Federal contract award
N4523A25F6038
ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN.
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | PUGET SOUND NAVAL SHIPYARD IMF |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | J999 — Non-nuclear Ship Repair (West) Ship repair (including overhauls and conversions) performed on. non-nuclear propelled and nonpropelled ships west of the 108th meridian |
| Parent award / vehicle | N0002425D4110 |
| Set-aside | Not reported |
| Pricing type | COST PLUS INCENTIVE FEE |
| Obligations | $16.5M |
| Current contract value | $16.5M |
| Potential contract value / ceiling | $16.5M |
| Start date | May 6, 2025 |
| Current end date | Aug 1, 2026 |
| Potential end date | Aug 1, 2026 |
| Latest award activity | Jun 11, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 9 of 9 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 11, 2026 | P00008 | $0 | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
| May 22, 2026 | P00007 | $885.0K | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
| Apr 1, 2026 | P00006 | $3.7M | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
| Mar 6, 2026 | P00005 | $459.7K | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
| Feb 24, 2026 | P00004 | $6.3M | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
| Sep 10, 2025 | P00003 | $59.8K | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
| Aug 5, 2025 | P00002 | $75.0K | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
| May 20, 2025 | P00001 | $33.4K | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
| May 6, 2025 | 0 | $3.7M | ACCOMPLISH THE EXECUTION PLANNING FOR THE REPAIR AND ALTERATION REQUIREMENTS FOR CVN DRYDOCKING PLANNED INCREMENTAL AVAILABILITY (DPIA) IN SUPPORT OF THE CVN 72 ABRAHAM LINCOLN. |
Research next steps
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.