Federal contract award

N5523625F5041

C460A_INCORPORATE REPAIRS FROM THE ORIGINAL WORK SPECIFICATION PACKAGE FOR USS MUSTIN

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeSOUTHWEST REGIONAL MAINT CENTER
NAICS336611 — Ship Building and Repairing
PSCJ999 — Non-nuclear Ship Repair (West) Ship repair (including overhauls and conversions) performed on. non-nuclear propelled and nonpropelled ships west of the 108th meridian
Parent award / vehicleN0002422D4461
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.1M
Current contract value$1.1M
Potential contract value / ceiling$1.1M
Start dateSep 3, 2025
Current end dateNov 2, 2025
Potential end dateNov 2, 2025
Latest award activityNov 25, 2025
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 6 of 6 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Nov 25, 2025A00005$-23.8KC460A_REMOVE REPAIRS FROM THE ORIGINAL WORK SPECIFICATION PACKAGE AND INCORPORATE DEOBLIGATION OF FUNDS FOR LEVEL OF EFFORT FROM ORIGINAL AWARD TOTAL FOR USS MUSTIN.
Nov 6, 2025A00004$20.6KC460A_ INCORPORATE ADDITIONAL REPAIRS TO THE WORK SPECIFICATION PACKAGE AND REMOVE REPAIRS FROM THE WORK SPECIFICATION PACKAGE FOR THE USS MUSTIN (DDG-89).
Oct 28, 2025A00003$-678C460A: TO FULLY FUND AND IMPLEMENT GROWTH AND DESCOPE WORK FOR THE USS MUSTIN (DDG-89) FY25 CMAV S002.
Oct 9, 2025A00002$0C460A_INCORPORATE ADMINISTRATIVE CHANGE TO DELIVERY DATE FOR USS MUSTIN DDG-89 FY25 S002
Aug 21, 2025A00001$0C460A - TO INCORPORATE EARLY START DATE FOR WORK ITEMS FOR USS MUSTIN
Aug 4, 20250$1.1MC460A_INCORPORATE REPAIRS FROM THE ORIGINAL WORK SPECIFICATION PACKAGE FOR USS MUSTIN

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.