 | $0 | FFG HMR00008 & HMR00009 |
| Feb 21, 2025 | A00017 | $4.1M | FFG62AF ECP-0022 MCCS SOFTWARE RE-ARCHITECTURE |
| Jan 31, 2025 | A00016 | $294.2K | L3 HARRIS PROPULSION LBES DELIVERY DATE EXTENSION |
| Jan 27, 2025 | P00043 | $11.2M | DETAIL DESIGN & CONSTRUCTION |
| Dec 20, 2024 | P00042 | $472.3K | DETAIL DESIGN & CONSTRUCTION |
| Dec 19, 2024 | A00015 | $0 | CY2023 EPA |
| Nov 27, 2024 | P00041 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Nov 14, 2024 | A00014 | $691.6K | DETAIL DESIGN & CONSTRUCTION |
| Oct 31, 2024 | P00040 | $5.6M | DETAIL DESIGN & CONSTRUCTION |
| Oct 16, 2024 | A00013 | $453.7K | DETAIL DESIGN & CONSTRUCTION |
| Sep 4, 2024 | P00039 | $37.9M | DETAIL DESIGN & CONSTRUCTION |
| Aug 28, 2024 | A00012 | $0 | DETAIL DESIGN & CONSTRUCTION- RBP & EPA |
| Aug 21, 2024 | P00038 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Jul 29, 2024 | A00011 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Jul 19, 2024 | P00037 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Jul 3, 2024 | P00036 | $6.6M | DETAIL DESIGN & CONSTRUCTION |
| Jun 6, 2024 | P00035 | $7.0M | DETAIL DESIGN & CONSTRUCTION |
| May 23, 2024 | P00034 | $1.0B | DETAIL DESIGN & CONSTRUCTION |
| Apr 30, 2024 | P00033 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Apr 10, 2024 | P00032 | $3.0M | DETAIL DESIGN & CONSTRUCTION |
| Apr 9, 2024 | A00010 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Mar 25, 2024 | A00009 | $401.2K | DETAIL DESIGN & CONSTRUCTION |
| Mar 21, 2024 | P00031 | $832.9K | DETAIL DESIGN & CONSTRUCTION |
| Feb 23, 2024 | P00030 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Jan 25, 2024 | P00029 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Dec 19, 2023 | P00028 | $466.2K | DETAIL DESIGN & CONSTRUCTION |
| Dec 6, 2023 | A00008 | $-1.8M | DETAIL DESIGN & CONSTRUCTION |
| Nov 29, 2023 | P00027 | $300.0K | DETAIL DESIGN & CONSTRUCTION |
| Nov 8, 2023 | P00026 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Oct 18, 2023 | P00025 | $10.0M | DETAIL DESIGN & CONSTRUCTION |
| Oct 12, 2023 | A00007 | $8.6M | DETAIL DESIGN & CONSTRUCTION |
| Sep 29, 2023 | A00006 | $379.5K | DETAIL DESIGN & CONSTRUCTION |
| Aug 31, 2023 | P00024 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Aug 15, 2023 | P00023 | $48.5M | DETAIL DESIGN & CONSTRUCTION |
| Aug 8, 2023 | A00005 | $16.7M | DETAIL DESIGN & CONSTRUCTION |
| Jul 28, 2023 | PZ0001 | $18.3M | DETAIL DESIGN & CONSTRUCTION |
| May 24, 2023 | P00022 | $0 | DETAIL DESIGN & CONSTRUCTION |
| May 18, 2023 | P00021 | $526.3M | DETAIL DESIGN & CONSTRUCTION |
| May 4, 2023 | A00004 | $0 | DETAIL DESIGN & CONSTRUCTION |
| May 4, 2023 | AZ0001 | $1.4M | DETAIL DESIGN & CONSTRUCTION |
| Apr 18, 2023 | P00020 | $0 | DETAIL DESIGN & CONSTRUCTION |
| Feb 17, 2023 | A00003 | $0 | DETAIL DESIGN & CONSTRUCTION - ECONOMIC PRICE ADJUSTMENT |
| Nov 4, 2022 | P00019 | $350.0K | INCENTIVE PAYMENT AND SECTION J UPDATES |
| Sep 22, 2022 | A00002 | $76.7M | DETAIL DESIGN & CONSTRUCTION |
| Sep 1, 2022 | P00018 | $3.2M | OMN FUNDING FOR CBM |
| Aug 15, 2022 | P00017 | $5.5M | FFG-62 P00017: POP EXTENSION AS WELL AS OPTION EXERCISE. |
| Jun 16, 2022 | P00016 | $536.9M | OPTION EXERCISE FOR DD&C FOR FUTURE USS CHESAPEAKE (FFG 64) AND IDE |
| Apr 4, 2022 | P00015 | $0 | IMPLEMENT DESIGN AND SYSTEM CHANGES FOR FFG SHIPS. |
| Mar 9, 2022 | P00014 | $0 | UPDATE TO J2 AND CDRL |
| Feb 25, 2022 | A00001 | $78.8K | DETAIL DESIGN & CONSTRUCTION |
| Feb 18, 2022 | P00013 | $0 | UPDATE SECTION G AND SECTION I CLAUSES. |
| Feb 10, 2022 | P00012 | $9.0M | GUIDED MISSILE FRIGATE BRIDGE TRAINER EQUIPMENT |
| Nov 10, 2021 | P00011 | $0 | DETAIL DESIGN & CONSTRUCTION OF FFG 62 |
| Sep 30, 2021 | P00010 | $500.0K | ENGINEERING AND CLASS SERVICES TO SUPPORT FFG 62 CONSTRUCTION |
| Aug 24, 2021 | P00009 | $0 | DETAIL DESIGN AND CONSTRUCTION OF FFG-62 CLASS GUIDED MISSILE FRIGATE |
| Aug 16, 2021 | P00008 | $5.0M | FISCAL 2021 ENGINEERING AND CLASS SERVICES REQUIREMENTS TO SUPPORT DETAIL DESIGN AND CONSTRUCTION OF CONSTELLATION-CLASS GUIDED-MISSILE FRIGATE |
| Aug 5, 2021 | P00007 | $0 | IMPLEMENT DESIGN UPDATES FOR FFG SHIPS |
| Jun 22, 2021 | P00006 | $0 | FUNDING CORRECTION |
| May 20, 2021 | P00005 | $553.9M | OPTION EXERCISE FOR DETAIL DESIGN & CONSTRUCTION OF FUTURE USS CONGRESS (FFG 63) AND INTEGRATED DIGITAL ENVIRONMENT SUPPORT |
| Jan 21, 2021 | P00004 | $0 | ADMINISTRATIVE UPDATES |
| Dec 14, 2020 | P00003 | $0 | CHANGE ORDER FOR FFG 62 REQUIREMENTS |
| Sep 2, 2020 | P00002 | $0 | ADMINISTRATIVE UPDATES |
| Aug 25, 2020 | P00001 | $0 | ADMINISTRATIVE UPDATES |
| Apr 30, 2020 | 0 | $795.1M | DETAIL DESIGN AND CONSTRUCTION OF FFG(X) GUIDED MISSILE FRIGATE |
Estimated positioning window
May 31, 2033 – Nov 30, 2033
50/100
Why this recompete signal
Contract timing and recorded acquisition signals at the time of calculation.
Stored score: 50/100. Available recorded signals: 45 points.
- Contract end 2034-05-31 (2768 days from calculation)
- +5 points
- 126 historical awards in this buyer and category group
- +15 points
- 79 recorded award transactions
- +10 points
- Latest award action: 2026-04-16
- +5 points
- Parent award identifier recorded
- +0 points
- Solicitation identifier recorded
- +10 points
- Linked official forecast
- +0 points
- Calculated on
- 2026-11-01 10:17:53.997580+00:00
The historical group combines buyer, NAICS, and PSC. Multiple awards in this group do not by themselves establish repeated competitions.
Rule-based research score; it does not measure your chance of winning.
This older calculation does not retain a complete reproducible breakdown. Missing or changed inputs are not assigned invented points: Original award-value bonus input.
Recompete score calculated Nov 1, 2026.
Research next steps
- Check the linked forecast or SAM for a confirmed solicitation and current timing.
- Check the stated set-aside against the solicitation and current certifications.
- Review the award scope and buyer evidence before making a bid/no-bid decision.