Federal contract award

N5523625F5002

C460A_DELIVERY ORDER AWARD FOR THE USS FITZGERALD (DDG-62)

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeSOUTHWEST REGIONAL MAINT CENTER
NAICS336611 — Ship Building and Repairing
PSCJ999 — Non-nuclear Ship Repair (West) Ship repair (including overhauls and conversions) performed on. non-nuclear propelled and nonpropelled ships west of the 108th meridian
Parent award / vehicleN0002422D4472
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$827.1K
Current contract value$827.1K
Potential contract value / ceiling$827.1K
Start dateDec 2, 2024
Current end dateJan 12, 2025
Potential end dateMay 12, 2025
Latest award activityApr 25, 2025
Source loadedAug 15, 2026

Funding and modification history

Showing the latest 11 of 11 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Apr 25, 2025A00010$-84C460A_ REMOVE REPAIRS FROM THE ORIGINAL WORK SPECIFICATION PACKAGE FOR USS FITZGERALD DDG-62
Feb 7, 2025A00009$4.5KC460A, MODIFICATION INCORPORATING REPAIRS THAT WERE DISCOVERED DURING THE SHIP'S MAINTENANCE AVAILABILITY AND AN EXTENSION TO THE DELIVERY DATE.
Feb 5, 2025A00008$-71.1KC460A, MODIFICATION TO DESCOPE REQUIREMENTS AND DEOBLIGATE REMAINING LEVEL OF EFFORT FUNDING THAT WAS NOT EXPENDED DURING THE SHIP'S MAINTENANCE AVAILABILITY.
Jan 15, 2025A00007$61.5KC460A_MODIFICATION TO INCORPORATE ADDITIONAL WORK AND DESCOPE WORK FROM THE PACKAGE.
Jan 6, 2025A00006$78.8KC460A, MODIFICATION TO INCORPORATE REPAIRS THAT WERE DISCOVERED DURING THE SHIP'S MAINTENANCE AVAILABILITY.
Dec 30, 2024A00005$102C460A, MODIFICATION TO INCORPORATE REPAIRS THAT WERE DISCOVERED DURING THE SHIP'S MAINTENANCE AVAILABILITY.
Dec 27, 2024A00004$102C460A, MODIFICATION TO INCORPORATE REPAIRS THAT WERE DISCOVERED DURING THE SHIPS MAINTENANCE AVAILABILITY.
Dec 18, 2024A00003$-1.3KC460A, MODIFICATION TO INCORPORATE DESCOPED WORK REQUIREMENTS THAT WERE DISCOVERED DURING THE SHIP'S MAINTENANCE AVAILABILITY.
Dec 11, 2024A00002$-265C460A, MODIFICATION TO INCORPORATE DESCOPE WORK THAT WAS FOUND DURING THE SHIP'S MAINTENANCE AVAILABILITY.
Nov 21, 2024A00001$102.7KC460A, MODIFICATION TO INCORPORATE REPAIRS THAT WERE DISCOVERED DURING THE SHIP'S MAINTENANCE AVAILABILITY.
Oct 22, 20240$652.3KC460A_DELIVERY ORDER AWARD FOR THE USS FITZGERALD (DDG-62)

Research next steps

  1. Verify whether remaining options may extend performance beyond the current end date.
  2. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  3. Review the award scope and buyer evidence before making a bid/no-bid decision.