Federal contract award
N5523624F9918
CODE 460C USS THEODORE ROOSEVELT (CVN-71) FY25 PIA HISM-CVN71-24-CN01
Award details
Obligations, current value and potential value describe different measures; they are never added together.
| Field | Reported value |
|---|---|
| Agency | Department of Defense |
| Office | SOUTHWEST REGIONAL MAINT CENTER |
| NAICS | 336611 — Ship Building and Repairing |
| PSC | J999 — Non-nuclear Ship Repair (West) Ship repair (including overhauls and conversions) performed on. non-nuclear propelled and nonpropelled ships west of the 108th meridian |
| Parent award / vehicle | N0002423D4107 |
| Set-aside | Not reported |
| Pricing type | COST PLUS INCENTIVE FEE |
| Obligations | $61.7M |
| Current contract value | $61.7M |
| Potential contract value / ceiling | $61.7M |
| Start date | Sep 3, 2024 |
| Current end date | Aug 7, 2025 |
| Potential end date | Oct 7, 2025 |
| Latest award activity | Jun 10, 2026 |
| Source loaded | Sep 26, 2026 |
Funding and modification history
Showing the latest 51 of 51 loaded transactions. Negative values are deobligations.
| Date | Modification | Obligation change | Description |
|---|---|---|---|
| Jun 10, 2026 | A00050 | $3.2M | CODE 430B - INCENTIVE FEE PAYOUT ON ALL CLINS |
| Aug 5, 2025 | A00049 | $0 | C460C MODIFICATION TO PROVIDE AN EXCEPTION TO THE DELIVERY DATE FOR A WORK ITEM. |
| Jul 28, 2025 | A00048 | $0 | C460C MODIFICATION TO ALLOW GROWTH TO ORIGINAL WORK PACKAGE AND GRANT EXCEPTION TO DELIVERY DATE FOR FOUR WORK ITEMS. |
| Jul 14, 2025 | A00047 | $17.0K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS, EXTEND PERIOD OF PERFORMANCE, AND DEOBLIGATE FUNDS FROM THE LEVEL OF EFFORT POOL. |
| Jul 8, 2025 | A00046 | $22.0K | C460C MODIFICATION TO INCORPORATE REPAIRS FROM ORIGINAL WORK PACKAGE AND TO REMOVE MAINTENANCE FROM ORIGINAL WORK PACKAGE. |
| Jul 2, 2025 | A00045 | $88.6K | C460C MODIFICATION FOR ADDITIONAL REPAIRS TO THE WORK PACKAGE. |
| Jun 26, 2025 | A00044 | $249.9K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS AND EXTEND THE PERIOD OF PERFORMANCE OF THE AVAILABILITY. |
| Jun 24, 2025 | A00043 | $28.4K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS AND MAINTENANCE. |
| Jun 18, 2025 | A00042 | $46.7K | C460C MODIFICATION TO INCORPORATE REPAIRS/MAINTENANCE TO ORIGINAL WORK DESCRIPTION AND REMOVE REPAIRS. |
| Jun 9, 2025 | A00041 | $-112.9K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS AND REMOVE REPAIRS/MAINTENANCE TO ORIGINAL WORK DESCRIPTION. |
| Jun 3, 2025 | A00040 | $312.4K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS AND REMOVE REPAIRS/MAINTENANCE TO ORIGINAL WORK DESCRIPTION. |
| May 23, 2025 | A00039 | $-20.2K | C460C MODIFICATION TO REMOVE REPAIRS/MAINTENANCE TO ORIGINAL WORK DESCRIPTION AND INCORPORATE ADDITIONAL REPAIRS. |
| May 16, 2025 | A00038 | $69.8K | C460C MODIFICATION TO INCORPORATE ADDITIONAL WORK NOT INCLUDED IN ORIGINAL WORK PACKAGE AND REMOVE REPAIR/MAINTENANCE FROM ORIGINAL PACKAGE. |
| May 7, 2025 | A00037 | $2.1K | C460C MODIFICATION TO REMOVE REPAIRS/MAINTENANCE TO ORIGINAL WORK DESCRIPTION AND ADD REPAIRS NOT IN ORIGINAL WORK PACKAGE. |
| Apr 29, 2025 | A00036 | $-27.2K | C460C- MODIFICATION TO REALIGN FUNDS AND RETURN USED FUNDS. |
| Apr 24, 2025 | A00035 | $-473.7K | C460C MODIFICATION TO DEOBLIGATE FUNDS, REMOVE REPAIRS/MAINTENANCE TO ORIGINAL WORK DESCRIPTION AND INCORPORATE ADDITIONAL REPAIRS. |
| Apr 17, 2025 | A00034 | $-14.1K | C460C MODIFICATION TO REMOVE REPAIRS/MAINTENANCE TO ORIGINAL WORK DESCRIPTION AND INCORPORATE ADDITIONAL REPAIRS. |
| Apr 10, 2025 | A00033 | $-298.4K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE. |
| Apr 4, 2025 | A00032 | $990 | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE. |
| Mar 28, 2025 | A00031 | $638.7K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE. |
| Mar 27, 2025 | A00030 | $165.4K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE AND REMOVE REPAIRS TO ORIGINAL WORK DESCRIPTION. |
| Mar 25, 2025 | A00029 | $-819.6K | C460C DEOBLIGATING FUND FROM ORIGINAL WORK PACKAGE. |
| Mar 19, 2025 | A00028 | $110.6K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE AND REMOVE REPAIRS/MAINTENANCE FROM ORIGINAL PACKAGE. |
| Mar 14, 2025 | A00027 | $125.5K | C460C MODIFICATION TO INCORPORATE REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE, REMOVE REPAIRS/MAINTENANCE AND ADD REPAIRS TO ORIGINAL WORK PACKAGE. |
| Mar 5, 2025 | A00026 | $658.6K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS TO INITIAL WORK PACKAGE AND ADDITIONAL REPAIRS ON INCLUDED IN INITIAL WORK PACKAGE. |
| Feb 27, 2025 | A00025 | $3.6M | C460C MODIFICATION TO INCREASE THE LOE POOL AND INCORPORATE ADDITIONAL REPAIRS TO INITIAL WORK PACKAGE. |
| Feb 24, 2025 | A00024 | $219.0K | CODE 460C-USS THEODORE ROOSEVELT (CVN-71) PIA MODIFICATION TO INCORPORATE GROWTH WORK AND DESCOPE WORK FOR HISM-CVN72-24-CN01 |
| Feb 13, 2025 | A00023 | $29.2K | C460C MODIFICATION TO REMOVE REPAIRS OR MAINTENANCE TO INITIAL WORK PACKAGE, AND INCORPORATE ADDITIONAL REPAIRS. |
| Feb 6, 2025 | A00022 | $-179.2K | C460C MODIFICATION TO REMOVE REPAIRS OR MAINTENANCE TO ORIGINAL WORK DESCRIPTION. |
| Jan 30, 2025 | A00021 | $444.3K | C460C MODIFICATION TO INCORPORATE NEW WORK NOT IN ORIGINAL WORK PACKAGE AND REMOVE REPAIRS/MAINTENANCE FROM ORIGINAL WORK PACKAGE. |
| Jan 23, 2025 | A00020 | $328.6K | C460C MODIFICATION TO INCORPORATE NEW WORK NOT IN ORIGINAL WORK PACKAGE AND TO REMOVE REPAIRS/MAINTENANCE FROM ORIGINAL WORK PACKAGE. |
| Jan 17, 2025 | A00019 | $1.6M | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE, FUND ADDITIONAL REPAIRS, AND REALIGN FUNDS. |
| Jan 7, 2025 | A00018 | $246.4K | C460C MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE AND REMOVE REPAIRS TO ORIGINAL WORK DESCRIPTION. |
| Dec 20, 2024 | A00017 | $176.8K | C460C- MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN ORIGINAL WORK PACKAGE AND TO REMOVE REPAIRS/MAINTENANCE TO ORIGINAL WORK PACKAGE. |
| Dec 12, 2024 | A00016 | $-299.1K | C460C MODIFICATION TO REMOVE REPAIRS FROM ORIGINAL WORK PACKAGE AND TO ADD ADDITIONAL REPAIRS/MAINTENANCE NOT IN ORIGINAL WORK PACKAGE. |
| Dec 9, 2024 | A00015 | $669.9K | C460C - MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE AND ADDING ADDITIONAL FUNDS TO THE CONTRACT TO CONTINUE PERFORMANCE. |
| Dec 4, 2024 | A00014 | $-339.5K | C460C MODIFICATION TO REMOVE REPAIRS OR MAINTENANCE TO THE ORIGINAL WORK PACKAGE AND REALIGNMENT OF FUNDS. |
| Nov 25, 2024 | A00013 | $-214.2K | C460C MODIFICATION TO REMOVE REPAIRS OR MAINTENANCE TO ORIGINAL WORK DESCRIPTION AND ADD FUNDS DUE TO CHANGES IN PERIOD OF PERFORMANCE. |
| Nov 18, 2024 | A00012 | $-75.1K | C460C- MODIFICATION TO REMOVE REPAIRS/MAINTENANCE TO ORIGINAL WORK DESCRIPTION AND TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE. |
| Nov 8, 2024 | A00011 | $0 | C460C MODIFICATION TO UPDATE LINE OF ACCOUNTING DATA AND ISSUE APPROVAL FOR EARLY START OF WORK ITEM. |
| Oct 31, 2024 | A00010 | $1.3M | C460C MODIFICATION TO REMOVE REPAIRS OR MAINTENANCE TO ORIGINAL WORK DESCRIPTION AND INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE. |
| Oct 25, 2024 | A00009 | $1.9M | C460C MODIFICATION TO INCORPORATE REPAIRS TO ADDITIONAL WORK DESCRIPTION AND ADD A LOE POOL |
| Oct 15, 2024 | A00008 | $2.0M | C460C MODIFICATION TO INCORPORATE WORK ITEMS IN TO THE PIA EXECUTION. |
| Oct 3, 2024 | A00007 | $4.4M | CODE 460C - USS THEODORE ROOSEVELT (CVN-71) PIA INCORPORATE WORK ITEMS INTO THE PIA EXECUTION. |
| Sep 26, 2024 | A00006 | $8.9M | CODE 460C - USS THEODORE ROOSEVELT (CVN-71) PIA INCORPORATE SUPPLEMENTAL WORK PACKAGE |
| Sep 16, 2024 | A00005 | $12.2K | CODE 460C - MODIFICATION TO ADD FUNDS TO OBLIGATE MATERIAL THAT WAS NOT PROVIDED IN ORIGINAL QUOTE |
| Sep 6, 2024 | A00004 | $0 | CODE 460C, MODIFICATION TO REALIGN FUNDS |
| Aug 23, 2024 | A00003 | $3.3M | C460C - MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE AS WELL AS PROCUREMENT OF MATERIAL REQUIRED TO SUPPORT SHIP REPAIR AND MAINTENANCE. |
| Aug 16, 2024 | A00002 | $17.9M | MODIFICATION TO INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE. |
| Jul 23, 2024 | A00001 | $1.2M | CODE 460C, PROCUREMENT OF MATERIAL REQUIRED TO SUPPORT SHIP REPAIR AND MAINTENANCE, AND INCORPORATE ADDITIONAL REPAIRS NOT INCLUDED IN INITIAL WORK PACKAGE. THIS MODIFICATION ALSO INCORPORATES THE CHANGE IN THE AVAILABILITY SCHEDULE. |
| Jun 13, 2024 | 0 | $10.5M | CODE 460C USS THEODORE ROOSEVELT (CVN-71) FY25 PIA HISM-CVN71-24-CN01 |
Research next steps
- Verify whether remaining options may extend performance beyond the current end date.
- Confirm the ordering vehicle and your eligibility or a qualified teaming route.
- Review the award scope and buyer evidence before making a bid/no-bid decision.