Federal contract award

N5523626F5004

C460_INCORPORATE REPAIRS FROM THE ORIGINAL WORK SPECIFICATION PACKAGE FOR USS MUSTIN

Research the contractorView USAspending sourceSave to my pursuit research

Award details

Obligations, current value and potential value describe different measures; they are never added together.

FieldReported value
AgencyDepartment of Defense
OfficeSOUTHWEST REGIONAL MAINT CENTER
NAICS336611 — Ship Building and Repairing
PSCJ999 — Non-nuclear Ship Repair (West) Ship repair (including overhauls and conversions) performed on. non-nuclear propelled and nonpropelled ships west of the 108th meridian
Parent award / vehicleN0002422D4458
Set-asideNot reported
Pricing typeFIRM FIXED PRICE
Obligations$1.1M
Current contract value$1.1M
Potential contract value / ceiling$1.1M
Start dateDec 22, 2025
Current end dateFeb 23, 2026
Potential end dateFeb 23, 2026
Latest award activityMar 2, 2026
Source loadedSep 19, 2026

Funding and modification history

Showing the latest 12 of 12 loaded transactions. Negative values are deobligations.

DateModificationObligation changeDescription
Mar 2, 2026A00011$-32.3KC460A_INCORPORATE DEOBLIGATION OF FUNDS FOR LEVEL OF EFFORT FROM ORIGINAL AWARD FOR USS MUSTIN (DDG-89).
Feb 18, 2026A00010$15.3KC460A_ TO FULLY FUND AND INCORPORATE CAUSED DELAY AND DISRUPTION ON THE USS MUSTIN (DDG-89).
Feb 6, 2026A00009$112.0KC460A_FULLY INCORPORATE AND FUND GROWTH WORK IN SUPPORT USS MUSTIN (DDG-89) FY26 S001
Jan 30, 2026A00008$161.8KC460A_ INCORPORATE AND FULLY FUND GROWTH WORK IN SUPPORT USS MUSTIN (DDG-89) FY26 S001.
Jan 29, 2026A00007$4.5KC460A_ INCORPORATE AND FULLY FUND NEW GROWTH WORK IN SUPPORT OF USS MUSTIN (DDG-89) FY26 S001
Jan 21, 2026A00006$79.7KC460A_INCORPORATE AND FULLY FUND GROWTH WORK IN SUPPORT OF USS MUSTIN (DDG-89) FY26 S001
Jan 15, 2026A00005$29.2KC460A_INCORPORATE AND FULLY FUND GROWTH WORK IN SUPPORT USS MUSTIN (DDG-89) FY26 S001
Jan 6, 2026A00004$54.4KC460A_ INCORPORATE AND FULLY FUND NEW WORK IN SUPPORT USS MUSTIN FY26 S001
Jan 2, 2026A00003$35.8KC460A_INCORPORATE AND FULLY FUND SUPPLEMENTAL WORK TO SUPPORT USS MUSTIN (DDG-89) FY26 S001.
Dec 22, 2025A00002$0C460A_INCORPORATE ADMINISTRATIVE CHANGE TO DODAAC FOR USS MUSTIN (DDG-89) FY26 S001
Dec 9, 2025A00001$0C460A_TO INCORPORATE ADMINISTRATIVE CHANGE TO PERIOD OF PERFORMANCE
Dec 4, 20250$659.7KC460_INCORPORATE REPAIRS FROM THE ORIGINAL WORK SPECIFICATION PACKAGE FOR USS MUSTIN

Research next steps

  1. Confirm the ordering vehicle and your eligibility or a qualified teaming route.
  2. Review the award scope and buyer evidence before making a bid/no-bid decision.